Missile Defense: Additional Knowledge Needed in Developing System for Intercepting Long-Range Missiles

Published by the Government Accountability Office on 2003-08-21.

Below is a raw (and likely hideous) rendition of the original report. (PDF)

              United States General Accounting Office

GAO           Report to the Ranking Minority
              Member, Subcommittee on Financial
              Management, the Budget, and
              International Security, Committee on
              Governmental Affairs, U.S. Senate
August 2003
              MISSILE DEFENSE

              Additional Knowledge
              Needed in
              Developing System
              for Intercepting
              Long-Range Missiles




GAO-03-600
                                                August 2003


                                                MISSILE DEFENSE

                                                Additional Knowledge Needed in
Highlights of GAO-03-600, a report to the       Developing System for Intercepting
Ranking Minority Member, Subcommittee
on Financial Management, the Budget,            Long-Range Missiles
and International Security, Committee on
Governmental Affairs, U.S. Senate




A number of countries hostile to                GMD is a sophisticated weapon system being developed to protect the
the United States and its allies have           United States against limited attacks by long-range ballistic missiles. It
or will soon have missiles capable              consists of a collection of radars and a weapon component—a three-stage
of delivering nuclear, biological, or           booster and exoatmospheric kill vehicle—integrated by a centralized
chemical weapons. To counter this               control system that formulates battle plans and directs the operation
threat, the Department of Defense’s
(DOD’s) Missile Defense Agency
                                                of GMD components. Successful performance of these components is
(MDA) is developing a system to                 dependent on 10 critical technologies.
defeat ballistic missiles.
                                                MDA expects to demonstrate the maturity of most of these technologies
MDA expects to spend $50 billion                before fielding the GMD element, which is scheduled to begin in
over the next 5 years to develop                September 2004. However, the agency has accepted higher cost and
and field this system. A significant            schedule risks by beginning integration of the element’s components before
portion of these funds will be                  these technologies have matured. So far, MDA has matured two critical GMD
invested in the Ground-based                    technologies. If development and testing progress as planned, MDA expects
Midcourse Defense (GMD)                         to demonstrate the maturity of five other technologies by the second quarter
element. To field elements as soon              of fiscal year 2004.
as practicable, MDA has adopted
an acquisition strategy whereby
capabilities are upgraded as new                The radar technologies are the least mature. MDA intends to demonstrate
technologies become available and               the maturity of an upgraded early warning radar in California in the first
is implementing it in 2-year blocks.            quarter of fiscal year 2005 and a sea-based radar in the Pacific Ocean in the
                                                fourth quarter of that year. Although MDA does not plan to demonstrate
Given the risks inherent to this                the maturity of the technology of the early warning radar in Alaska, which
strategy, GAO was asked to                      will serve as the primary fire control radar, through its own integrated
determine when MDA plans to                     flight tests, it may be able to do so through the anticipated launch of foreign
demonstrate the maturity of                     test missiles.
technologies critical to the
performance of GMD’s Block 2004                 MDA estimates that it will spend about $21.8 billion between 1997 and 2009
capability and to identify the
estimated costs to develop and
                                                to develop the GMD element. This estimate includes $7.8 billion to develop
field the GMD element and any                   and field the GMD Block 2004 capability. For example, the funds will be
significant risks with the estimate.            used to install interceptors at two sites, upgrade existing radars and testing
                                                infrastructure, and develop the sea-based X-band radar. We found that MDA
                                                has incurred a greater risk of cost growth because for more than a year the
                                                agency was not able to rely fully on data from its primary tool for monitoring
GAO is recommending DOD                         whether the GMD contractor has been performing work within cost and on
(1) explore options to demonstrate              schedule. In February 2002, MDA modified the prime contract to reflect an
effectiveness of the Cobra Dane
                                                increased scope of work for developing GMD. It was not until July 2003 that
radar and (2) establish procedures
to help ensure data are reliable                the agency completed a review to ensure that the data was fully reliable.
from MDA’s monitoring system.
DOD concurred with GAO’s first
recommendation and partially
concurred with GAO’s second.

www.gao.gov/cgi-bin/getrpt?GAO-03-600.

To view the full product, including the scope
and methodology, click on the link above.
For more information, contact Robert E. Levin
at (202) 512-4841 or levinr@gao.gov.
Contents


Letter                                                                                  1
               Results in Brief                                                         3
               Background                                                               4
               MDA Expects to Demonstrate the Maturity of Most GMD
                 Technologies before September 2004                                     8
               MDA Has Risked Cost Growth Because It Could Not Fully Rely on
                 Data from Its System for Monitoring Contractor Performance           18
               Conclusions                                                            24
               Recommendations for Executive Action                                   25
               Agency Comments and Our Evaluation                                     25

Appendix I     Scope and Methodology                                                  28



Appendix II    Comments from the Department of Defense                                29



Appendix III   Technology Readiness Level Assessment Matrix                           32



Appendix IV    Importance of Earned Value Management                                  35



Appendix V     GAO Contact and Staff Acknowledgments                                  40



Tables
               Table 1: Technology Readiness Levels of GMD Critical
                        Technologies                                                  11
               Table 2: Estimated Cost to Develop and Field GMD                       19
               Table 3: 32 Criteria for Earned Value Management Systems               35




               Page i                                          GAO-03-600 Missile Defense
Figures
          Figure 1: Components of GMD                                                               6
          Figure 2: Notional GMD Concept of Operations                                              7
          Figure 3: Tasks GMD Plans to Accomplish for the GMD Block 2004
                   Project                                                                          19




          Abbreviations

          BMDO              Ballistic Missile Defense Organization
          CPR               Cost Performance Report
          DCMA              Defense Contract Management Agency
          EVM               Earned Value Management
          GMD               Ground-based Midcourse Defense
          IBR               integrated baseline review
          IFT               integrated flight test
          MDA               Missile Defense Agency
          NMD               National Missile Defense
          TRL               technology readiness level




          This is a work of the U.S. government and is not subject to copyright protection in the
          United States. It may be reproduced and distributed in its entirety without further
          permission from GAO. However, because this work may contain copyrighted images or
          other material, permission from the copyright holder may be necessary if you wish to
          reproduce this material separately.




          Page ii                                                      GAO-03-600 Missile Defense
United States General Accounting Office
Washington, DC 20548




                                   August 21, 2003

                                   The Honorable Daniel K. Akaka
                                   Ranking Minority Member
                                   Subcommittee on Financial Management,
                                    the Budget, and International Security
                                   Committee on Governmental Affairs
                                   United States Senate

                                   Dear Senator Akaka:

                                   Hostile states, including those that sponsor terrorism, are investing
                                   significant resources to develop and deploy ballistic missiles of increasing
                                   range and sophistication that could be used against the United States, our
                                   deployed forces, and our allies. At least 25 countries now have, or are in
                                   the process of acquiring, missiles capable of delivering nuclear, biological,
                                   or chemical weapons. To counter this threat, the President of the United
                                   States in December 2002, directed the Department of Defense (DOD) to
                                   begin fielding a ballistic missile defense system in 2004.

                                   The Missile Defense Agency (MDA) within DOD is responsible for
                                   developing this system, including the Ground-based Midcourse Defense
                                   (GMD) element,1 which is being developed to protect the United States
                                   against long-range ballistic missiles. MDA is also building an integrated
                                   testing infrastructure—or “test bed”—with the newly designated GMD
                                   element as its centerpiece. MDA expects to spend nearly $50 billion in
                                   research and development funds between fiscal years 2004 and 2009 to
                                   develop and field a ballistic missile defense system. A significant
                                   percentage of the $50 billion will be invested in the GMD element.

                                   GMD is a sophisticated weapon system that will rely on state-of-the-art
                                   technologies that have been under development for a number of years.
                                   GMD will use space-based sensors to provide early warning of missile
                                   launches; ground-based radars to identify and refine the tracks of
                                   threatening warheads and associated objects; ground-based interceptors


                                   1
                                    In January 2002, the Secretary of Defense created the Missile Defense Agency and
                                   consolidated all ballistic missile defense programs under the new agency. Former missile
                                   defense acquisition programs are now referred to as elements of a single ballistic missile
                                   defense system.



                                   Page 1                                                        GAO-03-600 Missile Defense
(each consisting of a three-stage booster and exoatmospheric kill vehicle)
to destroy warheads; and a centralized control system that formulates
battle plans and directs the operation of GMD components for carrying out
the missile defense mission.

To meet the technical challenge of developing both the integrated
system and the GMD element, MDA has adopted a “capabilities-based”
acquisition strategy and is implementing it in 2-year development blocks.
This approach is designed to field elements as soon as practicable and
to improve the effectiveness of fielded elements by upgrading their
capability as new technologies become available or as the threat warrants.
Block 2004 will be the first block fielded, followed by Blocks 2006 and
2008. Although GMD’s Block 2004 capability is expected to be fielded
beginning in September 2004, MDA plans to upgrade that capability
through the end of 2005.2

Because development and fielding of GMD involves substantial technical
challenges and a major investment, you asked us to review technical and
cost issues related to the GMD element. Specifically, we determined when
MDA plans to demonstrate the maturity3 of technologies critical to the
performance of GMD’s Block 2004 capability. We also identified the
estimated costs to develop and field the GMD element and any significant
risks associated with the estimate.

Our scope and methodology are included in appendix I. Although we
assessed the maturity of specific GMD critical technologies, the scope of
this review did not include an evaluation of MDA’s test plans for
demonstrating GMD’s ability to operate as a system overall. Our detailed
assessment of GMD system-level testing is included in a classified report
that we issued in June 2003 to other congressional requesters.




