Year 2000 Computing Challenge: FBI Needs to Complete Business Continuity Plans

Published by the Government Accountability Office on 1999-10-22.

Below is a raw (and likely hideous) rendition of the original report. (PDF)

                 United States General Accounting Office

GAO              Report to the Special Committee on the
                 Year 2000 Technology Problem, U.S.
                 Senate


October 1999
                 YEAR 2000
                 COMPUTING
                 CHALLENGE

                 FBI Needs to
                 Complete Business
                 Continuity Plans




GAO/AIMD-00-11
Contents



Letter                                                                                      3


Appendixes   Appendix I:  Briefing to the Special Committee on the Year
               2000 Technology Problem                                                     14
             Appendix II:   Objectives, Scope, and Methodology                             57
             Appendix III: Comments From the Department of Justice                         59




             Abbreviations

             BOP       Bureau of Prisons
             CIO       Chief Information Officer
             FBI       Federal Bureau of Investigation
             IT        information technology
             JMD/CSS   Justice Management Division/Computer Services Staff
             NCIC      National Crime Information Center
             OMB       Office of Management and Budget
             PMO       Program Management Office
             SSA       Social Security Administration




             Page 1                  GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Page 2   GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
United States General Accounting Office                                                 Accounting and Information
Washington, D.C. 20548                                                                       Management Division



                                    B-282155                                                                               Leter




                                    October 22, 1999

                                    The Honorable Robert F. Bennett
                                    Chairman
                                    The Honorable Christopher J. Dodd
                                    Vice Chairman
                                    Special Committee on the Year 2000 Technology Problem
                                    United States Senate

                                    The Federal Bureau of Investigation (FBI) relies on automated information
                                    systems to fulfill its mission to investigate violations of federal criminal
                                    law, protect the United States from foreign intelligence and terrorist
                                    activities, and provide assistance to federal, state, and local agencies. To
                                    prevent disruptions to systems caused by the Year 2000 problem, the FBI
                                    has taken action to renovate and test its mission-critical systems.
                                    Nevertheless, because core business processes may still be disrupted by
                                    Year 2000-induced failures in internal systems, business partners’ systems,
                                    or public infrastructure systems, it is necessary for the FBI to develop and
                                    test plans for the continuity of business operations. If done effectively, such
                                    plans can help mitigate the risks and mission impacts associated with
                                    unexpected internal and uncontrollable external system failures.

                                    At your request, we determined (1) the status of and plans for completing
                                    the FBI’s contingency planning for continuity of operations and
                                    (2) whether the FBI’s contingency planning efforts satisfy the key
                                    processes in our Year 2000 business continuity and contingency planning
                                    guide.1 This report summarizes the information presented at our August 19,
                                    1999, briefing to your office and provides examples of important business
                                    continuity planning steps that the FBI is not fulfilling. This report also
                                    includes the briefing slides that we presented to your office because they
                                    contain our findings on how well the FBI is satisfying business continuity
                                    planning steps. The briefing slides are presented in appendix I, and our
                                    objectives, scope, and methodology in appendix II. We requested
                                    comments on a draft of this report from the Attorney General or her
                                    designee. The Department of Justice provided comments. These comments
                                    along with our evaluation are summarized in the “Agency Comments and


                                    1
                                     Year 2000 Computing Crisis: Business Continuity and Contingency Planning (GAO/AIMD-
                                    10.1.19, August 1998).




                                    Page 3                      GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                   B-282155




                   Our Evaluation” section of this report and are reprinted and addressed in
                   detail in appendix III. We performed our work from March through August
                   1999 in accordance with generally accepted government auditing
                   standards.



Results in Brief   As of August 1999, the FBI reported that it has renovated, tested, and
                   certified as Year 2000 compliant all but 1of its 43 mission-critical systems
                   and has developed system-level contingency plans for all but 2 of the 43.
                   Also, the FBI has made some progress in its Year 2000 business continuity
                   planning, but this very important effort is running late. To ensure that there
                   will be sufficient time to develop, test, and finalize plans, we
                   recommended2 in earlier testimony that plans be developed by April 30,
                   1999, and tested, including addressing problems and retesting, if necessary,
                   by September 30, 1999, in order to allow agencies sufficient time to
                   evaluate whether the plans will provide the level of core business capability
                   needed and whether the plans can be implemented within a specified time
                   frame. However, the FBI had not yet developed division-level business
                   continuity plans or field office plans, and it did not expect to complete the
                   integration of the division plans until September 1999. Further, it had not
                   yet established a target date for completing field office plans or testing both
                   field-level and division-level plans. These delays left the FBI with little time
                   to complete the many planning tasks that remain and ensure that it is ready
                   to minimize the impact of possible Year 2000-induced system failures.

                   Moreover, the FBI also did not have many of the management controls and
                   processes needed to effectively guide its continuity planning effort through
                   the short time remaining before the Year 2000 deadline. For example, the
                   FBI had not (1) developed a high-level business continuity planning
                   strategy, (2) developed a master schedule and milestones, (3) defined all its
                   core business processes, (4) implemented a complete risk management
                   process for business continuity planning, (5) performed risk and impact
                   analyses of each core business process, (6) assessed the costs and benefits
                   of alternative continuity strategies, or (7) planned for the testing phase of
                   its business continuity planning effort. According to the senior Year 2000
                   official, the FBI had not implemented these controls and processes
                   because Justice’s guidance focuses on system-level contingency plans and
                   does not require business continuity planning. Further, the official stated

                   2
                   Year 2000 Computing Crisis: Readiness Improving, But Much Work Remains to Avoid Major
                   Disruptions (GAO/T-AIMD-99-50, January 20,1999).




                   Page 4                      GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
             B-282155




             that the FBI is inherently capable of ensuring continuity of operations
             because its agents in both headquarters and the field are well trained and
             prepared for responding to various emergency circumstances, of which
             potential Year 2000 system failure is just one.

             The need for a structured and defined approach to managing Year 2000
             programs, including business continuity planning, is widely accepted by
             both public and private sector organizations, and it is precisely why our
             Year 2000 guidance has been adopted by the Office of Management and
             Budget (OMB) as a federal standard. By not employing the management
             rigor and discipline specified in our Year 2000 business continuity planning
             guide, the FBI will not be able to ensure that it (1) properly focuses its
             planning effort on the agency’s most critical operations, (2) selects the best
             strategies to protect these operations, (3) has sufficient resources and staff
             dedicated to implementing continuity plans, and (4) can efficiently and
             effectively invoke its continuity plans, if necessary.

             To strengthen the FBI’s management of business continuity planning, we
             are recommending that Justice clarify its expectations for Year 2000
             business continuity planning for all of its bureaus and that the FBI establish
             and implement (1) a plan for developing and testing business continuity
             plans and (2) effective controls and structures for managing Year 2000
             business continuity planning. In commenting on a draft of this report,
             Justice disagreed with our conclusion that it has not required the
             development and emphasized the importance of business continuity
             planning. However, it also cited steps that it has recently taken to address
             our recommendations, including orally clarifying business continuity
             planning for some bureaus, developing a plan for the timely development
             and testing of headquarters and field office business continuity plans, and
             establishing controls and structures for managing business continuity
             planning. To fully implement all recommendations, Justice must build on
             these first steps to ensure that all bureaus complete business continuity
             plans, and that specifically cited plans and management controls for the
             FBI’s business continuity planning are effectively implemented.



