             United States Government Accountability Office

GAO          Report to the Subcommittee on Federal Financial
             Management, Government Information, Federal
             Services, and International Security, Committee on
             Homeland Security and Governmental Affairs
             United States Senate


July 2012
             SOFTWARE
             DEVELOPMENT
             Effective Practices
             and Federal
             Challenges in
             Applying Agile
             Methods




GAO-12-681
                                                July 2012

                                                SOFTWARE DEVELOPMENT
                                                Effective Practices and Federal Challenges in
                                                Applying Agile Methods
Highlights of GAO-12-681, a report to the
Subcommittee on Federal Financial
Management, Government Information,
Federal Services, and International Security,
Committee on Homeland Security and
Governmental Affairs, United States Senate

Why GAO Did This Study                           What GAO Found
Federal agencies depend on IT to                GAO identified 32 practices and approaches as effective for applying Agile
support their missions and spent at             software development methods to IT projects. The practices generally align with
least $76 billion on IT in fiscal year          five key software development project management activities: strategic planning,
2011. However, long-standing                    organizational commitment and collaboration, preparation, execution, and
congressional interest has contributed          evaluation. Officials who have used Agile methods on federal projects generally
to the identification of numerous               agreed that these practices are effective. Specifically, each practice was used
examples of lengthy IT projects that            and found effective by officials from at least one agency, and ten practices were
incurred cost overruns and schedule             used and found effective by officials from all five agencies. The ten practices are
delays while contributing little to
mission-related outcomes. To reduce             •    Start with Agile guidance and an Agile adoption strategy.
the risk of such problems, the Office of        •    Enhance migration to Agile concepts using Agile terms, such as user stories
Management and Budget (OMB)                          (used to convey requirements), and Agile examples, such as demonstrating
recommends modular software                          how to write a user story.
delivery consistent with an approach            •    Continuously improve Agile adoption at both the project level and
known as Agile, which calls for
                                                     organization level.
producing software in small, short
increments. Recently, several agencies          •    Seek to identify and address impediments at the organization and project
have applied Agile practices to their                levels.
software projects.                              •    Obtain stakeholder/customer feedback frequently.
                                                •    Empower small, cross-functional teams.
Accordingly, GAO was asked to                   •    Include requirements related to security and progress monitoring in your
identify (1) effective practices in
                                                     queue of unfinished work (the backlog).
applying Agile for software
development solutions and (2) federal           •    Gain trust by demonstrating value at the end of each iteration.
challenges in implementing Agile                •    Track progress using tools and metrics.
development techniques. To do so,               •    Track progress daily and visibly.
GAO identified and interviewed ten
experienced users and officials from            GAO identified 14 challenges with adapting and applying Agile in the federal
five federal projects that used Agile           environment (see table).
methods and analyzed and
categorized their responses.                    Table: Federal Challenges

                                                 Teams had difficulty collaborating closely.   Procurement practices may not support Agile projects.
What GAO Recommends                              Teams had difficulty transitioning to self-   Customers did not trust iterative solutions.
                                                 directed work.
GAO is recommending that the Federal
                                                 Staff had difficulty committing to more       Teams had difficulty managing iterative requirements.
CIO Council, working with its chair,
                                                 timely and frequent input.
OMB’s Deputy Director for
                                                 Agencies had trouble committing staff.        Compliance reviews were difficult to execute within an
Management, include practices such                                                             iteration time frame.
as those discussed in this report in the         Timely adoption of new tools was difficult.   Federal reporting practices do not align with Agile.
Council’s ongoing effort to promote
modular development. After reviewing             Technical environments were difficult to      Traditional artifact reviews do not align with Agile.
                                                 establish and maintain.
a draft of this report, OMB commented
                                                 Agile guidance was not clear.                 Traditional status tracking does not align with Agile.
that the recommendation was better
addressed to the Council than to its            Source: GAO.
chair. GAO revised the
recommendation to address it to the             Finally, officials described efforts to address challenges by clarifying previously
Council working with its chair.                 unclear guidance on using Agile. In a related effort, the Federal Chief Information
View GAO-12-681. For more information,          Officers (CIO) Council is developing guidance on modular development in the
contact David A. Powner at (202) 512-9286 or    federal government, but it does not specifically address effective practices for
pownerd@gao.gov.                                Agile.


                                                                                                  United States Government Accountability Office
Contents


Letter                                                                                             1
               Background                                                                         3
               Effective Practices for Applying Agile                                             9
               Federal Challenges in Applying Agile                                              15
               Conclusions                                                                       21
               Recommendation for Executive Action                                               22
               Agency Comments and Our Evaluation                                                22

Appendix I     Objectives, Scope, and Methodology                                                24



Appendix II    The Agile Manifesto and Principles                                                26



Appendix III   Experienced Users                                                                 28



Appendix IV    Federal Project Profiles                                                          29



Appendix V     Comments from the Department of Veterans Affairs                                  31



Appendix VI    Comments from the Department of Commerce                                          33



Appendix VII   GAO Contacts and Staff Acknowledgments                                            34



Tables
               Table 1: Practices Used and Found Effective by Five Agencies                      14
               Table 2: Profile of Global Combat Support System-J Increment 7                    29
               Table 3: Profile of National Aeronautics and Space Administration
                        Enterprise Applications Competency Center Materials
                        Management Initiative                                                    29
               Table 4: Profile of Patents End-to-End                                            29
               Table 5: Profile of Occupational Health Record-keeping System                     30


               Page i                     GAO-12-681 Agile Effective Practices and Federal Challenges
         Table 6: Profile of Affordable Care Act Branded Prescription Drugs                        30


Figure
         Figure 1: Comparison of Agile and Waterfall Development                                   7




         Abbreviations
         CIO         Chief Information Officer
         EVM         earned value management
         IT          information technology
         NASA        National Aeronautics and Space Administration
         OMB         Office of Management and Budget
         XP          eXtreme Programming


         This is a work of the U.S. government and is not subject to copyright protection in the
         United States. The published product may be reproduced and distributed in its entirety
         without further permission from GAO. However, because this work may contain
         copyrighted images or other material, permission from the copyright holder may be
         necessary if you wish to reproduce this material separately.