2
 The intended performance of the Block 2004 capability is described in a classified annex
to this report.
3
 Technological maturity for starting product development or systems integration is
achieved when prototype hardware with the desired form, fit, and function has been
proven in a realistic operational environment. See U.S. General Accounting Office,
Best Practices: Better Management of Technology Development Can Improve Weapon
System Outcomes, GAO/NSIAD-99-162 (Washington, D.C.: July 1999).




Page 2                                                       GAO-03-600 Missile Defense
                   MDA expects to demonstrate the maturity of most of the ten technologies
Results in Brief   critical to GMD’s initial performance before fielding of the element begins
                   in September 2004. However, the agency has accepted a higher risk of cost
                   growth and schedule slips by beginning the integration of the element’s
                   components before these technologies have been demonstrated. So far,
                   MDA has matured two critical GMD technologies—the infrared sensors
                   of the kill vehicle4 and the fire control software of the battle management
                   component.5 But if development and testing progress as planned, MDA
                   expects to demonstrate the maturity of five others—resident in the kill
                   vehicle, interceptor boosters, and the battle management component—by
                   the second quarter of fiscal year 2004. MDA intends to demonstrate the
                   maturity of an upgraded early warning radar—located at Beale Air Force
                   Base, California—in the first quarter of fiscal year 2005 and a sea-based X-
                   band radar, located in the Pacific Ocean, in the fourth quarter of that year.
                   MDA does not plan to demonstrate through its own integrated flight tests
                   the maturity of a technology resident in the Cobra Dane radar located in
                   Alaska, which will serve as the element’s primary radar when GMD is first
                   fielded. Agency officials told us that they may be able to test the radar
                   through the anticipated launch of foreign test missiles. However, it is not
                   clear that testing Cobra Dane in this manner will provide all of the
                   information that a dedicated test provides because MDA will not control
                   the configuration of the target or the flight environment.

                   MDA estimates that it will spend about $21.8 billion between 1997 and
                   2009 to develop the GMD element. This estimate includes $7.8 billion to
                   develop and field the GMD Block 2004 capability and to develop the GMD
                   portion of the test bed between 2002 and 2005. For example, the funds will
                   be used to install interceptors at Fort Greely, Alaska, and Vandenberg Air
                   Force Base, California; upgrade existing radars and the test bed
                   infrastructure; and develop the sea-based X-band radar.

                   MDA has incurred a greater risk of cost growth because for more than a
                   year the agency was not able to rely fully on the data from its primary tool
                   for monitoring whether the GMD contractor was performing work within
                   cost and on schedule—the prime contractor’s Earned Value Management



                   4
                    The kill vehicle is the weapon component of the GMD element that attempts to detect and
                   destroy threat warheads through “hit-to-kill” impacts.
                   5
                    The battle management component is the integrating and controlling component of the
                   GMD element. The fire control software plans engagements and tasks GMD components to
                   execute a missile defense mission.




                   Page 3                                                     GAO-03-600 Missile Defense
             (EVM) system.6 In February 2002, MDA modified GMD’s contract to bring
             it into line with the agency’s new capabilities-based acquisition strategy. It
             took several months to establish an interim cost baseline7 against which to
             measure the contractor’s performance and 13 months to complete
             revisions to the baseline. Also, MDA and the contractor did not complete a
             review until July 2003 to ensure that the revised baseline was accurate and
             that contractor personnel were correctly using it to measure performance.
             This review was of particular importance because an earlier review
             revealed significant deficiencies in the contractor’s development and use
             of the initial contract baseline. Until this review was completed, MDA did
             not know for sure whether it could rely fully on the data from its EVM
             system to recognize and correct potential problems in time to prevent
             significant cost increases and schedule delays.

             We are making recommendations that MDA (1) consider adding a test of
             the effectiveness of the radar in Alaska; and (2) ensure that procedures are
             in place that will increase MDA’s confidence in data from its EVM system.
             DOD concurred with our first recommendation and partially concurred
             with the second. In commenting on the draft report, DOD stated that the
             feasibility of these procedures will be determined and that a portion of the
             work is already being accomplished.


             The concept of using a missile to destroy another missile (hit-to-kill) has
Background   been explored since the mid-1950’s, but it was not until 1984 that the first
             such intercept achieved its objective. Between the mid-1980’s and
             late-1990’s the United States conducted a number of experiments designed
             to demonstrate that it was possible to hit one missile with another. In
             1997, the Ballistic Missile Defense Organization (BMDO) established the
             National Missile Defense (NMD) Joint Program Office. The program office
             was directed to demonstrate by 1999 a system that could protect the
             United States from attacks of intercontinental ballistic missiles and to
             be in a position to deploy the system if the threat warranted by 2003. The


             6
              The EVM system is a management tool widely used by DOD to compare the value of
             contractor’s work performed to the work’s actual cost. The tool measures the contractor’s
             actual progress against its expected progress and enables the government and contractor
             to estimate the program’s remaining cost.
             7
              An interim baseline is often established by the contractor when the government has
             authorized work, but the requirements and terms of the work have not yet been negotiated.
             Until negotiations are completed, the contractor develops a baseline using proposed cost
             that has been divided among work packages with associated budgets and schedule.




             Page 4                                                       GAO-03-600 Missile Defense
initial system consisted of space- and ground-based sensors, early warning
radars, interceptors, and battle management functions.

The program underwent additional changes as the new decade began.
In September 2000, the President decided to defer deployment of the
NMD system, but development of the system continued with the goal of
being ready to deploy the system when directed. This action was followed
in 2001 by BMDO’s redirection of the prime contractor’s efforts from
developing and deploying an NMD system to developing an integrated test
bed with the newly designated GMD system as its centerpiece. The
Secretary of Defense, in January 2002, renamed BMDO as MDA and
consolidated all ballistic missile defense programs under the new agency.
Former missile defense acquisition programs became elements of a single
ballistic missile defense system. These changes were followed in
December 2002, by the President’s directive to begin fielding in 2004 a
ballistic missile defense system, which included components of the GMD
element already under development.

The GMD element is intended to protect the United States against long-
range ballistic missiles in the midcourse phase of their flight. This is the
point outside the atmosphere where the motors that boost an enemy
missile into space have stopped burning and the deployed warhead
follows a predictable path toward its target. Compared to the boost and
terminal phases, this stage of flight offers the largest window of
opportunity for interception and allows the GMD element a longer time to
track and engage a target.

As illustrated in figure 1, GMD will rely on a broad array of components
to track and intercept missiles. Figure 2 provides a notional concept of
how these components will operate once they are fully integrated into the
GMD element.




Page 5                                              GAO-03-600 Missile Defense
Figure 1: Components of GMD




Page 6                        GAO-03-600 Missile Defense
Figure 2: Notional GMD Concept of Operations




Note: The concept of operations assumes weapons release authority has been previously granted by
the President of the United States or the Secretary of Defense. Missile flight times may be too brief to
ask for permission to launch interceptors and engage the enemy.




Page 7                                                                GAO-03-600 Missile Defense
                         MDA is gaining the knowledge it needs to have confidence that
MDA Expects to           technologies critical to the GMD Block 2004 capability will work as
Demonstrate the          intended. Two of the ten technologies essential to the Block 2004
                         capability have already been incorporated into actual prototype hardware
Maturity of Most GMD     and have been demonstrated to function as expected in an operational
Technologies before      environment.8 Other technologies are reaching this level of maturity. If
                         development and testing proceed as planned, MDA will demonstrate the
September 2004           maturity of five additional technologies by the second quarter of fiscal
                         year 2004 and two critical radar technologies during fiscal year 2005. MDA
                         believes that its best opportunity to demonstrate the maturity of the tenth
                         technology, technology critical to GMD’s primary radar, may come
                         through the anticipated flight tests of foreign missiles.

                         Our work over the years has found that making a decision to begin system
                         integration of a capability before the maturity of all critical technologies
                         have been demonstrated increases the program’s cost, schedule, and
                         performance risks. Because the President directed DOD to begin fielding
                         a ballistic missile defense system in 2004, MDA began GMD system
                         integration with technologies whose maturity has not been demonstrated.
                         As a result, there is a greater likelihood that critical technologies will not
                         work as intended in planned flight tests. If this occurs, MDA may have to
                         spend additional funds in an attempt to identify and correct problems by
                         September 2004 or accept a less capable system.9


Importance of Maturing   Successful developers follow “knowledge-based acquisition” practices
Technology               to get quality products to the customer as quickly and cost effectively as
                         possible. As a part of meeting this goal, developers focus their technology
                         programs on maturing technologies that have the realistic potential for
                         being incorporated into the product under consideration. Accordingly,
                         successful developers spend time to mature technology in a technology
                         setting, where costs are typically not as great, and they do not move
                         forward with product development—the initiation of a program to fully




                         8
                           An operational environment is a real-world environment (e.g., flight demonstration)
                         that addresses all of the operational requirements and specifications demanded of the
                         final product.
                         9
                          U.S. General Accounting Office, Missile Defense: Knowledge-Based Practices Being
                         Adopted, but Risks Remain, GAO-03-441 (Washington, D.C.: Apr. 30, 2003). This report
                         presents our analysis of MDA’s new approach for developing missile defense technology.




                         Page 8                                                       GAO-03-600 Missile Defense
                          design, integrate, and demonstrate a product for production—until
                          essential technologies are sufficiently mature.

                          An analytical tool—which has been used by DOD and the National
                          Aeronautics and Space Administration, called technology readiness levels
                          (TRLs),10 —can assess the maturity level of technology as well as the risk
                          that technology poses if it is included in a product’s development. The nine
                          readiness levels are associated with progressing levels of technological
                          maturity and demonstrated performance relative to a particular
                          application—starting with paper studies of applied scientific principles
                          (TRL 1) and ending with a technology that has been “flight proven” on an
                          actual system through successful mission operations (TRL 9). Additional
                          details on TRLs are shown in appendix III.