Background   The FBI’s mission is to investigate violations of federal criminal law,
             protect the United States from foreign intelligence and terrorist activities,
             and provide leadership and law enforcement assistance to federal, state,
             local, and international agencies. The FBI supports its mission with 56 field
             offices, about 400 satellite offices, and 35 foreign legal attaches. In addition,




             Page 5                     GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
B-282155




classified systems link two computer centers−Washington, D.C. and
Clarksburg, West Virginia−and all FBI locations.

To carry out its mission, the FBI depends on information technology (IT)
systems that contain information on fugitives, wanted persons, stolen
vehicles, etc. and are used by both FBI staff and state and local law
enforcement agencies. For example, the FBI has recently implemented its
National Crime Information Center (NCIC) 2000 system, which is used by
law enforcement agencies in the United States, Puerto Rico, Mexico, and
Canada to share information about individuals, vehicles, and property
associated with criminal activity.

The FBI has been working to address the Year 2000 problem with its critical
IT systems. Under the leadership of a Year 2000 Senior Executive, the FBI
identified 43 mission-critical IT systems and hundreds of non-IT assets,
such as laboratory equipment and telephone and building systems, to be
renovated and tested before the Year 2000. All but one of these systems
have been renovated, tested, and certified as Year 2000 compliant. The FBI
has also developed system-level contingency plans for all but 2 of its 43
mission-critical systems.

Despite the FBI’s or any organization’s best efforts to remediate its mission-
critical systems; however, core business processes may still be disrupted
by Year 2000-induced failures and errors in internal systems, business
partners’ systems, or public infrastructure systems, such as power, water,
transportation, and telecommunications systems. Thus, it is necessary to
prepare plans for continuity of business operations to help mitigate the
risks and mission impacts associated with unexpected internal and
uncontrollable external system failures.

Our Year 2000 business continuity and contingency planning guidance
recommends that federal agencies follow a four-phased structured
approach to continuity and contingency planning, which is illustrated
below. OMB has adopted this guidance as a federal standard for business
continuity planning.

• Phase 1−Initiation . Establish a continuity work group and develop a
  high-level business continuity planning strategy. Develop a master
  schedule and milestones, and obtain executive support.
• Phase 2−Business impact analysis. Assess the potential impact of
  mission-critical system failures on the agency’s core business processes.
  Define Year 2000 failure scenarios, and perform risk and impact



Page 6                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                      B-282155




                        analyses of each core business process. Assess infrastructure risks, and
                        define the minimum acceptable levels of output for each core business
                        process.
                      • Phase 3−Contingency planning. Identify and document contingency
                        plans and implementation modes. Define triggers for activating
                        contingency plans, and establish business resumption teams for each
                        core business process.
                      • Phase 4−Testing. Validate the agency’s business continuity strategy.
                        Develop and document contingency test plans. Prepare and execute
                        tests. Update disaster recovery plans and procedures.



FBI’s Continuity of   To ensure that agencies have sufficient time to develop, test, and finalize
                      their plans, contingency and continuity plans should have been completed
Operations Planning   by April 30, 1999, and tested by September 30, 1999. However, the FBI has
Efforts Are Late      been running behind our recommended schedule for business continuity
                      planning, and its plans do not contain milestones for completing its
                      remaining tasks. As of August 1999, the FBI

                      • had not yet developed an integrated set of division-level business
                        continuity plans and did not expect this to be done until September
                        1999;
                      • had not yet established a milestone for the completion of field office
                        business continuity plans or instructed field offices on what the content
                        of their contingency plans should be; and
                      • had not yet established milestones for testing both field-level and
                        division-level continuity plans.

                      These delays, in part, are attributable to the FBI’s late start in undertaking
                      its business continuity planning effort. The agency did not initiate business
                      continuity planning until March 1999, did not instruct its field offices to
                      develop continuity plans until April 1999, and did not instruct divisions to
                      prepare continuity plans until May 1999. The Year 2000 Program
                      Management Office (PMO), in its Contingency Planning Guidebook for
                      Field Offices, stated that it will provide additional guidance to the field
                      offices on business continuity planning, including instructions for the
                      content of plans, in October 1999. According to FBI officials, the FBI
                      started late in business continuity planning because Justice’s guidance only
                      requires system-level contingency plans and does not address business
                      continuity planning. Our review of Justice’s Year 2000 guidance confirmed
                      this statement.




                      Page 7                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                         B-282155




FBI Lacks Key            The delays in the FBI’s development of business continuity plans have left
                         the agency with little time to properly test its plans and to update plans
Controls and Processes   based on the results of those tests. As a result, it is exceedingly important
Needed to Complete Its   for the FBI to have an effective set of management controls in place for
                         managing the remainder of its business continuity planning effort.
Continuity Planning      Nevertheless, the FBI does not have many of the key processes and
Effort                   controls necessary to reduce the risk of Year 2000 business disruptions
                         because, according to the FBI’s senior Year 2000 official, Justice’s guidance
                         focuses on system-level contingency plans and does not require business
                         continuity planning. Further, the official stated that continuity of
                         operations is embedded in the FBI’s normal daily operations, and its agents
                         in both headquarters and the field are well trained and prepared for
                         responding to various emergency circumstances, of which Year 2000
                         disruption is just one type.

                         However, the FBI does not have important management controls for
                         effectively managing Year 2000 business continuity planning, controls
                         which OMB has adopted as a federal standard and which public and private
                         sector organizations are employing. Without these controls, the FBI has
                         inadequate assurance that it will be able to effectively address potential
                         internal and external Year 2000-induced system failures.

                         The following are examples of our recommended business continuity
                         planning steps that, as of August 1999, the FBI had not fully satisfied.

