                                   UNITED STATES DEPARTMENT OF EDUCATION

                                                         OFFICE OF INSPECTOR GENERAL

                    

                                                                                                                                               

                                                                                                                     AUDIT SERVICES

                                                             June 1, 2010

                                                                      

FINAL ALERT MEMORANDUM



TO:                  Danny Harris

                     Chief Information Officer

                     Office of the Chief Information Officer

                     

                     Thomas Skelly

                     Acting Chief Financial Officer

                     Office of the Chief Financial Officer



FROM:                Keith West /s/

                     Assistant Inspector General for Audit

                     

SUBJECT:             Desktop Services Pricing Under the EDUCATE Contract

                     Control Number ED-OIG/L19K0004



While responding to allegations received by the Office of Inspector General’s (OIG) Hotline

regarding the U.S. Department of Education’s (Department) management of the Education

Department Utility for Communications, Applications, and Technology Environment

(EDUCATE) contract, we became aware that the Department may not have effectively assessed

the reasonableness of the EDUCATE contractor’s proposed prices for desktop services over the

life of the contract. Specifically, the Department may not have effectively:



      1. Validated aspects of the Independent Government Cost Estimate (IGCE) pertaining to

           desktop services prices;

      2. Performed market research regarding desktop services costs; and

      3. Resolved potential weaknesses identified in the contractor’s proposed pricing for desktop

           services.

           

As a result, the Department may be paying the EDUCATE contractor unreasonable prices for

these services. The purpose of this alert memorandum is to bring our concerns to your attention

in order to expedite corrective action.



Contract Background



Under the EDUCATE contract, the Department migrated from a Government-Owned

Contractor-Operated Information Technology (IT) environment, to a Contractor-Owned

Contractor-Operated (COCO) IT environment. This required the contractor to provide the total

IT platform and infrastructure to support Department employees in meeting the Department’s


                Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104


The Department of Education’s mission is to promote student achievement and preparation for global competitiveness by fostering educational

                                                    excellence and ensuring equal access.

Final Alert Memorandum

ED-OIG/L19K0004                                                                                                                   Page 2 of 5


mission. The contract was awarded in September 2007 as a 10-year, performance-based,

indefinite delivery/indefinite quantity contract with fixed unit prices.



The contracted services are performed under eight operational areas known as contract line item

numbers (CLIN). The CLINs consist of desktop, helpdesk support, systems/data center, e-mail,

network, disaster recovery, printer, and other special services. Desktop services, identified as

CLIN 1 in the contract, includes asset inventories and management, hardware refreshes based on

a 4-year life cycle, desktop engineering, image control and maintenance, ticketing management,

install moves, adds, changes, and associated reporting.



The Department estimated the costs of the EDUCATE strategy by developing an IGCE by CLIN

and conducting market research. The contractor’s proposed pricing was evaluated by a team of

Department officials known as the Price Evaluation Panel (PEP). The OIG also evaluated the

contractor’s proposed prices during its performance of pre-award work requested by Contracts

                                                         1

and Acquisition Management (CAM).

                                 



IGCE Validation 



During this review, we became aware that the contractor’s proposed price for desktop services

over the 10-year life of the contract was                                                                                           .

Specifically, the contractor’s proposed price for desktop services totaled
                                                                                    .



The Department awarded a task order to an independent contractor to review the Department’s

existing contracts and statements of work likely to be a part of EDUCATE’s scope and compare

their cost to the IGCE. However, the contractor reported it was unable to validate the IGCE’s

cost justifications because it did not have access to relevant business cases it considered

necessary to support it. In addition, the contractor’s report stated the Fiscal Year 2007

acquisition plan’s cost for desktop services validated as belonging in the EDUCATE scope

(baseline) was $6.2 million (37 percent) less than the IGCE. To address this and other variances,

the report suggested options that included reducing the IGCE or reducing the EDUCATE scope.

However, the contractor’s report did not include a variance analysis of the cost discrepancies

between the baseline and IGCE costs. As a result, the information offered limited value to the

Department.



Officials from CAM and other participants on the EDUCATE acquisition team were unable to

provide significant detail on the IGCE. The Contract Specialist stated that revisions were made

to the initial IGCE because the cost estimates were too high. The Director of Operations and

Maintenance Services of the Office of the Chief Information Officer (OCIO) confirmed the


                                             

1

 The scope of OIG’s evaluation was limited to the determination of whether the contractor’s proposed pricing was in line with comparable

contracts, sales pricing, and direct labor rates. In conducting the evaluation, OIG was not engaged to express an opinion on the contractor’s

proposal and therefore did not. OIG did provide information regarding variances in the contractor’s desktop services pricing and limitations in its

supporting data for proposed pricing to assist CAM with the negotiation of price, terms, and conditions of the proposal. The scope of OIG’s

evaluation did not include a review of the IGCE.   