                          TRLs provide a gauge of how much knowledge the program office has
                          on the progress or status of a particular technology and are based on
                          two principal factors: (1) the fidelity of demonstration hardware,
                          including design maturity and level of functionality achieved; and
                          (2) the extent and realism of the environment in which the technology
                          has been demonstrated.

                          MDA recognizes the value of beginning system integration with mature
                          technology and of using TRLs to assess the maturity of technology
                          proposed for a block configuration. In particular, MDA prefers to include
                          new technology in a block configuration only if the technology has
                          reached a TRL 7; that is, only if prototype hardware with the desired form,
                          fit, and function has been proved in an operational environment. However;
                          MDA retains the flexibility to include less mature technology in a block
                          configuration if that technology offers a significant benefit in performance
                          and the risk of retaining it is acceptable and properly managed.


Readiness Levels of GMD   Through technical discussions with the GMD joint program office and
Element Technologies      its prime contractor, we identified ten critical GMD technologies and
                          jointly assessed the readiness level of each. The critical technologies
                          are resident in the exoatmospheric kill vehicle, the boosters, the battle
                          management, command, and control component, and in the element’s



                          10
                            U.S. General Accounting Office, Best Practices: Better Management of
                          Technology Development Can Improve Weapon System Outcomes, GAO/NSIAD-99-162
                          (Washington, D.C.: July 1999).




                          Page 9                                               GAO-03-600 Missile Defense
radars. In 7 of 10 cases, we agreed with the program office and the
GMD prime contractor on the maturity level of the element’s critical
technologies. The differences in the remaining three cases, as discussed in
detail below, were primarily due to interpretation of TRL definitions. The
program office and its contractor rated the two booster technologies and
one radar technology at higher readiness levels than, in our opinion, MDA
had demonstrated.

Most critical GMD technologies are currently at TRLs 5 and 6. At TRL 5,
the technology’s development is nearing completion, but it has not been
applied or fitted for the intended product. At this point, the technology has
been incorporated into a high-fidelity breadboard11 that has been tested in
a laboratory or relevant environment 12. Although this demonstrates the
functionality of the technology to some extent, the hardware is not
necessarily of the form and fit (configuration) that would be integrated
into the final product. A new application of existing technology is usually
assessed at a TRL 5, because the technology has not been demonstrated in
the relevant environment for the new application. TRL 6 begins the true
“fitting” or application of the technology to the intended product. To reach
this level, technology must be a part of a representative prototype that is
very close to the form, fit, and function of that needed for the intended
product. Reaching a TRL 6 requires a major step in a technology’s
demonstrated readiness, that is, the prototype must be tested in a high-
fidelity laboratory environment or demonstrated in a restricted but
relevant environment.

Two of the ten GMD technologies were assessed at a TRL 7, the level that
successful developers insist upon before initiating product development.
To reach this level, a pre-production prototype of the technology must be
demonstrated to its expected functionality in an operational environment.
If development and testing proceed as planned by MDA, we judge that
most of the technologies (7 of 10) will be at a TRL 7 after the completion




11
  A breadboard is a collection of integrated components that provide a representation of
a system/subsystem that can be used to determine concept feasibility and to develop
technical data. A breadboard is typically configured for laboratory use to demonstrate the
technical principals of immediate interest.
12
  A relevant environment is defined as a testing environment that simulates key aspects of
the operational environment.




Page 10                                                       GAO-03-600 Missile Defense
                                             of integrated flight test (IFT)-14,13 which is scheduled for the second
                                             quarter of fiscal year 2004. Table 1 summarizes our assessment of the TRL
                                             for each critical technology as of June 2003 and the date at which MDA
                                             anticipates each technology will reach TRL 7. A detailed discussion of
                                             each critical technology follows.

Table 1: Technology Readiness Levels of GMD Critical Technologies

 Critical technology                                         TRL (as of June 2003)           Anticipated event/date for achieving TRL 7a
 Exoatmospheric kill vehicle
     Infrared seeker                                                                  7      Achieved
     On-board discrimination                                                          6      IFT-14 (2nd quarter FY04)
     Guidance, navigation, and control subsystem                                      6      IFT-14 (2nd quarter FY04)
 Boosters
     BV+                                                                              6      IFT-13A (1st quarter FY04)
     OSC Lite                                                                         6      IFT-13B (1st quarter FY04)
 Battle management command, control, and
 communications
     Fire control software                                                            7      Achieved
     In-flight interceptor communications system                                      6      IFT-14 (2nd quarter FY04)
 Radars
     Cobra Dane radar                                                                 5      Unknown
     Beale upgraded early warning radar                                               5      Radar certification flight (1st quarter FY05)
     Sea-based X-band radar                                                           5      IFT-18 (4th quarter FY05)
Source: GAO analysis of GMD data.

                                             Note: Information provided in the table—the configuration of flight test events and associated date—is
                                             as of June 2003 and is subject to change.
                                             a
                                              Assumes technology development and demonstrations will have been successful.




                                             13
                                               Integrated flight tests of the GMD element are real-world demonstrations of system
                                             performance during which an interceptor is launched to engage and intercept a mock
                                             warhead above the atmosphere.




                                             Page 11                                                              GAO-03-600 Missile Defense
Exoatmospheric Kill        The exoatmospheric kill vehicle is the weapon component of the GMD
Vehicle Technologies       interceptor that attempts to detect and destroy the threat reentry vehicle
                           through a hit-to-kill impact. The prime contractor identified three critical
                           technologies pertaining to the operation of the exoatmospheric kill
                           vehicle. They include the following:

                       •   Infrared seeker, which is the “eyes” of the kill vehicle. The seeker is
                           designed to support kill vehicle functions like tracking and target
                           discrimination. The primary subcomponents of the seeker are the infrared
                           sensors, a telescope, and the cryostat that cools down the sensors.
                       •   On-board discrimination, which is needed to identify the true warhead
                           from among decoys and associated objects. Discrimination is a critical
                           function of the hit-to-kill mission that requires the successful execution of
                           a sequence of functions, including target detection, target tracking, and the
                           estimation of object features. As such, successful operation of the infrared
                           seeker is a prerequisite for discrimination.
                       •   Guidance, navigation, and control subsystem, which is a combination
                           of hardware and software that enables the kill vehicle to track its
                           position and velocity in space and to physically steer itself into the
                           designated target.

                           All three kill vehicle technologies have been demonstrated to some extent
                           in actual integrated flight tests on near-production-representative kill
                           vehicles. The infrared seeker has reached a TRL 7, because a configuration
                           very much like that to be fielded has been demonstrated in previous
                           integrated flight tests, and only minor design upgrades are planned to
                           reach the Block 2004 configuration. The remaining two kill vehicle
                           technologies are at a TRL 6, because their functionality is being upgraded
                           and the technologies have yet to be incorporated into the kill vehicle and
                           demonstrated in an operational environment.

                           The on-board discrimination technology has not yet reached TRL 7
                           because MDA has not tested a “knowledge database” that is expected to
                           increase the kill vehicle’s discrimination capability. The purpose of the
                           database is to enable the kill vehicle to distinguish characteristics of
                           threatening from non threatening objects. MDA expects to test the
                           database for the first time in IFT-14.

                           As a software-intensive technology, on-board discrimination performance
                           under all flight conditions can only be evaluated through ground testing,
                           but flight-testing is needed to validate the software’s operation in a real
                           world environment. The discrimination capability that will be tested in
                           IFT-14 is expected to be fielded as part of the Block 2004 capability.



                           Page 12                                             GAO-03-600 Missile Defense
                       Therefore, IFT-14 should demonstrate the technology’s maturity if the test
                       shows that the kill vehicle achieves its discrimination objective.14

                       Similarly, the guidance, navigation, and control technology will also
                       increase to a TRL 7 if the technology achieves its objectives in IFT-14.
                       The inertial measurement unit, an important component of the guidance,
                       navigation, and control subsystem that enables the kill vehicle to track its
                       position and velocity, has not yet been tested in the severe environments
                       (e.g., vibrations and accelerations) induced by the operational booster.
                       This will be first attempted when one of the new operational boosters
                       is used in IFT-14. In addition to testing the inertial measurement unit,
                       IFT-14 will also test the upgraded divert hardware (used to actively
                       steer the kill vehicle to its target) that is expected to be part of the
                       Block 2004 configuration.


Booster Technologies   The integrated booster stack is the part of the GMD interceptor that is
                       composed of rocket motors needed to deliver and deploy the kill vehicle
                       into a desired intercept trajectory. For all flight tests to date, a two-stage
                       surrogate booster called the payload launch vehicle has been used.

                       In July 1998, the GMD prime contractor began developing a new
                       three-stage booster for the GMD program, known as the “Boost Vehicle”,
                       from commercial off-the-shelf components. However, the contractor
                       encountered difficulty. By the time the booster was flight tested in
                       August 2001, it was already about 18 months behind schedule. The first
                       booster flight test met its objectives, but the second booster tested drifted
                       off course and had to be destroyed 30 seconds after launch.

                       Subsequently, MDA altered its strategy for acquiring a new booster for
                       the interceptor. Instead of relying on a single contractor, MDA authorized
                       the GMD prime contractor to develop a second source for the booster
                       by awarding a subcontract to another contractor. If development of the
                       boosters proceeds as planned, both boosters will be part of the Block 2004
                       capability. One booster is known as BV+ and the other as “OSC Lite.”