                         • Develop a high-level strategy for business continuity planning. Our
                           guidance recommends that agencies develop and document a high-level
                           continuity planning strategy during the initiation phase to guide the
                           planning effort. It should include project structure, metrics and
                           reporting requirements, and cost and schedule estimates. Without a
                           planning strategy, agencies cannot ensure that they have sufficient
                           resources and staff dedicated to the contingency and continuity
                           planning effort.
                         • Develop a master schedule and milestones. Our guidance recommends
                           that agencies develop a master schedule, including milestones for the
                           delivery of interim and final products. These tools help agencies track
                           business continuity planning progress to ensure that important tasks are
                           completed according to defined requirements, and timely corrective
                           actions to address deviations from requirements are taken. While the
                           PMO directed the divisions to develop continuity plans by mid-August
                           and established early September as the milestone for integrating the




                         Page 8                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
B-282155




    division plans, it had not yet established a milestone for the completion
    of field office business continuity plans or established milestones for
    testing both field-level and division-level continuity plans.
•   Define all its core business processes. The business continuity planning
    process focuses on reducing the risk of Year 2000-induced business
    failures. Thus, it is essential for agencies to identify their core business
    processes and supporting mission-critical systems. Our guidance
    recommends that this be done during the initiation phase so that in the
    business impact phase agencies can examine business process
    composition, priorities, and dependencies and define the minimum
    acceptable level of outputs and services for each core process. In May
    1999, the PMO tasked its headquarters divisions to identify their core
    business processes and supporting mission-critical systems. As of July
    1999, only one of the five divisions we contacted had defined its core
    processes and supporting systems; the other four reported that they
    were in the process of doing so.
•   Implement a complete risk management process for continuity
    planning. Our guidance recommends that agencies implement a risk
    management and reporting process during the initiation phase of the
    business continuity planning project that includes identifying business
    continuity project risks, developing measures for tracking planning
    progress and determining plans’ quality, establishing reporting
    requirements, and assessing system renovation risks. The FBI had not
    identified project risks, developed measures, or established a reporting
    system for its business continuity planning project, although it had
    implemented a risk management process for its mission-critical
    systems.
•   Perform risk and impact analyses for each core business process. To
    help develop adequate contingency procedures, our guidance
    recommends that agencies determine the impact of internal and
    external information system failures and infrastructure services on each
    core business process. The PMO has directed both headquarters
    divisions and field offices to assess the impact of internal and external
    system failures on core functions and to use these analyses in their
    business continuity planning. One of the five divisions and two of the
    three field offices we contacted reported that they had not yet begun
    their impact analyses, although they stated that they plan to do so.
•   Assess the costs and benefits of alternative continuity strategies. To
    select the best contingency strategy for each core business process, our
    guidance recommends that agencies assess the costs and benefits of
    identified alternatives as a first step in the contingency planning phase.




Page 9                     GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                  B-282155




                    The FBI had not assessed the cost and benefits of alternative strategies,
                    and it has not instructed its divisions and field offices to do so.
                  • Plan for the testing phase of its business continuity planning effort.
                    Agencies need to test their continuity plans to evaluate whether they are
                    capable of providing the desired level of support to core business
                    processes and whether the plans can be implemented within a specified
                    period. To effectively prepare for such tests, our guidance recommends
                    that agencies develop and document test plans and establish teams and
                    acquire contingency resources. Our guidance also recommends that
                    agencies rehearse business resumption teams to ensure that each team
                    and team member is familiar with business resumption procedures and
                    their roles. The FBI had yet to undertake these important planning tasks
                    and, as discussed earlier, has yet to set milestones for completing its
                    testing efforts.



Conclusions       The FBI reports good progress in making its mission-critical systems Year
                  2000 compliant and in developing system-level contingency plans.
                  However, because Justice has not explicitly required and emphasized the
                  importance of business continuity plans, the FBI started late in undertaking
                  its business continuity planning effort, and it is now faced with a
                  compressed time frame for testing and finalizing its plans. Unless the FBI
                  moves swiftly to implement the management controls and processes it
                  lacks, it is unlikely to have effective business continuity plans in place by
                  the turn of the century, and it runs the serious risk of not being able to
                  sustain the minimal levels of service needed to meet its mission if
                  confronted with Year 2000 system failures.



Recommendations   We recommend that the Attorney General direct the Department of
                  Justice’s Year 2000 Program Office to clarify the department’s expectations
                  for Year 2000 business continuity planning for all Justice bureaus,
                  emphasizing the need for these plans and discussing OMB’s adoption of our
                  guidance as a federal standard. We also recommend that the Attorney
                  General direct the FBI Director to take the following actions:

                  • establish and implement a plan for the timely development and testing
                    of effective headquarters and field office Year 2000 business continuity
                    plans, including incremental milestones for completing all relevant key
                    processes in our guide associated with business impact analysis, plan
                    development, and plan testing, and



                  Page 10                  GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                      B-282155




                      • establish and implement effective controls and structures for managing
                        Year 2000 business continuity planning, including each of the relevant
                        key processes addressed in our Year 2000 contingency planning guide
                        and discussed in this report as not yet being satisfied.



Agency Comments and   In written comments on a draft of this report, Justice disagreed with our
                      conclusion that it has not required the development and emphasized the
Our Evaluation        importance of business continuity plans. To support its position, Justice
                      (1) cited Year 2000 guidance and information provided to its bureaus in
                      early 1998, (2) noted that three of its eight bureaus currently have plans in
                      place, and (3) stated that it provided OMB a departmentwide business
                      continuity and contingency plan on June 15, 1999.

                      We do not agree with Justice’s position for several reasons. First, guidance
                      cited by Justice does not address business continuity planning per se.
                      Justice’s guidance transmitted our Year 2000 guide and a description of the
                      Social Security Administration’s (SSA) business continuity planning efforts,
                      but did not direct the bureaus to develop and test business continuity
                      plans. Second, as stated in its response to our report, only three of eight
                      Justice bureaus have developed business continuity plans at this late date,
                      which further supports our conclusion. Third, Justice’s department-level
                      plan is not relevant to our conclusion about bureau-level planning,
                      direction and guidance. Moreover, in its comments Justice acknowledges
                      that it has concentrated on system-level contingency plans as opposed to
                      business continuity planning. To its credit, after receiving a draft of our
                      report, Justice held a meeting with selected bureaus that was attended by
                      us, in which it required and explained the importance of business
                      continuity plans; however, Justice provided no evidence that all bureaus
                      were subjected to this requirement.

                      Justice also stated that the FBI has developed a plan for the timely
                      development and testing of headquarters and field office business
                      continuity plans, and has established controls and structures for managing
                      business continuity planning. We are encouraged by the FBI’s first step in
                      responding to our recommendations. To fully implement our
                      recommendations, the FBI must effectively implement its plan, which
                      requires, among other things, that it define reporting requirements and
                      measures of interim progress and effectively act to address any deviations
                      from expectations. Further, the FBI must establish and effectively
                      implement all business continuity key processes, including effectively




                      Page 11                   GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
B-282155




monitoring their implementation so that any deviations are identified and
corrective action is taken immediately.

Justice’s written comments, along with our detailed response, are reprinted
in appendix III.

We are sending copies of this report to the Honorable Jacob J. Lew,
Director, Office of Management and Budget; the Honorable Janet Reno,
Attorney General; the Honorable Louis J. Freeh, Director of the Federal
Bureau of Investigation; and John Koskinen, Chairman of the President’s
Council on Year 2000 Conversion. Copies will be made available to others
upon request.

If you have any questions, please contact me or Deborah Davis, Assistant
Director, at (202) 512-6240 or by e-mail at hiter.aimd@gao.gov or
davisd.aimd@gao.gov. Other major contributors to this work were Cristina
Chaplain, Carl Higginbotham, and John Ortiz.