         Page ii                        GAO-12-681 Agile Effective Practices and Federal Challenges
United States Government Accountability Office
Washington, DC 20548




                                   July 27, 2012

                                   The Honorable Thomas R. Carper
                                   Chairman
                                   The Honorable Scott P. Brown
                                   Ranking Member
                                   Subcommittee on Federal Financial Management,
                                   Government Information, Federal Services,
                                     and International Security
                                   Committee on Homeland Security
                                     and Governmental Affairs
                                   United States Senate

                                   Information systems are integral to many aspects of federal government
                                   operations. To support agency missions, the federal government spent at
                                   least $76 billion in fiscal year 2011 on information technology (IT).
                                   However, as we have previously reported, prior IT expenditures too often
                                   have produced disappointing results, including multimillion dollar cost
                                   overruns and schedule delays measured in years, with questionable
                                   mission-related achievements. 1 Congress has expressed long-standing
                                   interest in monitoring and improving federal IT investments, which have
                                   often been developed in long, sequential phases. Recently, several
                                   agencies have tried an alternate approach known as Agile, which calls for
                                   producing software in small, short increments.

                                   Shorter, more incremental approaches to IT development have been
                                   identified as having the potential to improve the way in which the federal
                                   government develops and implements IT. For example, the Office of
                                   Management and Budget (OMB) recently issued guidance that advocates
                                   the use of shorter delivery time frames, an approach consistent with
                                   Agile. 2 As federal interest in Agile grows, it is helpful to know how
                                   experienced users effectively follow this approach and what challenges it
                                   presents in the federal environment.


                                   1
                                    GAO, Information Management and Technology, GAO/HR-97-9 (Washington, D.C.:
                                   February 1997) and Information Technology: Critical Factors Underlying Successful Major
                                   Acquisitions, GAO-12-7 (Washington, D.C.: Oct. 21, 2011).
                                   2
                                    OMB, 25 Point Implementation Plan to Reform Federal Information Technology
                                   Management, (Washington, D.C.: Dec. 9, 2010) and Immediate Review of Financial
                                   Systems IT Projects, M-10-26 (Washington, D.C.: June 28, 2010).




                                   Page 1                        GAO-12-681 Agile Effective Practices and Federal Challenges
Accordingly, the objectives of our review were to identify (1) effective
practices in applying Agile for software development solutions and (2)
federal challenges in implementing Agile development techniques.

To identify effective practices in applying Agile for software development
solutions, we interviewed a nongeneralizable sample of experienced Agile
users (see app. III). 3 We identified those users from publications, forums,
and recommendations from federal and private officials knowledgeable
about Agile. To ensure a broad range of experiences, we chose
individuals from private, public, and non-profit backgrounds. We asked
them individually to describe what they have found to be effective
practices in applying Agile methods. We compiled the practices and
asked the users to rate them for effectiveness. We then asked officials
from a nongeneralizable sample of five federal software development
projects that had used Agile methods for their views on the effectiveness
of the practices. The projects were selected to reflect a range of
agencies, system descriptions, and cost. The five federal agencies
supporting these projects were the Departments of Commerce, Defense,
and Veterans Affairs, the Internal Revenue Service, and the National
Aeronautics and Space Administration (see app. IV for additional
information on the projects and responsible officials).

To identify federal challenges in implementing Agile development
techniques, we asked the officials from the five projects to identify
challenges applying Agile in their agency and efforts they had taken to
address these challenges. We analyzed their responses and categorized
them by topic.

We conducted our work from October 2011 through July 2012 in
accordance with all sections of GAO’s Quality Assurance Framework that
were relevant to our objectives. The framework requires that we plan and
perform the engagement to obtain sufficient and appropriate evidence to
meet our stated objectives and to discuss any limitations in our work. We
believe that the information obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives. Further details of
our objectives, scope, and methodology are in appendix I.


3
 Results from a nongeneralizable sample cannot be used to make inferences about a
population. To mitigate this limitation, our sample was designed to ensure we obtained
highly-qualified users with a broad range of Agile experience across the private, public,
and non-profit sectors.




Page 2                          GAO-12-681 Agile Effective Practices and Federal Challenges
             While federal IT investments can improve operational performance and
Background   increase public interaction with government, too often they have become
             risky, costly, and unproductive mistakes. Congress has expressed
             interest in monitoring and improving IT investments through hearings and
             other reviews over the past two decades. In response, we have testified
             and reported on lengthy federal IT projects that too frequently incur cost
             overruns and schedule slippages while contributing little to mission-
             related outcomes. 4 Similarly, in 2010, OMB expressed concern about
             expansive federal IT projects that have taken years and have failed at
             alarming rates. OMB also noted that many projects follow “grand designs”
             to deliver functionality in years, rather than breaking projects into more
             manageable chunks and delivering functionality every few quarters.

             One approach to reducing the risks from broadly scoped, multiyear
             projects is the use of shorter software delivery times, a technique
             advocated by OMB in recent guidance documents. Specifically, OMB’s
             June 2010 memo on IT financial system reforms and the December 2010
             IT management reform plan 5 encourage modular development with
             usable functionality delivered in 90 to 120 days. In addition, the Federal
             Chief Information Officers (CIO) Council, chaired by OMB’s Deputy
             Director for Management, encourages the sharing and adoption of
             efficient IT development practices, such as those in OMB’s IT guidance.
             The Council is comprised of CIOs and Deputy CIOs of 28 agencies. It is


             4
              See, for example, GAO, Information Technology Reform: Progress Made: More Needs to
             Be Done to Complete Actions and Measure Results, GAO-12-745T (Washington, D.C.:
             May 24, 2012); FEMA: Action Needed to Improve Administration of the National Flood
             Insurance Program, GAO-11-297 (Washington, D.C.: June 9, 2011); Secure Border
             Initiative: DHS Needs to Reconsider Its Proposed Investment in Key Technology Program,
             GAO-10-340 (Washington, D.C.: May 5, 2010); Secure Border Initiative: DHS Needs to
             Address Testing and Performance Limitations That Place Key Technology Program at
             Risk, GAO-10-158 (Washington, D.C.: Jan. 29, 2010); Information Technology:
             Management and Oversight of Projects Totaling Billions of Dollars Need Attention,
             GAO-09-624T (Washington, D.C.: Apr. 28, 2009); Information Technology: Agriculture
             Needs to Strengthen Management Practices for Stabilizing and Modernizing Its Farm
             Program Delivery Systems, GAO-08-657 (Washington, D.C.: May 16, 2008); Information
             Technology: FBI Following a Number of Key Acquisition Practices on New Case
             Management System, but Improvements Still Needed, GAO-07-912 (Washington, D.C.:
             July 30, 2007); Information Technology: Foundational Steps Being Taken to Make Needed
             FBI Systems Modernization Management Improvements, GAO-04-842 (Washington, D.C.:
             Sept.10, 2004); and GAO/HR-97-9.
             5
              We recently reported on OMB’s progress on these reforms in GAO, Information
             Technology Reform: Progress Made; More Needs to Be Done to Complete Actions and
             Measure Results, GAO-12-461 (Washington, D.C.: Apr. 26, 2012).