The BV+ Booster        The prime contractor ultimately transferred development of the boost
                       vehicle to a subcontractor who is currently developing a variant—known
                       as “BV+”—for the GMD element. The program office and GMD


                       14
                            See classified annex for further details.




                       Page 13                                               GAO-03-600 Missile Defense
                                  contractor rated the BV+ at a TRL 7. The prime contractor reasoned
                                  that the extent of the legacy program and its one successful flight test
                                  should allow for this rating. However, given the limited testing to date, we
                                  assessed the BV+ booster currently at a TRL 6; that is, the technology has
                                  been demonstrated in a restricted flight environment using hardware close
                                  in form, fit, and function to that which will be fielded in 2004. We believe
                                  the contractor’s assessment is too high at this time, because the step from
                                  TRL 6 to TRL 7 is significant in terms of the fidelity of the demonstration
                                  environment. However, the first test of a full configuration BV+ booster
                                  will occur with IFT-13A, which is scheduled for the first quarter of fiscal
                                  year 2004. In our opinion, the BV+ booster will reach TRL 7 at this time if
                                  the booster works as planned.

The “OSC Lite” Booster            The second booster under development is referred to as “OSC Lite”. This
                                  booster, which is essentially the Taurus Lite missile that carries satellites
                                  into low-earth orbit, will be reconfigured for the GMD element. Despite the
                                  fact that the booster was recently tested under restricted flight conditions,
                                  GMD’s prime contractor believes that the legacy development of the
                                  Taurus Lite missile is sufficient to prove that the OSC Lite has reached
                                  TRL 7. However, in our opinion, because the test was conducted with
                                  hardware configured as it was in the Taurus missile, not as it will be
                                  configured for GMD’s Block 2004, the booster’s maturity level is
                                  comparable to that of the BV+. The first flight test of a full configuration
                                  OSC Lite booster is scheduled for IFT-13B in the first quarter of fiscal year
                                  2004. We believe that if the booster performs as intended in this test, it will
                                  reach TRL 7.

Battle Management Command,        The battle management component is the integrating and controlling
Control, and Communications       component of the GMD element. Prime contractor officials identified and
Technologies                      assessed the following sub-components as critical technologies:

                              •   GMD fire control software, which analyzes the threat, plans engagements,
                                  and tasks components of the GMD element to execute a mission.
                              •   In-flight interceptor communications system, which enables the GMD
                                  fire control component to communicate with the exoatmospheric kill
                                  vehicle while in flight.

                                  The two battle management technologies have been demonstrated to some
                                  extent in actual integrated flight tests, and both are near their Block 2004
                                  design. We determined that the GMD fire control software has currently
                                  achieved a TRL 7 and the in-flight interceptor communications system has
                                  reached a TRL 6. Prime contractor officials concur with our assessment.




                                  Page 14                                              GAO-03-600 Missile Defense
                     The fire control software is nearing expected functionality and prior
                     software builds have been demonstrated in GMD flight tests. Only minor
                     design changes will be made to address interfacing issues (linking the
                     fire control component with other GMD components) before the
                     software reaches the operational configuration of Block 2004. As a
                     software-intensive technology, the performance of the fire control
                     software throughout the entire “flight envelope” can only be evaluated
                     through ground testing. Ground testing is well underway at both the Joint
                     National Integration Center at Schriever Air Force Base, Colorado, and at
                     the prime contractor’s integration laboratory in Huntsville, Alabama.

                     The second technology associated with the battle management component
                     is the in-flight interceptor communications system. Even though the
                     pointing accuracy and communications capability of this technology
                     were demonstrated in previous flight tests, the operational hardware to
                     be fielded by 2004 is expected to operate at a different uplink frequency
                     than the legacy hardware used in these past flight tests.15 Accordingly, we
                     assessed the in-flight interceptor communications system at a TRL 6.
                     The first integrated flight test to include an operational-like build of this
                     technology is IFT-14, and if the technology meets its objectives in this
                     flight test, TRL 7 would be achieved.


Radar Technologies   The GMD contractor initially identified the sea-based X-band radar as
                     the only radar-related critical technology. Since its initial assessment in
                     September 2002, the contractor has now agreed with us that the Beale
                     upgraded early warning radar and the Cobra Dane radar are also critical
                     technologies of the GMD element. The contractor and the GMD program
                     office assessed the Beale and Cobra Dane radars at a TRL 5, because the
                     technology, especially mission software, is still under development and
                     has not yet been demonstrated in a relevant flight environment.16 The
                     contractor assessed the sea-based X-band radar at a TRL 6. As discussed
                     below, we agree with their assessment of the Beale and Cobra Dane radars
                     but rated the sea-based X-band radar as a TRL 5.




                     15
                          See classified annex for further details.
                     16
                       The hardware of the Beale and Cobra Dane radars is mature since both are currently in
                     operation for other missions, namely, integrated tactical warning and technical intelligence,
                     respectively. Adding the ballistic missile defense mission to these radars requires primarily
                     software-related development and testing.




                     Page 15                                                       GAO-03-600 Missile Defense
The early warning radar at Beale Air Force Base has participated in
integrated flight tests in a missile-defense role using legacy hardware
and developmental software. Design and development of operational
builds of the software are progressing, but such builds have only been
tested in a simulated environment. Therefore, we assessed the Beale radar
technology at a TRL 5—an assessment driven by software considerations.
The conversion of the early warning radar at Beale to an upgraded early
warning radar, which consists of minor hardware and significant software
upgrades, is planned for completion sometime during the middle of fiscal
year 2004. After this time, the Beale radar can take part in flight-testing
in its upgraded configuration. MDA currently plans to demonstrate the
upgraded Beale technology in a non intercept flight test, known as a
radar certification flight,17 in the first quarter of fiscal year 2005. The Beale
radar will be demonstrated at a TRL 7 if the objectives of this flight test
are achieved.

The Cobra Dane radar is currently being used in a surveillance mode
to collect data on selected intercontinental ballistic missile test launches
out of Russia and does not require real-time data processing and
communications capabilities. To achieve a defensive capability by
September 2004, the Cobra Dane radar is being upgraded to perform
both of these tasks. This upgrade, which requires a number of software
modifications, is designed to enable Cobra Dane to detect and track
enemy targets much as the Beale upgraded early warning radar does.
Although the hardware component of the Cobra Dane radar is mature and
will undergo only minor updating, Cobra Dane’s mission software is being
revised for this application. The revision includes reuse of existing
software and development of new software so that the Cobra Dane radar
can be integrated into the GMD architecture.

Upgrades to the Cobra Dane radar are due to be completed at the
beginning of 2004. After the software is developed and ground tested, the
radar can reach a TRL 6, but it is uncertain when the radar will reach a
TRL 7. Because of other funding and scheduling priorities, MDA has no
plans through fiscal year 2007 for using this radar in integrated flight tests;
such tests would require air- or sea-launched targets that are not currently
part of the test program. Unless the current test program is modified, the
only opportunities for demonstrating Cobra Dane in an operational
environment would come from flight tests of foreign missiles. MDA


17
     Ground testing of interim software builds to be mounted on the Beale radar is ongoing.




Page 16                                                         GAO-03-600 Missile Defense
officials anticipate that such opportunities will occur. However, it is not
clear that testing Cobra Dane in this manner will provide all of the
information that a dedicated test provides because MDA will not control
the configuration of the target or the flight environment.

The sea-based X-band radar is being built as part of the Block 2004
capability and scheduled for completion in 2005. It will be built from
demonstrated technologies—a sea-based platform and the prototype
X-band radar currently being used in the GMD test program. Prime
contractor officials told us that they consider the risk associated with
the construction and checkout of the radar as primarily a programmatic,
rather than technical risk, and believe that the sea-based X-band radar has
reached a TRL 6. The contractor also stated that the initial operational
build of the radar software is developed and currently being tested at the
contractor’s integration laboratory. We assessed the sea-based X-band
radar as a TRL 5 because the radar has not yet been built and because
constructing a radar from an existing design and placing it on a sea-based
platform is a new application of existing technology. For example, severe
wind and sea conditions may affect the radar’s functionality—conditions
that cannot be replicated in a laboratory. As a result, developers cannot be
sure that the sea-based X-band radar will work as intended until it is
demonstrated in this new environment. However, both we and the
contractor agree that the maturity level of the sea-based X-band radar will
increase to a TRL 7 if it achieves its test objectives in IFT-18 (scheduled
for the fourth quarter of fiscal year 2005).




Page 17                                             GAO-03-600 Missile Defense
                        From the program’s inception in 199718 through 2009, MDA expects to
MDA Has Risked          spend about $21.8 billion to develop the GMD element. About $7.8 billion
Cost Growth Because     of the estimated cost will be needed between 2002 and 2005 to develop
                        and field the Block 2004 GMD capability and to develop the GMD portion
It Could Not Fully      of the test bed.19 However, MDA has incurred a greater risk of cost
Rely on Data from Its   increases because for more than a year MDA was not sure that it could
                        rely fully upon data from the prime contractor’s Earned Value
System for Monitoring   Management (EVM) system,20 which provides program managers and
Contractor              others with early warning of problems that could cause cost and schedule
Performance             growth.


GMD Development Costs   Before the restructuring of the GMD program in 2002, about $6.2 billion
                        was spent (between 1997 and 2001) to develop a ground-based defense
                        capability. MDA estimates it will need an additional $7.8 billion between
                        2002 and 2005 to, among other tasks, install interceptors at Fort Greely,
                        Alaska, and at Vandenberg Air Force Base, California; upgrade existing
                        radars and test bed infrastructure; and develop the sea-based X-band radar
                        that will be added in the fourth quarter of fiscal year 2005. In addition,
                        MDA will invest an additional $7.8 billion between fiscal year 2004 and
                        2009 to continue efforts begun under Block 2004, such as enhancing
                        capability and expanding the test bed. Table 2, below, provides details on
                        the funding requirements by block and by fiscal year, and figure 3 provides
                        examples of specific Block 2004 tasks.