Randolph C. Hite
Associate Director, Governmentwide
 and Defense Information Systems




Page 12                  GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Page 13   GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Appendix I

Briefing to the Special Committee on the Year                                         Appenx
                                                                                           de
                                                                                            is




2000 Technology Problem                                                               Appendix
                                                                                             I




             Accounting and Information
             Management Division
         Briefing to Senate Special Committee
          on Year 2000 Technology Problem
                    FBI Year 2000
             Business Continuity Planning

                   August 19, 1999



     1




                    Page 14   GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
              Appendix I
              Briefing to the Special Committee on the Year
              2000 Technology Problem




    Overview


    •   Objectives, Scope, and Methodology
    •   Results in Brief
    •   Background
    •   Detailed Results
    •   Conclusions and Recommendations




2




              Page 15                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                 Appendix I
                 Briefing to the Special Committee on the Year
                 2000 Technology Problem




    Objectives, Scope, and
    Methodology
    The Committee asked us to determine

    • the status of and plans for completing the FBI’s
      contingency planning for continuity of business
      operations, and

    • whether the FBI’s contingency planning efforts
      satisfy the key processes in GAO’s contingency
      planning guide.*


    * Year 2000 Computing Crisis: Business Continuity and
      Contingency Planning (GAO/AIMD-10.1.19, August 1998)
3




                 Page 16                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                     Appendix I
                     Briefing to the Special Committee on the Year
                     2000 Technology Problem




          Objectives, Scope, and
          Methodology (cont’d)
GAO Business Continuity and Contingency Planning Guide
                  • Establish continuity work group and develop high-
     Initiation     level planning strategy and related guidance and
                    procedures. (8 key processes)

                  • Assess risk and impact of system failures on core
Business Impact
                    business processes and define minimum
   Analysis         acceptable levels of output. (5 key processes)

    Contingency   • Develop contingency plans and implementation
                    modes, assign resumption teams, and define
     Planning
                    implementation triggers. (5 key processes)

                  • Develop contingency test plans, execute tests, and
      Testing       validate business continuity strategy. (8 key
                    processes)
4




                     Page 17                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                  Appendix I
                  Briefing to the Special Committee on the Year
                  2000 Technology Problem




      Objectives, Scope, and
      Methodology (cont’d)
    • We reviewed completed and planned continuity of
      operations activities; discussed each such activity with
      FBI Year 2000 program office and contractor officials;
      obtained and reviewed documentation to corroborate
      officials’ statements; and compared plans and progress
      to GAO-advocated milestones.

    • We identified business continuity planning structures
      and controls (organization, standards, policies,
      guidance) in place and compared these to the key
      processes in GAO’s business continuity and
      contingency planning guide.

5




                  Page 18                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                  Appendix I
                  Briefing to the Special Committee on the Year
                  2000 Technology Problem




      Objectives, Scope, and
      Methodology (cont’d)
    • We discussed business continuity planning activities,
      structures, and controls with managers in five divisions
      (Criminal Investigative Division, Criminal Justice
      Information Services Division, Information Resources
      Division, Laboratory Division, and National Security
      Division) and three major field offices (New York, Los
      Angeles, and Washington).

    • We performed our work from March 1999 through
      August 1999 in accordance with generally accepted
      government auditing standards.


6




                  Page 19                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                Appendix I
                Briefing to the Special Committee on the Year
                2000 Technology Problem




    Results In Brief

    • Objective 1: FBI has made some progress in its
      business continuity planning but its division-level
      efforts are four months behind the GAO-
      recommended milestone, it has not established
      milestones for developing field office business
      continuity plans, and it has not developed
      milestones for testing both division and field
      office business continuity plans.

    • Objective 2: FBI has satisfied, partially satisfied,
      or plans to satisfy 16 of the 26 key processes in
      GAO’s contingency planning guidance, but has
      not satisfied the remaining 10 key processes.
7




                Page 20                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                Appendix I
                Briefing to the Special Committee on the Year
                2000 Technology Problem




    Background

    • The FBI’s mission is to

       • investigate violations of federal criminal law;

       • protect the United States from foreign
         intelligence and terrorist activities;

       • provide leadership and law enforcement
         assistance to federal, state, local, and
         international agencies.



8




                Page 21                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
               Appendix I
               Briefing to the Special Committee on the Year
               2000 Technology Problem




    Background (cont’d)

    • To carry out its mission, the FBI depends on
      information technology (IT) systems that contain
      information on fugitives, wanted persons, stolen
      vehicles, etc. State and local law enforcement
      agencies also depend on these systems.

    • Computer centers in Washington, DC and
      Clarksburg, WV support
       • 464 field offices & resident agencies, and
       • 35 foreign legal attaches.



9




               Page 22                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                 Appendix I
                 Briefing to the Special Committee on the Year
                 2000 Technology Problem




     Background (cont’d)

     • All FBI locations are linked by classified networks.

     • FBI has 43 mission-critical IT systems, and
       hundreds of mission-critical non-IT assets,
       including laboratory equipment and telephone and
       building systems.




10




                 Page 23                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                              Appendix I
                              Briefing to the Special Committee on the Year
                              2000 Technology Problem




             FBI Scope and Approach to Business
             Continuity Planning Has Evolved
                    •FBI Year 2000 Program Management Office
     1997           (PMO) focused on system-level contingency
                    plans for mission-critical applications.

                         •FBI Year 2000 business continuity planning was viewed
                         as part of National Security Division (NSD) Presidential
     March 1999
                         Decision Directive (PDD) 67 headquarters relocation
                         project.

                             •PMO initiated Year 2000 business continuity planning
            April 1999
                              for field offices.


                                     •PMO expanded Year 2000 business continuity
                  May 1999
                                     planning to headquarters divisions.
                                     •NSD PDD 67 effort viewed as part of Year 2000
                                     business continuity planning.

11




                              Page 24                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                Appendix I
                Briefing to the Special Committee on the Year
                2000 Technology Problem




     Objective 1: Planning Efforts Are Late
     And Key Milestones Are Missing

     • FBI plans to develop division-level business
       continuity plans by early September 1999, four
       months past the April 30, 1999, date
       recommended by GAO.

     • FBI has not established a date for developing field
       office business continuity plans.

     • FBI has not developed a plan or established
       milestones for testing division-level and field-level
       business continuity plans.


12




                Page 25                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                 Appendix I
                 Briefing to the Special Committee on the Year
                 2000 Technology Problem




     Objective 1: Planning Efforts Are Late
     And Key Milestones Are Missing
     • In May 1999, PMO directed the divisions to
       • define core business processes,
       • determine the impact of internal and external
         failures, and
       • prepare contingency plans and procedures for
         each process by mid-June 1999
     • PMO has revised the mid-June delivery date to mid-
       August.
     • Four of the five divisions we contacted reported that
       they expect to meet the August deadline and one
       plans to develop its plan in September/October.