             Page 3                       GAO-12-681 Agile Effective Practices and Federal Challenges
                      the principal interagency forum for improving agency practices related to
                      the design, acquisition, development, modernization, use, sharing, and
                      performance of federal information resources.

                      Agile software development supports the practice of shorter software
                      delivery. Specifically, Agile calls for the delivery of software in small, short
                      increments rather than in the typically long, sequential phases of a
                      traditional waterfall approach. More a philosophy than a methodology,
                      Agile emphasizes this early and continuous software delivery, as well as
                      using collaborative teams, and measuring progress with working
                      software. The Agile approach was first articulated in a 2001 document
                      called the Agile Manifesto, which is still used today. The manifesto has
                      four values: (1) individuals and interactions over processes and tools, (2)
                      working software over comprehensive documentation, (3) customer
                      collaboration over contract negotiation, and (4) responding to change
                      over following a plan. 6 Appendix II provides additional information on the
                      Agile Manifesto and its related principles.


Agile and Waterfall   The Agile approach differs in several ways from traditional waterfall
Approaches Differ     software development, 7 which produces a full software product at the end
                      of a sequence of phases. For example, the two approaches differ in (1)
                      the timing and scope of software development and delivery, (2) the timing
                      and scope of project planning, (3) project status evaluation, and (4)
                      collaboration.

                      •   Timing and scope of software development and delivery. In an
                          Agile project, working software is produced in iterations of typically
                          one to eight weeks in duration, each of which provides a segment of
                          functionality. To allow completion within the short time frame, each
                          iteration is relatively small in scope. For example, an iteration could
                          encompass a single function within a multistep process for
                          documenting and reporting insurance claims, such as a data entry
                          screen or a link to a database. Iterations combine into releases, with


                      6
                       The Agile Manifesto was written by a group of methodologists called the Agile Alliance.
                      For more information on the creation of the Agile Manifesto, go to
                      http://agilemanifesto.org.
                      7
                       For example, see the comparison of Agile and waterfall in Carnegie Mellon Software
                      Engineering Institute, Mary Ann Lapham, et al., Considerations for Using Agile in DOD
                      Acquisition (Pittsburgh, Pa: April 2010).




                      Page 4                         GAO-12-681 Agile Effective Practices and Federal Challenges
    the number of iterations dependent on the scope of the multistep
    process. To meet the goal of delivering working software, teams
    perform each of the steps of traditional software development for each
    iteration. Specifically, for each iteration, the teams identify
    requirements, design, and develop software to meet those
    requirements, and test the resulting software to determine if it meets
    the stated requirements. In contrast, waterfall development proceeds
    in sequential phases of no consistent, fixed duration to produce a
    complete system, such as one that addresses a comprehensive set of
    steps to manage insurance claims. Such full system development
    efforts can take several years. Waterfall phases typically address a
    single step in the development cycle. For example, in one phase,
    customer requirements for the complete product are documented,
    reviewed, and handed to technical staff. One or more phases follow,
    in which the technical staff develop software to meet those
    requirements. In the final phase, the software is tested and reviewed
    for compliance with the identified requirements.

•   Timing and scope of project planning. In Agile, initial planning
    regarding cost, scope, and timing is conducted at a high level.
    However, these initial plans are supplemented by more specific plans
    for each iteration and the overall plans can be revised to reflect
    experience from completed iterations. For example, desired project
    outcomes might initially be captured in a broad vision statement that
    provides the basis for developing specific outcomes for an iteration.
    Once an iteration has been completed, the overall plans can be
    revised to reflect the completed work and any knowledge gained
    during the iteration. For example, initial cost and schedule estimates
    can be revised to reflect the actual cost and timing of the completed
    work. In contrast, in traditional waterfall project management, this
    analysis is documented in detail at the beginning of the project for the
    entire scope of work. For example, significant effort may be devoted
    to documenting strategies, project plans, cost and schedule
    estimates, and requirements for a full system.

•   Project status evaluation. In Agile, project status is primarily
    evaluated based on software demonstrations. For example, iterations
    typically end with a demonstration for customers and stakeholders of
    the working software produced during that iteration. The
    demonstration can reveal requirements that were not fully addressed
    during the iteration or the discovery of new requirements. These
    incomplete or newly-identified requirements are queued for possible
    inclusion in later iterations. In contrast, in traditional project
    management, progress is assessed based on a review of data and


Page 5                    GAO-12-681 Agile Effective Practices and Federal Challenges
     documents at predetermined milestones and checkpoints. Milestones
     and checkpoints can occur at the end of a phase, such as the end of
     requirements definition, or at scheduled intervals, such as monthly.
     The reviews typically include status reports on work done to date and
     a comparison of the project’s actual cost and schedule to baseline
     projections. Federal IT evaluation guidance, such as our IT
     Investment Management guidance 8 and OMB IT reporting
     requirements 9 specify evaluations at key milestones, and annually,
     which more closely align with traditional development methods. For
     example, for major projects, OMB requires a monthly comparison of
     actual and planned cost and schedule and risk status and annual
     performance measures using, for example, earned value
     management (EVM). 10

•    Collaboration. Agile development emphasizes collaboration more
     than traditional approaches do. For example, to coordinate the many
     disciplines of an iteration, such as design and testing, customers work
     frequently and closely with technical staff. Furthermore, teams are
     often self-directed, meaning tasks and due dates are done within the
     team and coordinated with project sponsors and stakeholders as
     needed to complete the tasks. In contrast, with traditional project
     management, customer and technical staff typically work separately,
     and project tasks are prescribed and monitored by a project manager,
     who reports to entities such as a program management office.

See figure 1 for a depiction of Agile development compared to waterfall
development.




8
 GAO, Information Technology Investment Management: A Framework for Assessing and
Improving Process Maturity, GAO-04-394G (Washington, D.C.: March 2004).
9
 For certain IT investments, OMB requires an annual report called the exhibit 300 and
monthly status on a website called the IT Dashboard (http://www.itdashboard.gov/).
10
  EVM is a tool for measuring a project’s progress by comparing the value of work
accomplished with the amount of work expected to be completed, and is based on
variances from cost and schedule baselines.




Page 6                         GAO-12-681 Agile Effective Practices and Federal Challenges
Figure 1: Comparison of Agile and Waterfall Development




Agile Frameworks                        There are numerous frameworks available to Agile practitioners. One
                                        framework, called eXtreme Programming (XP), includes development
                                        techniques. 11 Another framework, called Scrum, defines management
                                        processes and roles. The Scrum framework is widely used in the public
                                        and private sector, and its terminology is often used in Agile discussions.
                                        For example, Scrum iterations are called sprints, which are bundled into
                                        releases. Sprint teams collaborate with minimal management direction,
                                        often co-located in work rooms. They meet daily and post their task status
                                        visibly, such as on wall charts.