                        18
                          We calculated program cost from 1997 forward because the National Missile Defense
                        program was established at that time.
                        19
                          The cost to develop and field the initial GMD capability and the ballistic missile defense
                        test bed is funded in MDA’s budget within the Defense Wide Research, Development,
                        Test and Evaluation appropriation. MDA is not requesting any procurement, military
                        construction, or military personnel funds for this effort.
                        20
                          The EVM system is a management tool widely used by DOD to compare the value of
                        contractor’s work performed to the work’s actual cost. The tool measures the contractor’s
                        actual progress against its expected progress and enables the government and contractor
                        to estimate the program’s remaining cost.




                        Page 18                                                        GAO-03-600 Missile Defense
Table 2: Estimated Cost to Develop and Field GMD

 Then-year dollars in billions
                                                                                             Fiscal years
                                            1997-2001              2002          2003       2004    2005    2006   2007   2008     2009     Subtotal
 Sunk Cost                                             6.2                                                                                       6.2
 GMD Initial Capability and
 Block 2004 Test Bed                                                 3.1              2.6    1.2      .9                                         7.8
 GMD Block 2006                                                                              1.6     1.8     1.4    1.2                          6.0
 GMD Block 2008                                                                                                              .9       .9         1.8
 Total                                                 6.2           3.1              2.6    2.8     2.7     1.4    1.2     .9        .9        21.8
Source: Ballistic Missile Defense Budget, Midcourse Defense Segment, February 2003.




                                                                Figure 3: Tasks GMD Plans to Accomplish for the GMD Block 2004 Project




                                                                Page 19                                                   GAO-03-600 Missile Defense
                             MDA did not include the following costs is its Block 2004 estimate:

                         •   The cost to recruit, hire, and train military personnel to operate the initial
                             defensive capability and provide site security at various locations, which
                             MDA estimates to be an additional $13.4 million (half in fiscal year 2003
                             and half in 2004 each), will be needed to operate GMD and provide
                             physical security. Additional costs to cover these personnel throughout
                             the life of the program beginning in 2005 and beyond were also omitted.
                         •   The cost to maintain equipment and facilities was not included.
                         •   Systems engineering and national team costs—which benefit all elements,
                             including GMD and cannot be divided among the elements—were not
                             included in MDA’s budget.


MDA’s Insight into           Because a significant portion of MDA’s Block 2004 GMD cost estimate is
Potential Cost Growth Was    the cost of work being performed by the element’s prime contractor,
Limited by the Agency’s      MDA’s ability to closely monitor its contractor’s performance is critical to
                             controlling costs. The tool that MDA, and many DOD entities, have chosen
Inability to Rely Fully on   for this purpose is the EVM system. This system uses contractor reported
Data from Earned Value       data to provide program managers and others with timely information on a
Management System            contractor’s ability to perform work within estimated cost and schedule. It
                             does so by examining variances reported in contractor cost performance
                             reports between the actual cost and time of performing work tasks and the
                             budgeted or estimated cost and time. While this tool can provide insightful
                             information to managers, MDA’s use of it has been hampered by several
                             factors. Principally, although major contract modifications were made in
                             February 2002, it took until July 2003 for MDA to complete a review to
                             confirm the reliability of data from the EVM system. An earlier review of a
                             similar nature revealed significant deficiencies in the contractor’s
                             formulation and collection of EVM data. Until a new review was
                             completed, MDA could not be sure about its ability to rely fully upon this
                             data to identify potential problems in time to prevent significant cost
                             growth and schedule delays.

Baseline Revised over        An accurate, valid, and current performance management baseline is
13-Month Period              needed to perform useful analyses using EVM. The baseline identifies and
                             defines work tasks, designates and assigns organizational responsibility
                             for each task, schedules the work task in accordance with established
                             targets, and allocates budget to the scheduled work. According to DOD




                             Page 20                                              GAO-03-600 Missile Defense
guidance,21 a performance management baseline should be in place as
early as possible after the contractor is authorized to proceed. Although
the guidance does not define how quickly the contractor should establish
a baseline, experts generally agree that it should be in place, on average,
within 3 months after a contract is awarded or modified.

About a year before the Secretary of Defense directed MDA to adopt an
evolutionary acquisition strategy, the agency awarded a new contract for
the development of a National Missile Defense system. In February 2002,
MDA modified this contract to redirect the contractor’s efforts. Instead of
developing a missile defense system that met all of the requirements of the
war fighter, as the initial contract required, the modification directed the
contractor to develop the first GMD increment, or block, which was to be
a ballistic missile test bed with GMD as its centerpiece.

Following the contract’s modification, the contractor in June 2002
established an interim baseline. This baseline was developed by adding
budgets for near-term new work to the original baseline. Because the cost
of the work being added to the baseline had not yet been negotiated, the
contractor based the budgets on the cost proposed to MDA, as directed by
DOD guidelines. The contractor implemented the baseline almost within
the 3-month time frame recommended by experts. In the time between the
modification and the development of the interim baseline, MDA authorized
the contractor to begin work and spend a specified amount of money, and
MDA paid the contractor about $390 million during this period.

An option that MDA could have used to help validate the interim baseline
was to have the Defense Contract Management Agency (DCMA)22 verify
contractor work packages and track the movement of funds between the
unpriced work account and the baseline. However, neither MDA nor
DCMA initiated these actions. In its technical comments on a draft of this
report, DOD pointed out that during the negotiation process, MDA reviews
prime and subcontractor proposal data that include engineering labor
hours, material, and cost estimates. DOD further noted that these
estimates eventually form a basis for the work packages that make up the
data for the performance management baseline. We agree that these costs


21
  Department of Defense, Earned Value Management Implementation Guide
(Washington, D.C.: Dec. 1996, as revised, p. 10).
22
 DCMA is the agency that DOD has given responsibility for validating contractors’
Earned Value data.




Page 21                                                     GAO-03-600 Missile Defense
                               will eventually be associated with the work packages that make up the
                               baseline. However, a joint contractor and MDA review of the initial GMD
                               baseline concluded that even though these costs were otherwise fair and
                               reasonable, some work packages that the contractor developed for the
                               original contract’s baseline did not correctly reflect the work directed by
                               MDA. An independent review of work packages included in the interim
                               baseline would have increased the likelihood that the work packages were
                               being properly developed and that their budget and schedule were
                               appropriate.

                               The contractor completed all revisions to the baseline for the prime
                               contractor and all five subcontractors by March 2003, 3 months
                               after negotiating the cost of the modification and 13 months after
                               authorizing the work to begin. The contracting officer explained that it
                               took until December 2002 to negotiate the 2002 contract change because
                               the additional work was extremely complex, and, as a result, the
                               modification needed to be vetted through many subcontractors that
                               support the prime.

Baseline Review Completed in   The DOD guidance states that an integrated baseline review (IBR) is to be
July 2003                      conducted within 6 months of award of a new contract or major change
                               to an existing contract.23 The review verifies the technical content of the
                               baseline. It also ensures that contractor personnel understand and have
                               been adequately trained to collect EVM data. The review also verifies the
                               accuracy of the related budget and schedules, ensures that risks have been
                               properly identified, assesses the contractor’s ability to implement properly
                               EVM, and determines if the work identified by the contractor meets the
                               program’s objectives. The government’s program manager and technical
                               staff carry out this review with their contractor counterparts.

                               Completing an IBR of the new baseline has been of particular importance
                               because the July 2001 IBR for the initial contract identified more than
                               300 deficiencies in the contractor’s formulation and execution of the
                               baseline. For example, the contractor had not defined a critical path for
                               the overall effort, many tasks did not have sufficient milestones that would
                               allow the contractor to objectively measure performance, and contractor
                               personnel who were responsible for reporting earned value were making
                               mistakes in measuring actual performance against the baseline.




                               23
                                    Earned Value Management Implementation Guide, pp. 34 and 36.




                               Page 22                                                    GAO-03-600 Missile Defense
                          MDA began a review in March 2003 of the contractor’s new baseline,
                          which reflected the contract modification,. Completing this IBR took
                          until July 2003 because of the complexity of the program and the many
                          subcontractors that were involved. Although the review team found fewer
                          problems with the contractor’s formulation and execution of the new
                          baseline, problems were identified. For example, the IBR showed that in
                          some cases the baseline did not reflect the new statement of work. Also,
                          both the prime contractor and subcontractors improperly allocated budget
                          to activities that indirectly affect a work product (known as level of effort
                          activities) when they could have associated these activities with a discrete
                          end product. Because of the way these activities are accounted for, this
                          designation could mask true cost variances.


Management Reserve        Before the IBR was underway, DCMA recognized another problem with
Used to Offset Expected   the contractor’s EVM reports. In its December 2002 cost performance
Cost Overruns at          report, the contractor reported that it expected no cost overrun at
                          contract completion. This implied that the program was not experiencing
Contract Completion       any problems that could result in significant cost or schedule growth.
                          However, DCMA stated that October 2002 was the second month in a row
                          that the contractor had used management reserve funds to offset a
                          significant negative cost variance.24 DCMA emphasized that this is not the
                          intended purpose of management reserves. (Management reserves are a
                          part of the total project budget intended to be used to fund work
                          anticipated but not currently defined.) DCMA officials told us that while
                          this is not a prohibited practice most programs wait until their work is
                          almost completed, that is 80 to 90 percent complete, before making a
                          judgment that the management reserve would not be needed for additional
                          undefined work and could be applied to unfavorable contract cost
                          variances.