13




                 Page 26                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                    Appendix I
                    Briefing to the Special Committee on the Year
                    2000 Technology Problem




      Objective 1: Planning Efforts Are Late
      And Key Milestones Are Missing
     • PMO provided guidance to the field offices in late April
       1999 that directed them to:
        • identify potential failure scenarios,
        • conduct risk assessments and impact analyses,
        • review existing contingency plans and use them as
          a base for developing new plans, and
        • develop continuity of operations plans.
     • Guidance to the field offices does not include
       milestones for completing development and testing of
       business continuity plans.
     • PMO plans to provide guidance on the contingency
       plan content and zero day procedures in October 1999.
     • All three field offices we contacted reported that they
       are currently developing their plans.
14




                    Page 27                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                  Appendix I
                  Briefing to the Special Committee on the Year
                  2000 Technology Problem




     Objective 1: Planning Efforts Are Late
     And Key Milestones Are Missing
     • FBI reports contingency plans developed for 41 of
       43 mission-critical IT systems. The last two plans
       will not be ready until September or October.

     • FBI and DOJ contractors plan to perform
       independent verification and validation (IV&V) of
       all system-level plans. Of the 41 plans submitted
       for IV&V, 40 have been approved, and one is
       being revised.




15




                  Page 28                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                   Appendix I
                   Briefing to the Special Committee on the Year
                   2000 Technology Problem




     Objective 2: Many GAO Key
     Processes Not Satisfied
                                     Number of Key Processes
     Phase                             Partially               Plans to          Not
                             Satisfied Satisfied               Satisfy         Satisfied

     Initiation                  2                3                2                1

     Business
                                 1                2                2                0
     Impact Analysis

     Contingency
                                 0                3                1                1
     Planning

     Testing                     0                0                0                8

     Total                       3                8                5               10

16




                   Page 29                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                    Appendix I
                    Briefing to the Special Committee on the Year
                    2000 Technology Problem




      Criteria For Satisfying Key
      Processes
     • Satisfied - key process developed and implemented;
       documentation provided
     • Partially satisfied - some components, but not all, of
       key processes developed and implemented;
       documentation provided
     • Plans to satisfy - key process not yet developed or
       implemented, but guidance directs divisions or field
       offices to develop
     • Not satisfied - key process not developed and not
       addressed in guidance




17




                    Page 30                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                            Appendix I
                            Briefing to the Special Committee on the Year
                            2000 Technology Problem




            Detailed Results: Initiation Phase


                   GAO Key Processes                                                 Results
     1. Establish business continuity work group                               Satisfied
     2. Develop high-level business continuity planning                        Not satisfied
        strategy
     3. Identify core business processes                                       Plans to satisfy
     4. Define roles and assign responsibilities                               Satisfied
     5. Develop master schedule and milestones                                 Partially satisfied
     6. Implement a risk management process and establish Partially satisfied
        reporting system
     7. Assess existing business continuity, contingency, and Partially satisfied
        disaster recovery plans
     8. Implement quality assurance reviews                   Plans to satisfy



18




                            Page 31                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                      Appendix I
                      Briefing to the Special Committee on the Year
                      2000 Technology Problem




          Detailed Results: Initiation Phase
          Key Process 1
     • A business continuity workgroup should be established
       that reports to executive management and includes
       representatives from major business units.

     • FBI established a task force consisting of division
       representatives to share business continuity information
       among divisions and agree on responsibilities for
       contingency plans that require action by more than one
       division. The PMO reports the group’s progress
       monthly to the FBI Deputy Director.

     • Satisfied

19




                      Page 32                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                       Appendix I
                       Briefing to the Special Committee on the Year
                       2000 Technology Problem




         Detailed Results: Initiation Phase
         Key Process 2
     • A high-level business continuity planning strategy
       should be developed and documented to guide the
       planning effort. It should include project structure,
       metrics and reporting requirements, and cost and
       schedule estimates.

     • FBI has not documented a high-level strategy to guide
       its overall business continuity effort.

     • Not Satisfied




20




                       Page 33                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                   Appendix I
                   Briefing to the Special Committee on the Year
                   2000 Technology Problem




       Detailed Results: Initiation Phase
       Key Process 3
     • Core business processes and the supporting
       mission-critical systems should be defined for each
       business area.

     • In May 1999, the PMO tasked headquarters
       divisions to identify their core business processes
       and supporting mission-critical systems. One of the
       divisions we contacted reported that it has defined
       its core processes and supporting mission-critical
       systems and the other four reported that they are in
       the process of doing so.

     • Plans to satisfy
21




                   Page 34                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                    Appendix I
                    Briefing to the Special Committee on the Year
                    2000 Technology Problem




         Detailed Results: Initiation Phase
         Key Process 4
     • Roles should be defined and responsibilities
       assigned for leading the planning effort, performing
       analyses, and designing business alternatives.

     • The PMO assigned responsibilities and roles for
       performing impact analyses and developing
       contingency plans to division Assistant Directors and
       to field office Special Agents- and Assistant
       Directors-in-Charge.

     • Satisfied


22




                    Page 35                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                     Appendix I
                     Briefing to the Special Committee on the Year
                     2000 Technology Problem




        Detailed Results: Initiation Phase
        Key Process 5
     • A master schedule, including milestones for the
       delivery of interim and final products, should be
       established.

     • PMO has not developed a master schedule.
       However, it directed headquarters divisions to
       develop continuity plans by mid-June 1999 originally,
       now by mid-August 1999, and has established early
       September as the milestone for integrating the
       divisions’ plans.

     • Partially satisfied

23




                     Page 36                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                       Appendix I
                       Briefing to the Special Committee on the Year
                       2000 Technology Problem




          Detailed Results: Initiation Phase
          Key Process 6
     • Organizations should implement a risk management and
       reporting process for the business continuity planning
       project that includes identifying project risks, developing
       metrics, establishing reporting requirements, and
       assessing system renovation risk.

     • PMO has not identified project risks, developed project
       metrics, or established a reporting system for its
       business continuity planning project; but it has
       implemented a risk management process for its mission-
       critical system renovation effort.

     • Partially satisfied
24




                       Page 37                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                     Appendix I
                     Briefing to the Special Committee on the Year
                     2000 Technology Problem




        Detailed Results: Initiation Phase
        Key Process 7
     • Organizations should assess existing business
       continuity, contingency, and disaster recovery plans
       for their applicability in addressing the Year 2000
       problem.

     • PMO directed field offices, but not the divisions, to
       review existing contingency plans as part of their
       business continuity planning effort. Two of the five
       divisions and all three field offices we contacted
       reported that they have assessed their existing
       plans.

     • Partially satisfied
25




                     Page 38                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                   Appendix I
                   Briefing to the Special Committee on the Year
                   2000 Technology Problem




       Detailed Results: Initiation Phase
       Key Process 8
     • Quality assurance reviews should be conducted to
       verify that the continuity of operations plans satisfy
       information requirements.

     • The PMO plans for its contractor to review some
       division-level plans and is considering expanding
       their review to field office plans.