                                        Other concepts commonly used by sprint teams are user stories, story
                                        points, and backlog. User stories convey the customers’ requirements. A



                                        11
                                          For example, XP includes technical practices such as test-driven development, in which
                                        the test of software code to meet a requirement is written before writing the operational
                                        code.




                                        Page 7                         GAO-12-681 Agile Effective Practices and Federal Challenges
                           user story typically follows the construct of “As a <type of user> I want
                           <some goal> so that <some reason>.” For example, “As a claims
                           processor, I want to check a claim payment status so that I can promptly
                           reply to a customer’s request for payment status.” Each user story is
                           assigned a level of effort, called story points, which are a relative unit of
                           measure used to communicate complexity and progress between the
                           business and development sides of the project. To ensure that the
                           product is usable at the end of every iteration, teams adhere to an
                           agreed-upon definition of done. This includes stakeholders defining how
                           completed work conforms to an organization’s standards, conventions,
                           and guidelines. The backlog is a list of user stories to be addressed by
                           working software. If new requirements or defects are discovered, these
                           can be stored in the backlog to be addressed in future iterations.

                           Progress in automating user stories is tracked daily using metrics and
                           tools. An example of a metric is velocity. Velocity tracks the rate of work
                           using the number of story points completed or expected to be completed
                           in an iteration. For example, if a team completed 100 story points during a
                           four-week iteration, the velocity for the team would be 100 story points
                           every four weeks. An example of a tool is a burn-down chart, which tracks
                           progress and the amount of work remaining for an iteration or for a
                           release, which is made up of multiple iterations.


Agile in the Private and   Agile use is reported in the private sector for small to medium sized
Federal Sectors            projects and is starting to be used for larger projects as well. Also, widely
                           accepted industry guidance on software development has recently been
                           revised to include more Agile approaches. Specifically, the Software
                           Engineering Institute’s Capability Maturity Model® Integration 12 updated
                           some process areas to help those using Agile to interpret its practices.

                           Furthermore, the federal government has begun to use Agile. For
                           example, we have reported on several federal software development
                           efforts that have used Agile techniques. Specifically, in December 2010




                           12
                             The Software Engineering Institute is a nationally recognized, federally funded research
                           and development center established at Carnegie Mellon University to address software
                           engineering practices. The institute has developed process maturity models for software
                           development, including CMMI® for Development, Version 1.3, Improving Processes for
                           Developing Better Products and Services, (Pittsburgh, Pa: November 2010).




                           Page 8                         GAO-12-681 Agile Effective Practices and Federal Challenges
                          we reported 13 that the Department of Veterans Affairs was using Agile to
                          develop software to support a new benefit for veterans. We also
                          reported 14 that the Department of Defense was developing the Global
                          Combat Support System-Joint system using Agile. In addition, the
                          department sponsored studies that examined the possibility of more
                          widespread use of Agile in its development projects. 15


                          We identified 32 practices and approaches 16 as effective for applying
Effective Practices for   Agile to software development projects, based on an analysis of practices
Applying Agile            identified by experienced Agile users. Our analysis also found that the
                          identified practices generally align with five key project management
                          activities outlined in widely-accepted software development guidance:
                          strategic planning, organizational commitment and collaboration,
                          preparation, execution, and evaluation.


Strategic Planning        Strategic planning describes an organization’s overall plans in an Agile
                          environment. Six practices align with strategic planning. They are:

                          •     Strive to be more Agile, rather than simply following Agile
                                methods and steps. This approach encourages adoption of the
                                philosophy, or mindset, rather than specific steps. This is also referred
                                to as being Agile, or having agility versus using it.

                          •     Allow for a gradual migration to Agile appropriate to your
                                readiness. Migration steps might include combining Agile and



                          13
                            GAO, Information Technology: Veterans Affairs Can Further Improve Its Development
                          Process for Its New Education Benefits System, GAO-11-115 (Washington, D.C.: Dec. 1,
                          2010).
                          14
                              GAO-12-7.
                          15
                            Carnegie Mellon Software Engineering Institute, Mary Ann Lapham, et al.,
                          Considerations for Using Agile in DOD Acquisition (Pittsburgh, Pa: April 2010); and Agile
                          Methods: Selected DOD Management and Acquisition Concerns (Pittsburgh, Pa: October
                          2011).
                          16
                             Although we asked the experienced users to identify effective practices, several of the
                          items they identified can be considered more of an approach, or way to think about
                          proceeding, than practices that describe how something should be done. This aligns with
                          the concept of Agile being as much a philosophy as a set of steps to be followed.




                          Page 9                         GAO-12-681 Agile Effective Practices and Federal Challenges
                     existing methods, conducting pilots, and preparing technical
                     infrastructure.

                 •   Observe and communicate with other organizations
                     implementing Agile. For example, those starting to use Agile can
                     consult with others who have more experience, including academic,
                     private sector, and federal practitioners.

                 •   Follow organizational change disciplines, such as establishing a
                     sense of urgency and developing a change vision. A clear vision
                     of change helps staff understand what the organization is trying to
                     achieve. Another organizational change discipline is communication
                     strategies.

                 •   Be prepared for difficulties, regression, and negative attitudes.
                     This approach reinforces that Agile is not painless and users may
                     backslide to entrenched software methods.

                 •   Start with Agile guidance and an Agile adoption strategy. This
                     practice advocates having these elements in place at the start, even if
                     they must be copied from external sources.


Organizational   Organizational commitment describes the management actions that are
Commitment and   necessary to ensure that a process is established and will endure.
Collaboration    Collaboration in Agile typically refers to the close and frequent interaction
                 of teams. Four practices align with organizational commitment and
                 collaboration:

                 •   Ensure all components involved in Agile projects are committed
                     to the organization’s Agile approach. This practice encourages
                     organizations to ensure that everyone contributing to a project
                     understands and commits to the organization’s approach. This
                     includes those working directly on the project and those with less
                     direct involvement, such as those providing oversight.

                 •   Identify an Agile champion within senior management. This
                     practice calls for someone with formal authority within the organization
                     to advocate the approach and resolve impediments at this level.

                 •   Ensure all teams include coaches or staff with Agile experience.
                     This practice stresses the importance of including on each team those




                 Page 10                    GAO-12-681 Agile Effective Practices and Federal Challenges
                  with direct experience in applying Agile. While training is helpful,
                  hands on experience helps the team members learn and adjust.