                 Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104



                                                                         


                                                                         

Final Alert Memorandum

ED-OIG/L19K0004                                                                                Page 3 of 5


Contract Specialist’s statement that there were multiple revisions made to the IGCE. However,

he indicated that he was not engaged in its development and identified another OCIO official as

the appropriate point of contact for that area, but the OCIO official also indicated that he did not

participate in the IGCE development. A former Deputy Chief Information Officer stated that he

had some involvement in the development of the IGCE. However, he did not recall specific

information.



Market Research Limitations



The independent contractor also conducted market research under the task order cited above.

However, the market research presented in its report was limited to the identification of the scope

of services for seven other Federal agencies that acquired managed services or outsourced

aspects of IT services and an estimate of related per user cost. The estimated per user costs were

reported as an aggregate total for the scope of services provided under each contract. We found

the scope of each acquisition differed from the EDUCATE scope, therefore the information

likely offered limited value to the Department. In addition, the independent contractor did not

make recommendations or draw conclusions in its report based on the market research presented.

Participants of the EDUCATE acquisition team were unable to provide significant details

regarding the market research conducted by the Department.



Potential Weaknesses in Desktop Services Pricing 



The Department’s PEP used the IGCE to evaluate the EDUCATE contractor’s proposed prices

over the 10-year life of the contract and followed the applicable criteria established in the

Request for Proposal (RFP). The RFP stated that the Government would conduct evaluations of

(a) proposed prices to determine if they were valid, realistic, and consistent with the technical

proposal and cost model; and (b) proposed unit prices and supporting data to verify that they

were reasonable, realistic, balanced, and consistent with the Performance Work Statement.









The OIG also evaluated the EDUCATE contractor’s proposed prices during its performance of

pre-award work requested by CAM to assist with the negotiation of price, terms, and conditions

of the proposal.


           Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104



                                                    


                                                    

Final Alert Memorandum

ED-OIG/L19K0004                                                                                                               Page 4 of 5





                                                                       We requested similar information during this

review; however, the Department could not provide documentation outlining the underlying

support for these costs. A Department official indicated that the Department had previously

requested this information, but the EDUCATE contractor refused to provide this data and was

not contractually required to do so.



During the course of our review, we attempted to assess the reasonableness of certain per unit

costs charged under desktop services.



                                                                                                                             However,

we noted that at the time of our review, a comparable unit could be purchased for $1,765.35.

Although the Department furnished the equipment it already owned to the contractor, such as

laptops and desktops, the contractor proceeded to bill the Department for the full monthly per

unit equipment costs.
                      it would appear the Department was being billed for its own equipment up until

the time of replacement.



In response to our inquiries regarding the overall reasonableness of the above costs, a CAM

official indicated that the desktop services costs included items beyond the hardware profile,

such as desk-side support including parts and labor associated with equipment repairs. The

official also noted that the commercial unit price was not specific to hardware and reflected the

commercial price for providing the service, to include labor. Finally, the official noted that

CAM had reviewed proposed contract pricing to determine price reasonableness that included

comparisons at the CLIN and total price levels and determined that no proposal was lowest

across the board on all CLINs.





The Federal Acquisition Regulation (FAR) 15-404-1(g), Unbalanced Pricing, states



        (1) Unbalanced pricing may increase performance risk and could result in payment of

           unreasonably high prices. Unbalanced pricing exists when, despite an acceptable total

           evaluated price, the price of one or more contract line items is significantly over or

           understated as indicated by the application of cost or price analysis techniques…

        (2) All offers with separately priced line items or subline items shall be analyzed to

           determine if the prices are unbalanced. If cost or price analysis techniques indicate that

           an offer is unbalanced, the contracting officer shall—

           


                                           

2

 The Principal/Mobile package included a laptop (80GB hard drive), battery, docking station, keyboard, mouse, monitor, desk phone, and roller

case.


                Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104



                                                                      


                                                                      

Final Alert Memorandum

ED-OIG/L19K0004                                                                                Page 5 of 5


                   (i) Consider the risks to the Government associated with the unbalanced

                       pricing in determining the competitive range and in making the source

                       selection decision; and

                   (ii) Consider whether award of the contract will result in paying unreasonably

                       high prices for contract performance.



Based on the information outlined in this memorandum, the EDUCATE contractor’s proposed

prices for desktop services may not be fair and reasonable. The Department did not appear to

take appropriate actions prior to awarding the contract to address concerns raised by the PEP and

OIG which may have indicated unbalanced pricing. The lack of effective IGCE and market

research processes as tools for price analysis may have limited the Department’s ability to

evaluate proposed desktop services pricing. As a result, the Department may be paying the

contractor unreasonable prices for desktop services over the life of the contract.



Recommendations



We recommend that the Chief Information Officer and Chief Financial Officer:



1.1  Instruct the CO to review the estimated costs for desktop services over the remaining life of

     the EDUCATE contract and consider re-negotiating pricing for the services before the next

     option year of the contract is exercised.