     • Plans to satisfy




26




                   Page 39                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                        Appendix I
                        Briefing to the Special Committee on the Year
                        2000 Technology Problem




         Detailed Results: Business Impact
         Analysis Phase

               GAO Key Processes                                                  Results
1. Define and document information requirements,                            Partially satisfied
   methods, and techniques
2. Define and document Year 2000 failure scenarios                          Satisfied

3. Perform risk analysis of each core business process                      Plans to Satisfy

4. Assess and document infrastructure risks                                 Partially satisfied

5. Define the minimum acceptable level of outputs and                       Plans to satisfy
   services for each core business process




27




                        Page 40                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                      Appendix I
                      Briefing to the Special Committee on the Year
                      2000 Technology Problem




         Detailed Results: Business Impact
         Analysis Phase Key Process 1
     • Organizations need to define detailed information
       requirements, techniques, and methods for
       constructing a business continuity plan.

     • PMO has provided some information requirements to
       the divisions and field offices, including personnel,
       special equipment, system access, status of facilities’
       assets/systems, electricity, and telecommunications.
       However, the PMO has not provided the field offices or
       headquarters divisions any information on methods or
       techniques for developing contingency plans.

     • Partially satisfied
28




                      Page 41                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                      Appendix I
                      Briefing to the Special Committee on the Year
                      2000 Technology Problem




         Detailed Results: Business Impact
         Analysis Phase Key Process 2
     • Organizations need to define and document Year 2000
       failure scenarios, including the loss of all mission-critical
       information systems, the possibility that problems may
       be encountered earlier than expected, and the potential
       disruption of infrastructure services.

     • PMO defined failure scenarios for headquarters
       divisions and has also directed field offices to identify
       potential disruptions to internal systems and the public
       infrastructure, including electric power and
       transportation. Two of the three field offices we
       contacted reported they have either defined or are
       currently defining the potential disruptions.

     • Satisfied
29




                      Page 42                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                      Appendix I
                      Briefing to the Special Committee on the Year
                      2000 Technology Problem




          Detailed Results: Business Impact
          Analysis Phase Key Process 3
     • Organizations should monitor Year 2000 progress and
       determine the risk and impact of internal and external
       system failures on each core business process.

     • The PMO directed both headquarters divisions and field
       offices to assess the impact of internal and external
       system failures on core functions and to use these
       analyses in their business continuity planning, but
       directed only the field offices to perform a risk
       assessment of internal and external system failures.
       Four of the five divisions and one of the three field
       offices we contacted reported that they have begun their
       impact analyses and the others plan to conduct them.

     • Plans to satisfy
30




                      Page 43                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                    Appendix I
                    Briefing to the Special Committee on the Year
                    2000 Technology Problem




       Detailed Results: Business Impact
       Analysis Phase Key Process 4
     • Organizations should monitor the Year 2000
       readiness of the public infrastructure, assess the risk
       of service outages, and determine if emergency
       services may be available to mitigate outages.

     • PMO provided Year 2000 compliance information for
       public infrastructure services, including electric power
       and telecommunications, to field offices to use in
       conducting their business impact analyses.

     • Three of the five divisions we contacted are
       conducting their own assessments.

     • Partially satisfied
31




                    Page 44                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                    Appendix I
                    Briefing to the Special Committee on the Year
                    2000 Technology Problem




       Detailed Results: Business Impact
       Analysis Phase Key Process 5
     • To facilitate the selection of adequate contingencies,
       organizations need to define the minimum acceptable
       level of outputs and services for each core business
       process.

     • According to the FBI senior year 2000 executive, the
       FBI has long-established and well-understood rules
       governing emergency operations and priorities. The
       executive plans for these rules to govern how the FBI
       deals with Year 2000 contingencies.

     • Plans to satisfy

32




                    Page 45                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                          Appendix I
                          Briefing to the Special Committee on the Year
                          2000 Technology Problem




         Detailed Results: Contingency
         Planning Phase

                GAO Key Processes                                                  Results
 1. Assess the cost and benefits of identified alternatives                   Not satisfied
    and select the best contingency strategy for each core
    business process
 2. Identify and document contingency plans and                               Plans to satisfy
    implementation modes
 3. Define and document triggers for activating plans                         Partially satisfied

 4. Establish a business resumption team for each core                        Partially satisfied
    business process
 5. Develop and document “zero day” strategy and                              Partially satisfied
    procedures




33




                          Page 46                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                       Appendix I
                       Briefing to the Special Committee on the Year
                       2000 Technology Problem




          Detailed Results: Contingency
          Planning Phase Key Process 1
     • Organizations need to assess the cost and benefits of
       identified alternatives and select the best contingency
       strategy for each core business process.

     • FBI has not assessed the costs and benefits of
       alternative strategies and has not instructed the
       headquarters divisions or field offices to do so. One of
       the five divisions reported that it has developed a cost
       estimate for its preferred alternative but was not able to
       obtain funding for the alternative. All three field offices
       reported that they have not developed cost estimates.

     • Not satisfied


34




                       Page 47                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                     Appendix I
                     Briefing to the Special Committee on the Year
                     2000 Technology Problem




         Detailed Results: Contingency
         Planning Phase Key Process 2
     • Organizations need to identify and document
       contingency plans.

     • PMO has instructed both the headquarters divisions
       and field offices to prepare contingency plans, and the
       five divisions and three field offices that we talked to
       reported that they are currently preparing their plans.

     • Plans to satisfy




35




                     Page 48                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                       Appendix I
                       Briefing to the Special Committee on the Year
                       2000 Technology Problem




          Detailed Results: Contingency
          Planning Phase Key Process 3
     • Organizations need to define and document triggers for
       activating contingency plans for each core business
       process.

     • The PMO instructed the headquarters divisions to use
       the defined failure scenarios as triggers but has not
       instructed the field offices to use or develop triggers.
       Four of the five divisions and one of the three field
       offices we contacted reported they are developing
       triggers for their plans.

     • Partially satisfied

36




                       Page 49                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                      Appendix I
                      Briefing to the Special Committee on the Year
                      2000 Technology Problem




         Detailed Results: Contingency
         Planning Phase Key Process 4
     • Organizations need to designate responsible individuals
       to ensure that the plans are executed if necessary.

     • PMO has instructed the divisions to identify and notify
       such individuals of their responsibilities. The PMO did
       not instruct the field offices to identify these individuals.
       All five divisions and one of the three field offices we
       contacted reported they have begun identifying the
       responsible individuals.

     • Partially satisfied


37




                      Page 50                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                   Appendix I
                   Briefing to the Special Committee on the Year
                   2000 Technology Problem




      Detailed Results: Contingency
      Planning Phase Key Process 5
     • Organizations should develop a risk reduction
       strategy and procedures for the period between
       December 30 1999, and January 3, 2000.

     • FBI has not yet developed strategies, but the PMO
       has directed field offices and headquarters divisions
       to develop procedures for the weekend of
       December 31, 1999 to January 2, 2000. Three of
       the five divisions and one of the three field offices
       we contacted reported they have begun preparing
       such procedures for the weekend.