                          24
                            Defense Contract Management Agency, Ground-Based Midcourse Defense Monthly
                          Assessment Report Contract No. HQ0006-01-C-0001 for Missile Defense Agency (Seal
                          Beach, Calif.: Dec. 2002, p. 10). DCMA reported that cost performance reports were giving
                          “… a misleading feeling that everything in the program is OK. For the 2nd month in a row,
                          [the prime contractor] has covered up a significant Variance-at-Completion (-$107,800K) …
                          by taking money out of Management Reserve (MR). This is not the intended purpose of
                          using MR funds. [The prime contractor] is reporting a $0 Variance-At-Completion [VAC] by
                          subtracting $107,800K from MR to reduce VAC to $0. Based on prior performance to date,
                          this could be an indication of a trend for growth of the EAC [estimate-at-completion].”




                          Page 23                                                     GAO-03-600 Missile Defense
              Because of the President’s direction to begin fielding a ballistic missile
Conclusions   defense system in 2004, the MDA took a higher risk approach by beginning
              GMD system integration before knowing whether its critical technologies
              were mature. If development and testing progress as planned, however,
              MDA expects to have demonstrated the maturity of 7 of the 10 critical
              GMD technologies before the element is initially fielded in September 2004
              and 2 others during fiscal year 2005. If technologies do not achieve their
              objectives during testing, MDA may have to spend additional funds in an
              attempt to identify and correct problems by September 2004 or accept a
              less capable system.

              Because of other funding and scheduling priorities, MDA does not plan
              to demonstrate through integrated flight tests whether the Cobra Dane
              radar’s software can process and communicate data on the location of
              enemy missiles in “real time.” Although tests using sea- or air-launched
              targets before September 2004 would provide otherwise unavailable
              information on the software’s performance, we recognize those tests
              would be costly and funds have not been allocated for that purpose. We
              also recognize that the most cost efficient means of testing the Cobra Dane
              radar is through launches involving foreign test missiles. However, we
              believe it would be useful for MDA to consider whether the increased
              confidence provided by a planned test event outweighs other uses for
              those funds.

              MDA is investing a significant amount of money to achieve an operational
              capability during the first block of GMD’s development, and the agency
              expects to continue investing in the element’s improvement over the next
              several years. Because MDA is also developing other elements and must
              balance its investment in each, it needs an accurate GMD cost estimate.
              If it is used as intended, the EVM system can be an effective means of
              monitoring one of GMD’s largest costs, the cost of having a contractor
              develop the GMD system. It is understandable that the dynamic changes in
              MDA’s acquisition strategy led to major contract modifications, which
              made it more difficult for the contractor to establish a stable baseline.
              However, in this environment, it is even more important that MDA find
              ways to ensure the integrity of the interim baselines and to quickly
              determine that revised baselines can be fully relied on to identify potential
              problems before they significantly affect the program’s cost.




              Page 24                                             GAO-03-600 Missile Defense
                         To increase its confidence that the Ground-based Midcourse Defense
Recommendations for      element fielded in 2004 will operate as intended, we recommend that the
Executive Action         Secretary of Defense direct the Director, Missile Defense Agency, to
                         explore its options for demonstrating the upgraded Cobra Dane radar in its
                         new ballistic missile defense role in a real-world environment before
                         September 2004.

                         To improve MDA’s oversight of the GMD element and to provide the
                         Congress with the best available information for overseeing the program,
                         we recommend that the Secretary of Defense direct the Director, Missile
                         Defense Agency, to:

                     •   ensure that when a contractor is authorized to begin new work before a
                         price is negotiated that DCMA validate the performance measurement
                         baseline to the extent possible by (1) tracking the movement of budget
                         from the authorized, unpriced work account into the baseline, (2) verify
                         that the work packages accurately reflect the new work directed, and
                         (3) report the results of this effort to MDA; and
                     •   strive to initiate and complete an integrated baseline review (IBR) of any
                         major contract modifications within 6 months.


                         DOD’s comments on our draft report are reprinted in appendix II.
Agency Comments          DOD concurred with our first recommendation. DOD stated that MDA is
and Our Evaluation       exploring its options for demonstrating, prior to 2004, the upgraded
                         Cobra Dane radar in a real-world environment. However, DOD noted that
                         because it takes considerable time to develop and produce targets and to
                         conduct safety and environmental assessments, completing a Cobra
                         Dane radar test before September 2004 would be very challenging. DOD
                         concluded that “targets of opportunity” (flight tests of foreign missiles)
                         and ground testing may provide the best means to demonstrate the radar’s
                         maturity in the near term.

                         DOD partially concurred with our second recommendation. In responding
                         to the first part of recommendation two, DOD stated that MDA and the
                         DCMA will jointly determine the feasibility of tracking the budget for
                         authorized, unpriced work into the baseline and will concurrently
                         assess work package data while establishing the formal performance
                         measurement baseline. DOD also stated that a selected portion of this
                         work is already being accomplished by DCMA. We continue to believe in
                         the feasibility of our recommendation. DCMA officials told us that they
                         could monitor the movement of budget into the baseline and verify the
                         work packages associated with the budget. In addition, the guidelines



                         Page 25                                            GAO-03-600 Missile Defense
state that surveillance may be accomplished through sampling of internal
and external data. We believe that if DCMA sampled the data as it is
transferred into the baseline, the implementation of this recommendation
should not be burdensome.

In responding to the second part of recommendation two, DOD stated that
MDA will continue to adhere to current DOD policy by starting an IBR of
any major contract modification within 6 months. MDA correctly pointed
out that DOD’s Interim Defense Acquisition Guidebook only requires a
review be initiated within 6 months (180 days) after a contract is awarded
or a major modification is issued. However, DOD’s Earned Value
Management Implementation Guide states that such a review is
conducted within 6 months. Similar language is found in the applicable
clause from the GMD contract,25 which states that such reviews shall be
scheduled as early as practicable and should be conducted within 180
calendar days after the incorporation of major modifications. While we
understand the difficulty of conducting reviews within 180 days when the
contract is complex and many subcontractors are involved, we believe
that it is important for the government to complete an IBR as soon as
possible to ensure accurate measurement of progress toward the
program’s cost, schedule, and performance goals.

DOD also provided technical comments to this report, which we
considered and implemented as appropriate. In its technical comments,
for example, DOD expressed particular concern that our draft report
language asserting MDA’s inability to rely on the EVM system was
unsupported and misleading. DOD also stated that its prime contractor’s
EVM system is reliable. It stated, for example, that MDA has reviewed, and
continues to review on a monthly basis, the contractor’s cost performance
reports and that the prime contractor’s EVM system and accounting
systems have been fully certified and validated by DCMA. We modified our
report to better recognize MDA’s ability to use and trust the EVM system.
However, we still believe that MDA would benefit from taking additional
measures to increase its confidence in the accuracy of its interim
baselines. Also, when the revised baseline is in place, a review of its
formulation and execution is necessary before MDA can confidently and
fully rely on data from the EVM system.




25
  Defense Federal Acquisition Regulation Supplement clause 252.234-7001, EVM System
(March 1998).




Page 26                                                   GAO-03-600 Missile Defense
We conducted our review from December 2001 through August 2003 in
accordance with generally accepted government auditing standards. As
arranged with your staff, unless you publicly announce its contents earlier,
we plan no further distribution of this report until 30 days from its issue
date. At that time, we plan to provide copies of this report to interested
congressional committees, the Secretary of Defense, and the Director,
Missile Defense Agency. We will make copies available to others upon
request. In addition, the report will be available at no charge on the GAO
Web site at http://www.gao.gov/.

If you or your staff have any questions concerning this report, please
contact me on (202) 512-4841. Major contributors to this report are listed
in appendix V.

Sincerely yours,




Robert E. Levin
Director
Acquisition and Sourcing Management




Page 27                                            GAO-03-600 Missile Defense
             Appendix I: Scope and Methodology
Appendix I: Scope and Methodology


             To determine when MDA plans to demonstrate the maturity of
             technologies critical to the performance of GMD’s Block 2004 capability,
             we reviewed their critical technologies using technology readiness levels
             (TRLs) developed by the National Aeronautics and Space Administration
             and used by DOD. We did so by asking contractor officials at the Boeing
             System Engineering and Integration Office in Arlington, Virginia, to
             identify the most critical technologies and to assess the level of maturity of
             each technology using definitions developed by the National Aeronautics
             and Space Administration. We reviewed these assessments along with
             program documents, such as the results of recent flight tests and
             discussed the results with contractor and agency officials in order to reach
             a consensus, where appropriate, on the readiness level for each
             technology and identify the reasons for any disagreements.

             In reviewing the agency’s current cost estimate to develop the first block
             of the GMD element and its test bed, we reviewed and analyzed budget
             backup documents, cost documents, and selected acquisition reports for
             the GMD program extending over a period of several years. We also met
             with program officials responsible for managing the development and
             fielding of the GMD Block 2004 capability. For example, we met with
             officials from the GMD Joint Program Office in Arlington, Virginia, and
             Huntsville, Alabama; and the Office of the Deputy Assistant for Program
             Integration at the MDA, Arlington, Virginia.

             To determine whether there were any significant risks associated with the
             estimate, we met with agency officials responsible for determining the
             cost of the GMD element to find out if there were costs that were omitted,
             but should have been included, in the estimate. We also analyzed data
             from cost performance reports that the GMD contractor developed for the
             MDA. We reviewed data from the GMD element and contracting officials
             and conducted interviews to discuss the data. Although we did not
             independently verify the accuracy of the cost performance reports we
             received from MDA, the data were assessed independently by DCMA.