     

1.2 Ensure that in future acquisitions the Department’s IGCE and market research processes

     result in a meaningful contribution to the overall acquisition process.



Department Comments


A draft of this memorandum was provided to OCIO and the Office of the Chief Financial Officer

(OCFO) for comment. In its response to the draft alert memorandum, OCIO/OCFO concurred

with our recommendations and described planned corrective actions. The response is included in

its entirety as an attachment to this memorandum.


Corrective actions proposed (resolution phase) and implemented (closure phase) will be

monitored and tracked through the Department’s Audit Accountability and Resolution Tracking

System.


For further information, please contact Michele Weaver-Dugan, Director, Operations Internal

Audit team, at (202) 245-6941.


Attachment




           Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104



                                                    


                                                    

                                                                                                      Attachment



                               UNITED STATES DEPARTMENT OF EDUCATION


                                                                  

                                                                  

                

MEMORANDUM




DATE:            April 27, 2010




TO:              Keith West

                 Assistant Inspector General for Audit



FROM:            Thomas P. Skelly

                 Delegated to Perform Functions of the Chief Financial Officer

                 Office of the Chief Financial Officer



                 Danny A. Harris

                 Chief Information Officer

                 Office of the Chief Information Officer




SUBJECT:         Response to Draft Alert Memo Entitled Desktop Services Pricing Under the

                 EDUCATE Contract (Control Number ED-OIG/L-19K0004)



The Department has received and reviewed the subject Alert Memo, dated April 12, 2010, and

appreciates the opportunity to respond to the alert.


The Department’s comments regarding specific recommendations are as follows:


Recommendation 1.1: Instruct the CO to review the estimated costs for desktop services over

the remaining life of the EDUCATE contract and consider re-negotiating pricing for the services

before the next option year of the contract is exercised.


The Department concurs with this recommendation. The Contracting Officer (CO) will review

the CLIN 0001 Desktop Services prices prior to exercising option periods. Should the review of

the prices for the upcoming option period find the prices unfair and unreasonable the CO will

pursue re-negotiating the prices for desktop services with the contractor.


As mentioned in the Alert Memo, the EDUCATE Contractor is required to provide all hardware

necessary to fulfilling the requirements set forth under Contract Line Item Number (CLIN) 0001

(Desktop Services) of the Performance Work Statement (PWS). However, the Department would


             Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104      


                           400 Maryland Avenue, SW, Washington, D.C. 20202-4300

      Our M ission is to prom ote student achievem ent and preparation for global com petitiveness by fostering

                                 educational excellence and ensuring equal access



                                                    




like to emphasize that the PWS further requires the EDUCATE Contractor to supply the labor in

order to satisfy the following requirements:


1. A single point of contact for “How to” support calls

2. Level 2 and Level 3 desk side support

3. All maintenance, operational, functionality, and software support for the Education

    Performance Appraisal System (EDPAS)

4. Change/configuration management requests

5. Inventory management

6. Installation and patch management signature files

7. License management

8. Equipment and software warranties

9. Equipment and software maintenance agreements

10. Electronic alert notifications







                                                               It should be further noted that the

contract has an established 15% minimum and maximum “seat” ordering threshold of 4,500 and

6,100 based on the solicited number of 5,300 seats.




                                        In order to ensure that the proposed and agreed-to pricing

accounts for market changes that could not be predicted at the time of award, the contract further

contains an economic price adjustment clause that applies to all hardware and software costs

during Option Periods V-IX.


The Department would like to further emphasize that, regardless of the acquisition, proposed

costs and associated prices are highly dependent upon the proposed solution that are unique to

each offer and are independent of the assumptions posed during the formulation of the


           Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104



                                                    


                                                    

                                                    




government’s cost estimate. This is especially the case as it relates to solutions that are

innovative and cutting edge, or offerors that are experienced within their respective industry.


Recommendation 1.2: Ensure that in future acquisitions the Department’s IGCE and market

research processes result in a meaningful contribution to the overall acquisition process.


The Department concurs with this recommendation. The Department will ensure that the

acquisition workforce is aware of the importance of the meaningful contribution to the overall

acquisition process of independent government cost estimates and market research. The

Department believes that the market research performed as part of the EDUCATE acquisition

process was meaningful. There were a limited number of agencies that operated under a seat

management model and the Department could not locate any agencies operating under a

contractor owned contractor operated computer network model. As a result, it was difficult to

compare the prices other agencies were paying for the services being acquired under the

EDUCATE contract.


Again, the Department appreciates the opportunity to respond to the associated

recommendations. We look forward to our continued relationship with your office and are

available to discuss this matter further if you feel necessary.
















           Source Selection Information in this memorandum is redacted. See FAR 2.101 and 3.104