     • Partially satisfied
38




                   Page 51                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                           Appendix I
                           Briefing to the Special Committee on the Year
                           2000 Technology Problem




        Detailed Results: Testing Phase


                    GAO Key Processes                                           Results
     1. Validate business continuity strategy                              Not satisfied

     2. Develop and document contingency test plans                        Not satisfied

     3. Establish test teams and acquire contingency                       Not satisfied
        resources
     4. Prepare for and execute tests                                      Not satisfied

     5. Validate the capability of contingency plans                       Not satisfied

     6. Rehearse business resumption teams                                 Not satisfied

     7. Update the business continuity plan based upon                     Not satisfied
        lessons learned and re-test if necessary
     8. Update disaster recovery plans and procedures                      Not satisfied




39




                           Page 52                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                   Appendix I
                   Briefing to the Special Committee on the Year
                   2000 Technology Problem




       Conclusion

• FBI reports good progress in making its mission-critical
  systems Year 2000 compliant and in developing system-level
  contingency plans. However, because the Justice
  Department has not required and emphasized the importance
  of business continuity plans, the FBI is late in undertaking its
  business continuity planning effort, and is now faced with a
  compressed timeframe for testing and finalizing its plans.
  Unless the FBI moves swiftly to implement management
  controls and processes it lacks, it is unlikely to have effective
  business continuity plans in place by the turn of the century
  and it runs the serious risk of not being able to sustain the
  minimal levels of service needed to meet its mission if
  confronted with Year 2000 system failures.
40




                   Page 53                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                    Appendix I
                    Briefing to the Special Committee on the Year
                    2000 Technology Problem




         Recommendations

     • The Attorney General should direct the Justice
       Department’s Year 2000 Office to:

       • clarify the Department’s expectations for Year
         2000 business continuity planning for all
         Justice component agencies and to ensure this
         clarification emphasizes the need for these
         plans and discusses OMB’s adoption of our
         guidance as a federal standard.




41




                    Page 54                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                     Appendix I
                     Briefing to the Special Committee on the Year
                     2000 Technology Problem




         Recommendations (cont’d)

     • The Attorney General should direct the FBI Director to
       take the following actions:

        • establish and implement a plan for the timely
          development and testing of effective headquarters and
          field Year 2000 business continuity plans, including
          incremental milestones for completing all relevant key
          processes in GAO’s guides associated with business
          impact analysis, plan development, and plan testing,
          and




42




                     Page 55                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                Appendix I
                Briefing to the Special Committee on the Year
                2000 Technology Problem




     Recommendations (cont’d)

     • establish and implement effective controls and
       structures for managing Year 2000 business
       continuity planning, including each of the relevant
       key processes in GAO’s Year 2000 contingency
       planning guide discussed in this briefing as not
       being satisfied.




43




                Page 56                        GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Appendix II

Objectives, Scope, and Methodology                                                                       Appendix
                                                                                                                I




              Our objectives were to determine (1) the status of and plans for completing
              the FBI’s contingency planning for continuity of operations and
              (2) whether the FBI’s contingency planning efforts satisfy the key
              processes described in our business continuity and contingency planning
              guide.1

              To accomplish our first objective, we reviewed the FBI’s progress towards
              developing and testing business continuity plans and compared it to our
              recommended milestones.2 Also, we reviewed supporting documentation
              to evaluate the status and progress of the FBI’s efforts against milestones.
              Specifically, we reviewed the FBI’s business continuity guidance provided
              to headquarters divisions and field offices, business continuity task force
              meeting minutes, IT and non-IT status reports, and system-level
              contingency planning documents. In addition, we reviewed Justice’s Year
              2000-related guidance, including its roles, responsibilities and guidance
              document, dated January 23, 1999; and its guidelines for testing
              contingency plans, dated March 1999.

              We accomplished our second objective by identifying the FBI’s Year 2000
              program management controls and comparing these to controls (i.e., key
              processes) described in our business continuity and contingency planning
              guide. In addition, we reviewed supporting documentation to verify that the
              management controls were functioning as intended and, using specified
              criteria,3 determined whether each of the key processes was satisfied. To
              do this verification, we reviewed documents describing the FBI’s business
              continuity planning activities, business continuity task force meeting
              minutes, contractors’ statements of work, organization charts, and
              business continuity planning guidance provided to the headquarters
              divisions and field offices by the Year 2000 Program Office.



              1
               Year 2000 Computing Crisis: Business Continuity and Contingency Planning (GAO/AIMD-
              10.1.19, August 1998).
              2
                Year 2000 Computing Crisis: Readiness Improving, But Much Work Remains to Avoid Major
              Disruptions (GAO/T-AIMD-99-50, January 20, 1999).
              3
               “Satisfied” means that the key process was developed and implemented, and
              documentation was provided. “Partially satisfied” means that some, but not all, components
              of the key process were developed and implemented, and documentation was provided.
              “Plans to satisfy” means that the key process was not yet developed or implemented but
              guidance directs the divisions to develop it. “Not satisfied” means that the key process was
              not developed and not addressed in guidance to the divisions.




              Page 57                       GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Appendix II
Objectives, Scope, and Methodology




To supplement our analysis of documentation, we interviewed key Year
2000 program officials, such as the Year 2000 Program Manager, support
contractor representatives, and headquarters’ division and field office
representatives4 responsible for developing business continuity plans. We
selected these offices because the divisions were responsible for
developing continuity plans for the FBI’s core business processes and the
field offices were three of the largest field units. The Year 2000 Program
Office agreed with our selections.

We performed our work at FBI headquarters in Washington, D.C. We
performed our work from March through August 1999 in accordance with
generally accepted government auditing standards.




4
 Criminal Investigative Division, Criminal Justice Information Services Division,
Information Resources Division, Laboratory Division, National Security Division and the
Los Angeles, New York, and Washington, D.C., field offices.




Page 58                       GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Appendix III

Comments From the Department of Justice                                                        AppendxIi




Note: GAO comments
supplementing those in the
report text appear at the
end of this appendix.




See comment 1.




See comment 2.




                             Page 59   GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                 Appendix III
                 Comments From the Department of Justice




See comment 3.




See comment 4.




See comment 5.




See comment 6.




                 Page 60                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                 Appendix III
                 Comments From the Department of Justice




See comment 7.




See comment 8.




See comment 9.




                 Page 61                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Appendix III
Comments From the Department of Justice




Page 62                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
               Appendix III
               Comments From the Department of Justice




               The following is our detailed response to the Department of Justice’s
               comments, dated September 21, 1999, on a draft of this report.



GAO Response   1. We do not agree with Justice’s statement that its guidance and
               information adequately emphasizes the importance of business continuity
               planning, and therefore have not modified our position in the report that
               the department has not required and emphasized the importance of
               business continuity plans. As we stated in our report, Justice’s Year 2000
               guidance, dated January 23, 1999, only requires that its bureaus develop
               system-level contingency plans and does not address business continuity
               planning. In addition, Justice’s Year 2000 Program Manager told us that
               Justice’s Year 2000 guidance does not instruct its bureaus to prepare
               business continuity plans, and in fact Justice, in its comments on our draft
               report, states that the Department has concentrated on system-level
               contingency plans as opposed to business continuity plans.