              •   Empower small, cross-functional teams. Empowered teams of 7 to
                  18 people decide what to deliver and how to produce it. The teams
                  should not over-rely on one member’s skills.


Preparation   Taking certain preparatory steps prior to the start of an iteration can
              facilitate a rapid development pace. The following eight practices
              generally align with the preparation of people and processes.

              •   Train the entire organization in your Agile approach and mindset,
                  and train Agile practitioners in your Agile methods. For example,
                  managers must understand the approach so that they know how it will
                  affect them and teams need to know the specific steps of an iteration
                  to conduct it properly.

              •   Ensure that subject matter experts and business team members
                  have the required knowledge. This practice stresses that staff
                  involved in fast-paced iterations must truly be experts in the
                  processes being automated in that iteration in order to reduce delays.
                  For example, a team member representing financial customers must
                  be fully familiar with the needs of those customers.

              •   Enhance migration to Agile concepts using Agile terms and
                  examples. For example, use terms like user stories instead of
                  requirements, and Agile Center of Excellence instead of Project
                  Management Office. Provide examples, such as one illustrating the
                  small scope of a user story to teams writing these stories.

              •   Create a physical environment conducive to collaboration. A
                  common practice is to co-locate the team in a single room where they
                  can continually interact. Other ways to enhance collaboration are to
                  reorganize office space and use tools to connect remote staff.

              •   Identify measurable outcomes, not outputs, of what you want to
                  achieve using Agile. An example of this practice is creating a vision
                  statement of project outcomes (such as a decrease in processing time
                  by a specific percent in a set time), rather than outputs (such as the
                  amount of code produced).

              •   Negotiate to adjust oversight requirements to a more Agile
                  approach. This practice notes that teams may be able to adjust


              Page 11                    GAO-12-681 Agile Effective Practices and Federal Challenges
                oversight requirements by using frequent, tangible demonstrations to
                gain the trust of reviewers and investors, potentially reducing the need
                for more formal oversight documents.

            •   Ensure that the definition of how a story will be determined to be
                done is comprehensive and objective. Comprehensiveness
                includes defining what constitutes a finished product (i.e., packaged,
                documented, tested, and independently verified). Objective means
                measurable or verifiable versus subjective judgment.

            •   Make contracts flexible to accommodate your Agile approach.
                Contracts requiring waterfall-based artifacts and milestone reviews
                may not support the frequent changes and product demonstrations in
                iterations, and may inhibit adoption.


Execution   Execution entails the concrete steps necessary to conduct the iteration
            following the designated approach. The seven identified practices that
            align with execution are:

            •   Use the same duration for each iteration. An example would be
                establishing that iterations will be four weeks each within a release to
                establish a uniform pace.

            •   Combine Agile frameworks such as Scrum and XP if appropriate.
                Disciplines from different frameworks can be combined. For example,
                use project management disciplines from Scrum and technical
                practices from XP.

            •   Enhance early customer involvement and design using test-
                driven development. Test-driven development refers to writing
                software code to pass a test. This practice maintains that involving
                customers in these tests helps to engage them in the software
                development process.

            •   Include requirements related to security and progress
                monitoring in your queue of unfinished work (backlog). Including
                activities such as security reviews and status briefings in the backlog
                ensures their time and cost are reflected and that they are addressed
                concurrent with, and not after, iteration delivery.

            •   Capture iteration defects in a tool such as a backlog. This practice
                calls for queuing issues so that they are resolved in later iterations.
                For example, lists of unmet requirements generated at end-of-iteration


            Page 12                   GAO-12-681 Agile Effective Practices and Federal Challenges
                 demonstrations should be queued in the backlog for correction in a
                 future iteration.

             •   Expedite delivery using automated tools. For example, tools can
                 track software modifications, and compliant development sites or
                 “sandboxes” help customers conceptualize the software in an
                 environment that meets architectural and security standards.

             •   Test early and often throughout the life cycle. The theme of this
                 practice is that testing during software code delivery instead of after
                 delivery reduces risk and remediation costs.


Evaluation   Evaluations can occur at the project and organizational level. For
             example, at the project level, the iteration is reviewed at its completion in
             a retrospective. At the organizational level, processes are reviewed for
             opportunities to improve the approach. The following seven practices
             align with evaluation:

             •   Obtain stakeholder/customer feedback frequently and closely.
                 For example, feedback is obtained during the iteration and at its
                 completion at an iteration retrospective. This practice was linked to
                 reducing risk, improving customer commitment, and improving
                 technical staff motivation.

             •   Continuously improve Agile adoption at both the project level
                 and organization level. This practice invokes the discipline of
                 continuous improvement, meaning always looking for ways to
                 improve. For example, improvements can be made by adding
                 automated test and version control tools, and enhancing team rooms.
                 These issues can be tracked in project and organizational-level
                 backlogs.

             •   Seek to identify and address impediments at the organization
                 and project levels. This practice encourages organizations to be
                 frank about identifying impediments so that they can be addressed.

             •   Determine project value based on customer perception and
                 return on investment. This practice recognizes that tracking
                 progress only against cost or schedule criteria set before the project
                 began could lead to inaccurate measurement of progress if, for
                 example, major changes in scope occur. Instead, Agile encourages




             Page 13                    GAO-12-681 Agile Effective Practices and Federal Challenges
                                customer feedback as one measure of progress. Comparing solution
                                value to the cost of the solution is also a gauge of success.

                           •    Gain trust by demonstrating value at the end of each iteration.
                                This practice includes demonstrating key requirements in early
                                iterations, and showing customers that requirements in the backlog
                                are delivered and not forgotten.

                           •    Track progress using tools and metrics. Progress can be tracked
                                using tools and metrics such as burn-down charts and velocity, which
                                can be automated, and by success indicators such as “customer
                                delight,” and reduced staff stress and overtime.

                           •    Track progress daily and visibly. This practice stresses that status
                                is checked daily and publicly. For example, a progress chart is posted
                                openly in the team’s workspace, with timely revisions to reflect
                                ongoing feedback.


Federal Use of Effective   Officials who have used Agile on federal projects at five agencies
Practices                  generally agreed that the practices identified by the experienced users
                           are effective in a federal setting. Specifically, each practice was used and
                           found effective by officials from at least one agency. Ten of the 32
                           practices were used and found effective by officials at all five agencies
                           (see table 1).