             Page 28                                             GAO-03-600 Missile Defense
             Appendix II: Comments from the Department
Appendix II: Comments from the Department
             of Defense



of Defense




             Page 29                                     GAO-03-600 Missile Defense
Appendix II: Comments from the Department
of Defense




Page 30                                     GAO-03-600 Missile Defense
Appendix II: Comments from the Department
of Defense




Page 31                                     GAO-03-600 Missile Defense
                                             Appendix III: Technology Readiness Level
Appendix III: Technology Readiness Level     Assessment Matrix



Assessment Matrix


Technology readiness level (TRL)          Description                    Hardware /software             Demonstration environment
1. Basic principles observed and          Lowest level of technology None (paper studies and            None
   reported.                              readiness. Scientific      analysis)
                                          research begins to be
                                          translated into applied
                                          research and development.
                                          Examples might include
                                          paper studies of a
                                          technology’s basic
                                          properties.
2. Technology concept and/or              Invention begins. Once        None (paper studies and         None
   application formulated.                basic principles are          analysis)
                                          observed, practical
                                          applications can be
                                          invented. The application is
                                          speculative, and there is no
                                          proof or detailed analysis to
                                          support the assumption.
                                          Examples are still limited to
                                          paper studies.
3. Analytical and experimental critical   Active research and            Analytical studies and         Lab
   function and/or characteristic proof   development is initiated.      demonstration of nonscale
   of concept.                            This includes analytical       individual components
                                          studies and laboratory         (pieces of subsystem).
                                          studies to physically
                                          validate analytical
                                          predictions of separate
                                          elements of the technology.
                                          Examples include
                                          components that are not
                                          yet integrated or
                                          representative.
4. Component and/or breadboard.           Basic technological            Low fidelity breadboard.       Lab
   Validation in laboratory               components are integrated      Integration of nonscale
   environment.                           to establish that the pieces   components to show
                                          will work together. This is    pieces will work together.
                                          relatively “low fidelity”      Not fully functional or form
                                          compared to the eventual       or fit but representative of
                                          system. Examples include       technically feasible
                                          integration of “ad hoc”        approach suitable for flight
                                          hardware in a laboratory.      articles.




                                             Page 32                                                           GAO-03-600 Missile Defense
                                            Appendix III: Technology Readiness Level
                                            Assessment Matrix




Technology readiness level (TRL)         Description                    Hardware /software              Demonstration environment
5. Component and/or breadboard           Fidelity of breadboard         High fidelity breadboard.       Lab demonstrating functionality but
   validation in relevant environment.   technology increases           Functionally equivalent but     not form and fit. May include flight-
                                         significantly. The basic       not necessarily form and/or     demonstrating breadboard in
                                         technological components       fit (size, weight, materials,   surrogate aircraft.
                                         are integrated with            etc). Should be
                                         reasonably realistic           approaching appropriate         Technology ready for detailed
                                         supporting elements so that    scale. May include              design studies.
                                         the technology can be          integration of several
                                         tested in a simulated          components with
                                         environment. Examples          reasonably realistic support
                                         include “high fidelity”        elements/subsystems to
                                         laboratory integration of      demonstrate functionality.
                                         components.
6. System/subsystem model or             Representative model or        Prototype. Should be very       High-fidelity lab demonstration or
   prototype demonstration in a          prototype system, which is     close to form, fit, and         limited/restricted flight
   relevant environment.                 well beyond the breadboard     function. Probably includes     demonstration for a relevant
                                         tested for TRL 5, is tested    the integration of many         environment.
                                         in a relevant environment.     new components and
                                         Represents a major step up     realistic supporting            Integration of technology is well
                                         in a technology’s              elements/subsystems if          defined.
                                         demonstrated readiness.        needed to demonstrate full
                                         Examples include testing a     functionality of the
                                         prototype in a high fidelity   subsystem.
                                         laboratory environment or
                                         in simulated operational
                                         environment.
7. System prototype demonstration in     Prototype near or at           Prototype. Should be form,      Flight demonstration in
   an operational environment.           planned operational            fit and function integrated     representative operational
                                         system. Represents a           with other key supporting       environment such as flying test bed
                                         major step up from TRL 6,      elements/subsystems to          or demonstrator aircraft.
                                         requiring the demonstration    demonstrate full
                                         of an actual system            functionality of subsystem.     Technology is well substantiated
                                         prototype in an operational                                    with test data.
                                         environment, such as in an
                                         aircraft, on a vehicle or in
                                         space. Examples include
                                         testing the prototype in a
                                         test bed aircraft.
8. Actual system completed and “flight Technology has been          Flight-qualified hardware           Developmental test and evaluation
   qualified” through test and         proven to work in its final                                      in the actual system application
   demonstration.                      form and under expected
                                       conditions. In almost all
                                       cases, this TRL represents
                                       the end of true system
                                       development. Examples
                                       include developmental test
                                       and evaluation of the
                                       system in its intended
                                       weapon system to
                                       determine if it meets design
                                       specifications.




                                            Page 33                                                           GAO-03-600 Missile Defense
                                                                 Appendix III: Technology Readiness Level
                                                                 Assessment Matrix




 Technology readiness level (TRL)                           Description                     Hardware /software            Demonstration environment
 9. Actual system “flight proven”                           Actual application of the       Actual system in final form   Operational test and evaluation in
    through successful mission                              technology in its final form                                  operational mission conditions
    operations.                                             and under mission
                                                            conditions, such as those
                                                            encountered in operational
                                                            test and evaluation. In
                                                            almost all cases, this is the
                                                            end of the last “bug fixing”
                                                            aspects of true system
                                                            development. Examples
                                                            include using the system
                                                            under operational mission
                                                            conditions.
Source: GAO and its analysis of National Aeronautics and Space Administration data.

                                                                 Note: GAO information based on U.S. General Accounting Office, Missile Defense: Knowledge-Based
                                                                 Decision Making Needed to Reduce Risks in Developing Airborne Laser, GAO-02-631 (Washington,
                                                                 D.C.: June 2002).




                                                                 Page 34                                                         GAO-03-600 Missile Defense
                                        Appendix IV: Importance of Earned Value
Appendix IV: Importance of Earned Value Management



Management

                                        Pulling together essential cost, schedule, and technical information in a
                                        meaningful, coherent fashion is always a challenge for any program.
                                        Without this information, management of the program will be fragmented,
                                        presenting a distorted view of program status. For several decades, DOD
                                        has compared the value of work performed to the work’s actual cost. This
                                        measurement is referred to as Earned Value Management (EVM). Earned
                                        value goes beyond the two-dimensional approach of comparing budgeted
                                        costs to actuals. It attempts to compare the value of work accomplished
                                        during a given period with the work scheduled for that period. By using
                                        the value of completed work as a basis for estimating the cost and time
                                        needed to complete the program, the earned value concept should alert
                                        program managers to potential problems early in the program.

                                        In 1996, in response to acquisition reform initiatives, DOD reemphasized
                                        the importance of earned value in program management and adopted
                                        32 criteria for evaluating the quality of management systems. These
                                        32 criteria are organized into 5 basic categories: organization, planning and
                                        budgeting, accounting considerations, analysis and management reports,
                                        and revisions and data maintenance. The 32 criteria are listed in table 1. In
                                        general terms, the criteria require contractors to (1) define the contractual
                                        scope of work using a work breakdown structure; (2) identify
                                        organizational responsibility for the work; (3) integrate internal
                                        management subsystems; (4) schedule and budget authorized work;
                                        (5) measure the progress of work based on objective indicators; (6) collect
                                        the cost of labor and materials associated with the work performed;
                                        (7) analyze any variances from planned cost and schedules; (8) forecast
                                        costs at contract completion; and (9) control changes.

Table 3: 32 Criteria for Earned Value Management Systems

Categories of Criteria             Criteria
Organization                       1. Define the authorized work elements for the program. A work breakdown structure, tailored
                                   for effective internal management control, is commonly used in this process.
                                   2. Identify the program organizational structure, including the major subcontractors responsible
                                   for accomplishing the authorized work, and define the organizational elements in which work
                                   will be planned and controlled.
                                   3. Provide for the integration of the company’s planning, scheduling, budgeting, work
                                   authorization, and cost accumulation processes with each other and, as appropriate, the
                                   program work breakdown structure and the program organizational structure.
                                   4. Identify the company organization or function responsible for controlling overhead (indirect
                                   costs).
                                   5. Provide for integration of the program work breakdown structure and the program
                                   organizational structure in a manner that permits cost and schedule performance measurement
                                   by elements of either or both structures as needed.




                                        Page 35                                                        GAO-03-600 Missile Defense
                                 Appendix IV: Importance of Earned Value
                                 Management




Categories of Criteria      Criteria
Planning and Budgeting      6. Schedule the authorized work in a manner that describes the sequence of work and
                            identifies significant task interdependencies required to meet the requirements of the program.
                            7. Identify physical products, milestones, technical performance goals, or other indicators that
                            will be used to measure progress.
                            8. Establish and maintain a time-phased budget baseline, at the control account level, against
                            which program performance can be measured. Budget for far-term efforts may be held in
                            higher-level accounts until an appropriate time for allocation at the control account level. Initial
                            budgets established for performance measurement will be based on either internal
                            management goals or the external customer-negotiated target cost including estimates for
                            authorized but undefinitized work. On government contracts, if an over target baseline is used
                            for performance measurement reporting purposes, prior notification must be provided to the
                            customer.
                            9. Establish budgets for authorized work with identification of significant cost elements (labor,
                            material, etc.) as needed for internal management and for control of subcontractors.
                            10. To the extent it is practical to identify the authorized work in discrete work packages,
                            establish budgets for this work in terms of dollars, hours, or other measurable units. Where the
                            entire control account is not subdivided into work packages, identify the far term effort in larger
                            planning packages for budget and scheduling purposes.
                            11. Provide that the sum of all work package budgets plus planning package budgets within a
                            control account equals the control account budget.
                            12. Identify and control level of effort activity by time-phased budgets established for this
                            purpose. Only that effort which is unmeasurable or for which measurement is impractical may
                            be classified as level of effort.
                            13. Establish overhead budgets for each significant organizational component of the company
                            for expenses that will become indirect costs. Reflect in the program budgets, at the appropriate
                            level, the amounts in overhead pools that are planned to be allocated to the program as
                            indirect costs.
                            14. Identify management reserves and undistributed budget.
                            15. Provide that the program target cost goal is reconciled with the sum of all internal program
                            budgets and management reserves.
Accounting Considerations   16. Record direct costs in a manner consistent with the budgets in a formal system controlled
                            by the general books of account.
                            17. When a work breakdown structure is used, summarize direct costs from control accounts
                            into the work breakdown structure without allocation of a single control account to two or more
                            work breakdown structure elements.
                            18. Summarize direct costs from the control accounts into the contractor’s organizational
                            elements without allocation of a single control account to two or more organizational elements.
                            19. Record all indirect costs which will be allocated to the contract.
                            20. Identify unit costs, equivalent units costs, or lot costs when needed.
Accounting Considerations   21. For EVMS, the material accounting system will provide for: (1) Accurate cost accumulation
                            and assignment of costs to control accounts in a manner consistent with the budgets using
                            recognized, acceptable, costing techniques. (2) Cost performance measurement at the point in
                            time most suitable for the category of material involved, but no earlier than the time of progress
                            payments or actual receipt of material. (3) Full accountability of all material purchased for the
                            program including the residual inventory.