               Regarding the comment that beginning in February 1998, the department’s
               Year 2000 Program Office provided information on business continuity and
               contingency plans to its components, including the FBI, Justice did not
               provide evidence with its comments to support this statement. We
               subsequently asked for support and were advised that the Year 2000
               Program Manager provided our Year 2000 business continuity and
               contingency planning guide to Justice’s designated senior officials for Year
               2000 and members of Justice’s Year 2000 working group. Justice’s Year 2000
               Program Manager also provided the Year 2000 working members with a
               copy of SSA’s business continuity and contingency plan, as well as meeting
               minutes from the April and May Chief Information Officer (CIO) Council
               Committee working group on the Year 2000, where SSA’s business
               continuity plan was discussed. However, Justice provided no evidence that
               it established expectations for its bureaus with respect to business
               continuity planning, and Justice’s Year 2000 Program Manager told us that
               communications with the bureaus never included a requirement to develop
               and test business continuity plans.

               2. Justice issued Year 2000-related guidance to its bureaus on testing
               contingency plans, but the guidance only addresses the testing of system-
               level contingency plans, not business continuity plans. In fact, in his
               March 31, 1999, memorandum, the Assistant Attorney General for
               Administration makes this point clear when he states that contingency
               plans have been completed for most of the Department’s mission-critical
               systems and that the next step is the testing of these plans.



               Page 63                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Appendix III
Comments From the Department of Justice




3. We have not reviewed the Justice referenced department-level business
continuity and contingency plan because this plan was not relevant to the
scope of our review. As a result, we cannot comment on this plan beyond
noting that many of the essential elements of such a plan, e.g., core
business processes, risk and impact analyses, and contingency strategies,
had not been completed by all the bureaus at the time Justice submitted the
plan to OMB (June 15, 1999). For example, as of August 1999, the FBI had
not yet (1) identified its core business processes, (2) completed risk and
impact analyses at its headquarters and field offices, and (3) developed
contingency strategies. Only since receiving our draft report for comment
has Justice requested that four of its bureaus, including the Immigration
and Naturalization Service and the U.S. Marshals Service, develop and test
business continuity and contingency plans, and thus far these four have
only initiated preliminary development activities.

4. We cannot comment on the number of Justice bureaus that do or do not
have business continuity plans because we have not reviewed each of the
bureaus’ continuity planning efforts. However, the fact that Justice
acknowledges in its comments that only three of its eight components have
developed business continuity plans further demonstrates our point that
Justice has not established clear expectations for Year 2000 business
continuity planning.

5. We do not agree that we have favorably reviewed the Bureau of Prisons’
(BOP) business continuity plans. As of January 1999, when we completed
our review of BOP’s Year 2000 program management, BOP had not yet
completed business continuity plans, and had not yet completed its review
and testing of emergency preparedness plans. As we stated in our report,
Year 2000 Computing Crisis: Status of Bureau of Prisons’ Year 2000 Effort
(GAO/AIMD-99-23, January 27, 1999), BOP’s Year 2000 Program Manager
had at that time directed all offices, including BOP contract facilities and
institutions, to (1) review and analyze emergency preparedness plans for
consideration of the threat of external infrastructure and internal system
failures, (2) revise those plans as necessary by March 1, 1999, and (3) test
the revised plans prior to April 5, 1999. As a result, we concluded that BOP
had established plans for completing important business continuity
planning efforts but that BOP still needed to effectively implement its plans
to minimize its Year 2000 risks.

6. We have not reviewed Justice Management Division/Computer Services
Staff’s (JMD/CSS) business continuity plan because it was not relevant to
the scope of our review. Therefore, we cannot comment on JMD/CSS’ plan.



Page 64                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
                   Appendix III
                   Comments From the Department of Justice




                   7. Requiring selected bureaus to develop and test continuity of business
                   plans is the first step in responding to our recommendation. We are
                   committed to providing Justice further assistance, if requested, in
                   explaining our Year 2000 business continuity planning guide. To fully
                   respond to our recommendation, Justice must clarify its expectations for
                   all of its bureaus and explicitly require all of them to effectively develop
                   and test continuity of business plans. In addition, Justice’s Year 2000
                   Program Office must monitor each bureau’s business continuity planning
                   efforts and ensure that they are completed in accordance with
                   expectations.

                   8. Establishing and implementing a plan for timely development and
                   testing of effective headquarters and field office Year 2000 business
                   continuity plans is a first step in responding to our recommendation. The
                   FBI must ensure that its plan is effectively implemented, which among
                   other things, will require it to define reporting requirements and measures
                   of interim progress, and effectively act to address any deviations from
                   expectations.

                   9. Establishing and implementing effective controls and structures for
                   managing Year 2000 business continuity planning are first steps in
                   responding to our recommendation. In particular, the FBI (1) developed a
                   master schedule for developing and testing contingency plans, (2) tasked
                   its headquarters and field offices to define and describe the minimum
                   acceptable level of business operations, complete contingency plans by the
                   end of October 1999, and develop and execute test plans by November
                   1999, and (3) provided guidance to its headquarters and field offices for
                   developing contingency plans. However, it did not provide any evidence
                   that it has (1) established a risk management process, (2) initiated quality
                   assurance reviews, and (3) planned for updating business continuity plans
                   based upon test results and retesting the plan, if necessary. Moreover, given
                   that the FBI has many important tasks to complete with very little time, it is
                   important that FBI’s leadership monitor its implementation of these
                   controls and structures to ensure that any deviations are identified and
                   corrective action taken immediately.




(511140)   Leter   Page 65                    GAO/AIMD-00-11 FBI Year 2000 Business Continuity Planning
Ordering Information

The first copy of each GAO report and testimony is free.
Additional copies are $2 each. Orders should be sent to the
following address, accompanied by a check or money order made
out to the Superintendent of Documents, when necessary, VISA and
MasterCard credit cards are accepted, also.

Orders for 100 or more copies to be mailed to a single address are
discounted 25 percent.

Orders by mail:

U.S. General Accounting Office
P.O. Box 37050
Washington, DC 20013

or visit:

Room 1100
700 4th St. NW (corner of 4th and G Sts. NW)
U.S. General Accounting Office
Washington, DC

Orders may also be placed by calling (202) 512-6000
or by using fax number (202) 512-6061, or TDD (202) 512-2537.

Each day, GAO issues a list of newly available reports and
testimony. To receive facsimile copies of the daily list or any list
from the past 30 days, please call (202) 512-6000 using a touchtone
phone. A recorded menu will provide information on how to obtain
these lists.

For information on how to access GAO reports on the INTERNET,
send an e-mail message with “info” in the body to:

info@www.gao.gov

or visit GAO’s World Wide Web Home Page at:

http://www.gao.gov
United States                       Bulk Rate
General Accounting Office      Postage & Fees Paid
Washington, D.C. 20548-0001           GAO
                                 Permit No. GI00
Official Business
Penalty for Private Use $300

Address Correction Requested