                           Table 1: Practices Used and Found Effective by Five Agencies

                            Practice
                            1. Start with Agile guidance and an Agile adoption strategy.
                            2. Enhance migration to Agile concepts using Agile terms and examples.
                            3. Continuously improve Agile adoption at both project and organization levels.
                            4. Seek to identify and address impediments at the organization and project levels.
                            5. Obtain stakeholder/customer feedback frequently and closely.
                            6. Empower small, cross-functional teams.
                            7. Include requirements related to security and progress monitoring in your queue of
                            unfinished work (backlog).
                            8. Gain trust by demonstrating value at the end of each iteration.
                            9. Track progress using tools and metrics.
                            10. Track progress daily and visibly.
                           Source: GAO.




                           Page 14                         GAO-12-681 Agile Effective Practices and Federal Challenges
                        Also, in most cases, a practice was still believed to be effective even if it
                        was not used. For example, officials explained that they did not use a
                        practice they indicated was effective because it was not appropriate for
                        their project or that they used an alternate practice.

                        Although the identified practices were generally described as effective,
                        officials from three agencies each reported one practice they had used
                        but found to be not effective. According to the agency officials, two
                        practices were identified as ineffective because they were difficult to
                        implement. These practices were: (1) ensuring commitment from
                        components and (2) negotiating oversight requirements. The third
                        practice, striving to be Agile rather than simply following Agile methods,
                        was described by an agency official as not effective because he believed
                        that strict adherence was necessary for a successful project.


                        We identified 14 challenges with adapting to and applying Agile in the
Federal Challenges in   federal environment based on an analysis of experiences collected from
Applying Agile          five federal agencies that had applied Agile to a development effort.
                        These challenges relate to significant differences in not only how software
                        is developed but also how projects are managed in an Agile development
                        environment versus a waterfall development environment. We aligned the
                        challenges with four of the project management activities used to
                        organize effective practices: (1) ensuring organizational commitment and
                        collaboration, (2) preparing for Agile, (3) executing development in an
                        Agile environment, and (4) evaluating the product and project. In addition
                        to identifying challenges, federal officials described efforts underway at
                        their agencies to address these challenges.


Organizational          As described in the effective practices, Agile projects require the ongoing
Commitment and          collaboration and commitment of a wide array of stakeholders, including
Collaboration           business owners, developers, and security specialists. One way Agile
                        promotes commitment and collaboration is by having teams work closely
                        together, in one location, with constant team communication. Officials at
                        the selected agencies identified challenges in achieving and maintaining
                        such commitment and collaboration from their stakeholders as follows.

                        •   Teams had difficulty collaborating closely: Officials from three
                            agencies reported that teams were challenged in collaborating
                            because staff were used to working independently. For example, one
                            official reported that staff were challenged when asked to relocate to a
                            team room because the technical staff preferred to work alone. The


                        Page 15                    GAO-12-681 Agile Effective Practices and Federal Challenges
    official added that some staff viewed open communication, such as
    posting project status on team room wall charts, as intrusive. A
    second official said that technical staff did not like constantly showing
    their work to customers. The third official said that customers initially
    did not want to see such development, preferring to wait for a polished
    product.

•   Teams had difficulty transitioning to self-directed work: Officials
    at two agencies reported that staff had challenges in transitioning to
    self-directed teams. In Agile, teams made up of customers and
    technical staff are encouraged to create and manage their tasks
    without project manager direction and to elevate issues to
    stakeholders who have the authority to resolve them. Cross
    functionality is also encouraged to allow teams to share tasks. One
    official reported that teams used to direction from a project manager
    were challenged in taking responsibility for their work and in elevating
    issues they could not resolve within the team to senior officials. A
    second official noted that it was a challenge to create cross-functional
    teams because federal staff tend to be specialists in one functional
    area. An example of this would be where a team could include
    someone to represent system users, but that person may not be
    familiar with the needs of all users. Specifically, a team developing an
    insurance system might include someone with a background in claims
    processing. However, that person may not be experienced with
    payment procedures.

•   Staff had difficulty committing to more timely and frequent input:
    While Agile advocates frequent input and feedback from all
    stakeholders, four agency officials noted challenges to commit to
    meeting such input expectations. One agency official noted that
    individuals were challenged to commit to keeping work products, such
    as schedules, updated to reflect the status of every iteration because
    they were not used to this rapid pace. A second official stated that
    teams initially had difficulty maintaining the pace of an iteration
    because they were used to stopping their work to address issues
    rather than making a decision and moving on. A third official said that
    it was challenging incorporating security requirements at the rapid
    pace of the sprint. A fourth official said customer availability was a
    challenge because customers initially did not understand the amount
    and pace of the time commitment for Agile and needed to develop a
    mindset to attend meetings as well as frequently review deliverables.

•   Agencies had trouble committing staff: Three agency officials
    reported being challenged assigning and maintaining staff


Page 16                   GAO-12-681 Agile Effective Practices and Federal Challenges
                  commitments to projects. The frequent input expected of staff involved
                  in projects requires a more significant time commitment than that
                  required for waterfall development projects that allow more sporadic
                  participation. For example, two officials said their agencies were
                  challenged dedicating staff with multiple, concurrent duties to teams
                  because staff could not be spared from their other duties while
                  participating in the Agile teams. The third official said stakeholder
                  commitment is challenging to maintain when stakeholders rotate
                  frequently and new staff need to learn the roles and responsibilities of
                  those being replaced.


Preparation   When an organization following waterfall software development migrates
              to Agile, new tools and technical environments may be required to
              support that approach, as well as updates to guidance and procurement
              strategies. Officials described challenges in preparing for Agile as follows.

              •   Timely adoption of new tools was difficult: As identified in the
                  effective practices, automated tools may be used to support project
                  planning and reporting. One official noted that implementing Agile
                  tools that aid in planning and reporting progress was initially a
                  challenge because there was a delay in buying, installing, and
                  learning to use these tools.

              •   Technical environments were difficult to establish and maintain:
                  Two agency officials noted that establishing and maintaining technical
                  environments posed challenges because Agile calls for development,
                  test, and operational activities to be performed concurrently.
                  According to one agency’s officials, preparing and maintaining
                  synchronized hardware and software environments for these three
                  activities in time to support the releases was expensive to support and
                  logistically challenging. Furthermore, one of these officials noted that
                  his agency experienced a challenge running multiple concurrent
                  iterations because this required more complex coordination of staff
                  and resources.

              •   Agile guidance was not clear: Officials from three agencies
                  identified a challenge related to the lack of clear guidance for Agile
                  software development, particularly when agency software
                  development guidance reflected a waterfall approach. For example,
                  one official said that it was challenging to develop policy and
                  procedure guidance for iterative projects because they were new, and
                  the agency strategy aligned with the waterfall approach. As a result, it
                  was difficult to ensure that iterative projects could follow a standard


              Page 17                   GAO-12-681 Agile Effective Practices and Federal Challenges
                approach. A second official reported that deviating from waterfall-
                based procedural guidance to follow Agile methods made people
                nervous. For example, staff were nervous following team versus
                project manager directed tasks because this approach was not in their
                IT guidance. A third official said that their guidance mixed iterative and
                waterfall life cycle approaches, which staff found confusing.