                                 Page 36                                                             GAO-03-600 Missile Defense
                                                              Appendix IV: Importance of Earned Value
                                                              Management




 Categories of Criteria                                  Criteria
 Analysis and Management                                 22. At least on a monthly basis, generate the following information at the control account and
 Reports                                                 other levels as necessary for management control using actual cost data from, or reconcilable
                                                         with, the accounting system: (1) Comparison of the amount of planned budget and the amount
                                                         of budget earned for work accomplished. This comparison provides the schedule variance.
                                                         (2) Comparison of the amount of the budget earned and the actual (applied where appropriate)
                                                         direct costs for the same work. This comparison provides the cost variance.
                                                         23. Identify, at least monthly, the significant differences between both planned and actual
                                                         schedule performance and planned and actual cost performance, and provide the reasons for
                                                         the variances in the detail needed by program management.
                                                         24. Identify budgeted and applied (or actual) indirect costs at the level and frequency needed
                                                         by management for effective control, along with the reasons for any significant variances.
                                                         25. Summarize the data elements and associated variances through the program organization
                                                         and/or work breakdown structure to support management needs and any customer reporting
                                                         specified in the contract.
                                                         26. Implement managerial actions taken as the result of earned value information.
                                                         27. Develop revised estimates of cost at completion based on performance to date,
                                                         commitment values for material, and estimates of future conditions. Compare this information
                                                         with the performance measurement baseline to identify variances at completion important to
                                                         company management and any applicable customer reporting requirements including
                                                         statements of funding requirements.
 Revisions and Data Maintenance                          28. Incorporate authorized changes in a timely manner, recording the effects of such changes
                                                         in budgets and schedules. In the directed effort prior to negotiation of a change, base such
                                                         revisions on the amount estimated and budgeted to the program organizations.
                                                         29. Reconcile current budgets to prior budgets in terms of changes to the authorized work and
                                                         internal replanning in the detail needed by management for effective control.
                                                         30. Control retroactive changes to records pertaining to work performed that would change
                                                         previously reported amounts for actual costs, earned value, or budgets. Adjustments should be
                                                         made only for correction of errors, routine accounting adjustments, effects of customer or
                                                         management directed changes, or to improve the baseline integrity and accuracy of
                                                         performance measurement data.
                                                         31. Prevent revisions to the program budget except for authorized changes.
                                                         32. Document changes to the performance measurement baseline.
Source: Interim Defense Acquisition Guidebook, app. 4.

                                                              Note: In the Interim Defense Acquisition Guidebook, DOD states that these guidelines are reproduced
                                                              from the American National Standards (ANSI) Institute/Electronic Industries Alliance (EIA) EVM
                                                              System Standard (ANSI/EIA-748-98), Chapter 2 (May 19, 1998).




                                                              Page 37                                                           GAO-03-600 Missile Defense
Appendix IV: Importance of Earned Value
Management




The criteria have become the standard for EVM and have also been
adopted by major US government agencies, industry, and the governments
of Canada and Australia. The full application of EVM system criteria is
appropriate for large cost reimbursable contracts where the government
bears the cost risk. For such contracts, the management discipline
described by the criteria is essential. In addition, data from an EVM system
have been proven to provide objective reports of contract status, allowing
numerous indices and performance measures to be calculated. These can
then be used to develop accurate estimates of anticipated costs at
completion, providing early warning of impending schedule delays and
cost overruns.

The standard format for tracking earned value is through a Cost
Performance Report (CPR). The CPR is a monthly compilation of cost,
schedule and technical data which displays the performance measurement
baseline, any cost and schedule variances from that baseline, the amount
of management reserve used to date, the portion of the contract that is
authorized unpriced work, and the contractor’s latest revised estimate to
complete the program.

As a result, the CPR can be used as an effective management tool because
it provides the program manager with early warning of potential cost and
schedule overruns. Using data from the CPR, a program manager can
assess trends in cost and schedule performance. This information is useful
because trends tend to continue and can be difficult to reverse. Studies
have shown that once programs are 15 percent complete the performance
indicators are indicative of the final outcome. For example, a CPR
showing a negative trend for schedule status would indicate that the
program is behind schedule. By analyzing the CPR, one could determine
the cause of the schedule problem such as delayed flight tests, changes in
requirements, or test problems because the CPR contains a section that
describes the reasons for the negative status. A negative schedule
condition is a cause for concern, because it can be a predictor of later cost
problems since additional spending is often necessary to resolve
problems. For instance, if a program finishes 6 months later than planned,
additional costs will be expended to cover the salaries of personnel and
their overhead beyond what was originally expected. CPR data provides
the basis for independent assessments of a program’s cost and schedule
status and can be used to project final costs at completion in addition to
determining when a program should be completed.

Examining a program’s management reserve is another way that a
program can use a CPR to determine potential issues early on.


Page 38                                             GAO-03-600 Missile Defense
Appendix IV: Importance of Earned Value
Management




Management reserves, which are funds that may be used as needed,
provide flexibility to cope with problems or unexpected events. EVM
experts agree that transfers of management reserve should be tracked and
reported because they are often problem indicators. An alarming situation
arises if the CPR shows that the management reserve is being used at a
faster pace than the program is progressing toward completion. For
example, a problem would be indicated if a program has used 80 percent
of its management reserve but only completed 40 percent of its work. A
program’s management reserve should contain at least 10 percent of the
cost to complete a program so that funds will always be available to cover
future unexpected problems that are more likely to surface as the program
moves into the testing and evaluation phase.




Page 39                                           GAO-03-600 Missile Defense
                  Appendix V: GAO Contact and Staff
Appendix V: GAO Contact and Staff
                  Acknowledgments



Acknowledgments

                  Barbara Haynes (256) 922-7500
GAO Contact

                  In addition to the individual named above Yvette Banks, Myra Watts
Acknowledgments   Butler, Cristina Chaplain, Roger Corrado, Jennifer Echard, Dayna Foster,
                  Matt Lea, Karen Richey, and Randy Zounes made key contributions to this
                  report.




(120109)
                  Page 40                                          GAO-03-600 Missile Defense
                         The General Accounting Office, the audit, evaluation and investigative arm of
GAO’s Mission            Congress, exists to support Congress in meeting its constitutional responsibilities
                         and to help improve the performance and accountability of the federal
                         government for the American people. GAO examines the use of public funds;
                         evaluates federal programs and policies; and provides analyses,
                         recommendations, and other assistance to help Congress make informed
                         oversight, policy, and funding decisions. GAO’s commitment to good government
                         is reflected in its core values of accountability, integrity, and reliability.


                         The fastest and easiest way to obtain copies of GAO documents at no cost is
Obtaining Copies of      through the Internet. GAO’s Web site (www.gao.gov) contains abstracts and full-
GAO Reports and          text files of current reports and testimony and an expanding archive of older
                         products. The Web site features a search engine to help you locate documents
Testimony                using key words and phrases. You can print these documents in their entirety,
                         including charts and other graphics.
                         Each day, GAO issues a list of newly released reports, testimony, and
                         correspondence. GAO posts this list, known as “Today’s Reports,” on its Web site
                         daily. The list contains links to the full-text document files. To have GAO e-mail
                         this list to you every afternoon, go to www.gao.gov and select “Subscribe to e-mail
                         alerts” under the “Order GAO Products” heading.


Order by Mail or Phone   The first copy of each printed report is free. Additional copies are $2 each. A
                         check or money order should be made out to the Superintendent of Documents.
                         GAO also accepts VISA and Mastercard. Orders for 100 or more copies mailed to a
                         single address are discounted 25 percent. Orders should be sent to:
                         U.S. General Accounting Office
                         441 G Street NW, Room LM
                         Washington, D.C. 20548
                         To order by Phone:     Voice:    (202) 512-6000
                                                TDD:      (202) 512-2537
                                                Fax:      (202) 512-6061


                         Contact:
To Report Fraud,
                         Web site: www.gao.gov/fraudnet/fraudnet.htm
Waste, and Abuse in      E-mail: fraudnet@gao.gov
Federal Programs         Automated answering system: (800) 424-5454 or (202) 512-7470


                         Jeff Nelligan, Managing Director, NelliganJ@gao.gov (202) 512-4800
Public Affairs           U.S. General Accounting Office, 441 G Street NW, Room 7149
                         Washington, D.C. 20548