            •   Procurement practices may not support Agile projects: Agile
                projects call for flexibility adding the staff and resources needed to
                meet each iteration, and to adapt to changes from one iteration to the
                next. One official stated that working with federal procurement
                practices presents a challenge where they do not support the flexibility
                required. For example, he said that federal contracts that require
                onerous, waterfall-based artifacts to constantly evaluate contractor
                performance are not needed in an Agile approach when the contractor
                is part of the team whose performance is based on the delivery of an
                iteration. Furthermore, the official said that they are challenged
                changing contractor staff in time to meet iteration time frames and that
                accommodating task changes from one iteration to the next is
                challenging because contracting officers require cumbersome
                traditional structured tasks and performance checks.


Execution   As described in the effective practices, Agile projects develop software
            iteratively, incorporating requirements and product development within an
            iteration. Such requirements may include compliance with agency legal
            and policy requirements. Officials reported challenges executing steps
            related to iterative development and compliance reviews as follows.

            •   Customers did not trust iterative solutions: Agile software
                products are presented to customers incrementally, for approval at the
                end of each iteration, instead of presenting complete products for
                approval at waterfall milestones. Officials at two agencies reported a
                challenge related to customer mistrust of iterative solutions.
                Specifically, one agency official said customers expecting a total
                solution feared that the initial demonstrations of functionality provided
                in the current iteration would be considered good enough, and they
                would not receive further software deliveries implementing the
                remainder of their requirements. At another agency, an official said
                this fear contributed to customers finding it difficult to define done.
                Specifically, customers were challenged in defining when each
                requirement would be considered done because they were afraid that
                this would be viewed as meaning all related functions were being met,



            Page 18                    GAO-12-681 Agile Effective Practices and Federal Challenges
                 and that unmet requirements would be dropped and never
                 implemented.

             •   Teams had difficulty managing iterative requirements: Teams
                 provide input on prioritizing requirements, and deciding what to do
                 with new requirements discovered during iterations. Two agencies’
                 officials reported challenges managing requirements. Specifically, one
                 official reported that customers were initially challenged to validate
                 and prioritize which requirements would be assigned to a release.
                 Using the waterfall development model, they were used to identifying
                 all requirements up front and not revisiting them as they were
                 developed. The second official said they were challenged to
                 accommodate new requirements within the fixed schedule for a
                 product release.

             •   Compliance reviews were difficult to execute within an iteration
                 time frame: Iterations may incorporate compliance reviews to ensure,
                 for example, that agency legal and policy requirements are being met
                 within the iteration. One agency official reported a challenge obtaining
                 compliance reviews within the short, fixed time frame of an iteration
                 because reviewers followed a slower waterfall schedule. Specifically,
                 the official said that compliance reviewers queued requests as they
                 arose and that the reviews could take months to perform. This caused
                 delays for iterations that needed such reviews within the few weeks of
                 the iteration.


Evaluation   Agile advocates evaluation of working software over the documentation
             and milestone reporting typical in traditional project management.
             Officials described challenges in evaluating projects related to the lack of
             alignment between Agile and traditional evaluation practices. Specifically,
             officials explained that:

             •   Federal reporting practices do not align with Agile: Two agency
                 officials noted that several federal reporting practices do not align with
                 Agile, creating challenges. For example, one official said federal
                 oversight bodies want status reports at waterfall-based milestones
                 rather than timely statements regarding the current state of the
                 project. The second official said OMB’s IT investment business case
                 (known as the exhibit 300) and IT Dashboard, a publicly available




             Page 19                    GAO-12-681 Agile Effective Practices and Federal Challenges
    website that displays detailed information on federal agencies’ major
    IT investments, 17 are waterfall-based. For example, the IT Dashboard
    calls for monthly statistics instead of demonstrations of working
    software. He also noted that it is frustrating when dashboard statistics
    are flagged in red to note deviations, even when the deviation is
    positive, such as being ahead of schedule and under cost.

•   Traditional artifact reviews do not align with Agile: Traditional
    oversight requires detailed artifacts in the beginning of a project, such
    as cost estimates and strategic plans, while Agile advocates
    incremental analysis. One agency official noted that requiring these
    artifacts so early was challenging because it was more worthwhile to
    start with a high-level cost estimate and vision to be updated as the
    solution was refined through iterations, rather than spending time
    estimating costs and strategies that may change.

•   Traditional status tracking does not align with Agile: Officials from
    three agencies noted that project status tracking in Agile does not
    align with traditional status tracking methods, creating challenges. For
    example, one official said that tracking the level of effort using story
    points instead of the traditional estimating technique based on hours
    was a challenge because team members were not used to that
    estimation method, although eventually this method was embraced.
    Two other agency officials said EVM was challenging to apply in an
    Agile environment. Specifically, one official said that the required use
    of EVM was challenging because there was no guidance on how to
    adapt it to iterations. The second official found EVM challenging
    because the agency was required to use it to track changes in cost,
    schedule, and product scope through monthly reports, and changes
    were viewed as control problems rather than as revisions to be
    expected during an iteration. For example, the project’s scope was
    prioritized within every iteration based on the cost and schedule limits
    of the iteration and release. He also noted that risk tracking in Agile
    does not align with traditional risk tracking methods because issues
    are addressed within an iteration rather than queued, such as in a
    traditional monthly risk log.




17
  The IT Dashboard includes assessments of actual performance against cost and
schedule targets (referred to as ratings) for approximately 800 major federal IT
investments. The IT Dashboard website is located at http://www.itdashboard.gov/.




Page 20                       GAO-12-681 Agile Effective Practices and Federal Challenges
              In addition to identifying challenges, federal officials described their efforts
              to address these challenges. For example, officials said they clarify
              policies to address the challenge of Agile guidance lacking clarity. To
              mitigate the challenge related to customers not trusting iterative solutions,
              an official said they call the iteration review a mini-critical design review.
              This helps customers understand that they must declare the iteration
              complete or not, known as committing to done. Another official said one
              way that they addressed the challenge related to teams having difficulty
              managing iterative requirements was to add an empty iteration to the end
              of the release schedule to accommodate requirements discovered during
              the iterations.

              In addition to the efforts at individual agencies to mitigate Agile
              challenges, the Federal CIO Council has begun an effort on a related
              topic. According to an official working with the Council, it is currently
              drafting a document on modular development. Consistent with OMB’s IT
              reform efforts, the document is expected to provide guidance for agencies
              seeking to use more modular development approaches, such as Agile.
              However, according to the official, the draft does not specifically address
              Agile effective practices. Also, in June 2012 OMB released contracting
              guidance to support modular development. 18 This guidance includes
              factors for contracting officers to consider for modular development efforts
              regarding for example, statements of work, pricing arrangements, and
              small business opportunities.


              As Agile methods begin to be more broadly used in federal development
Conclusions   projects, agencies in the initial stages of adopting Agile can benefit from
              the knowledge of those with more experience. The ongoing effort by the
              Federal CIO Council to develop guidance on modular development
              provides an excellent opportunity to share these experiences. The
              effective practices and approaches identified in this report, as well as
              input from others with broad Agile experience, can inform this effort.




              18
                OMB, Contracting Guidance to Support Modular Development (Washington, D.C.: June
              2012).




              Page 21                     GAO-12-681 Agile Effective Practices and Federal Challenges
                     To ensure that the experiences of those who have used Agile
Recommendation for   development are shared broadly, we recommend that the Federal CIO
Executive Action     Council, working with its chair, the Office of Management and Budget’s
                     Deputy Director for Management, include practices such as those
                     discussed in this report in the Council’s ongoing effort to promote modular
                     development in the federal government.


                     We provided a draft of our report to OMB and to the five federal agencies
Agency Comments      included in our review. In oral comments on the draft, OMB’s E-
and Our Evaluation   government program manager said that the draft recommendation was
                     better addressed to the Federal CIO Council than to the OMB official who
                     is the chair of the Council. Accordingly, we revised the recommendation
                     to address it to the Council, working with its chair, the OMB Deputy
                     Director for Management. Two of the five agencies provided written
                     comments on the draft, which are reprinted in appendix V and VI.
                     Specifically, the Department of Veterans Affairs Chief of Staff stated that
                     the department generally agreed with the draft’s findings, and the Acting
                     Secretary of the Department of Commerce stated that the Patent and
                     Trademark Office concurred with our assessment. Two other agencies,
                     the Internal Revenue Service and the Department of Defense, provided
                     technical comments via e-mail, which we incorporated as appropriate. In
                     an e-mail, a manager in the National Aeronautics and Space
                     Administration (NASA) center included in our review said that NASA had
                     no comments.




                     Page 22                   GAO-12-681 Agile Effective Practices and Federal Challenges
As agreed with your offices, we will send copies of this report to
interested congressional committees; the Secretaries of Defense,
Commerce, and Veterans Affairs; the Administrator of NASA and the
Commissioner of Internal Revenue; the Director of the Office of
Management and Budget; and other interested parties. In addition, the
report will be available at no charge on our website at http://www.gao.gov.

If you or your staff have any questions on the matters discussed in this
report, please contact David A. Powner at (202) 512-9286 or Dr.
Nabajyoti Barkakati at (202) 512-4499 or by e-mail at pownerd@gao.gov
or barkakatin@gao.gov. Contact points for our Offices of Congressional
Relations and Public Affairs may be found on the last page of this report.
GAO staff who made major contributions to this report are listed in
appendix VII.




David A. Powner
Director
Information Technology
Management Issues




Dr. Nabajyoti Barkakati
Director
Center for Technology and Engineering




Page 23                   GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix I: Objectives, Scope, and
              Appendix I: Objectives, Scope, and
              Methodology



Methodology

              Our objectives were to identify (1) effective practices in applying Agile for
              software development solutions and (2) federal challenges in
              implementing Agile development techniques.

              To identify effective practices, we interviewed a nongeneralizable sample
              of nine experienced users and a tenth experienced user helped us pre-
              test our data collection process. 1 To identify these users, we researched
              publications, attended forums, and obtained recommendations from
              federal and private officials knowledgeable about Agile. We selected
              individuals with Agile software development experience with public,
              private sector, and non-profit organizations. Using a structured interview,
              we asked them to identify effective practices when applying Agile
              methods to software development projects. We then compiled the
              reported practices and aligned and combined some with a broader
              practice. For example, practices related to preparation, such as mock and
              pilot iterations, were aligned and then combined into the final practice,
              “Allow for a gradual migration to Agile appropriate to your readiness.” If a
              practice did not align with other or broader practices, it was listed
              individually.

              We then sent the resulting list of practices in a questionnaire to our
              experienced users. This list was not organized into categories to ensure
              that each practice would be viewed individually. We asked our users to
              rate each practice as either (1) highly effective, (2) moderately effective,
              (3) somewhat effective, or (4) not applicable/do not know. We compiled
              the ratings and included in our list the practices that received at least six
              ratings of highly effective or moderately effective from the 8 experienced
              users who provided the requested ratings. 2 This resulted in 32 practices,
              which we aligned to key project management activities in Software
              Engineering Institute guidance: strategic planning, organizational
              commitment and collaboration, preparation, execution, and evaluation.
              This alignment was based on our best judgment.




              1
               Results from nongeneralizable samples cannot be used to make inferences about a
              population. To mitigate this limitation, our sample was designed to ensure we obtained
              highly-qualified users with a broad range of Agile experience across the private, public,
              and non-profit sectors.
              2
               The ninth experienced user was asked for input on the list of practices with the others,
              but did not respond in time to meet our reporting deadline.




              Page 24                         GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix I: Objectives, Scope, and
Methodology




To identify federal challenges, we interviewed officials responsible for five
federal software development projects that reported using Agile practices.
To identify the projects, we researched our previous work, federal
websites, and publications, and attended federal forums. We selected a
nongeneralizable sample of projects designed to reflect a range of
agencies, system descriptions, and cost (see app. IV for details about the
projects and the responsible officials). We then asked officials from each
project to identify federal challenges in implementing an Agile approach
using a structured interview. We summarized the challenges and
categorized them as aligning with either organizational commitment and
collaboration, preparation, execution, or evaluation. Separately, we sent
the federal officials a questionnaire listing the effective practices we
compiled based on input from our experienced users. The questionnaire
asked whether these practices were used and found effective. Although
our results are not generalizable to the population of software
development projects reporting the use of Agile practices, they provided
valuable insight into both the effective use and challenges in applying
Agile in the federal sector.

We conducted our work from October 2011 through July 2012 in
accordance with all sections of GAO’s Quality Assurance Framework that
are relevant to our objectives. The framework requires that we plan and
perform the engagement to obtain sufficient and appropriate evidence to
meet our stated objectives and to discuss any limitations in our work. We
believe that the information obtained provides a reasonable basis for our
findings and conclusions based on our audit objectives.




Page 25                        GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix II: The Agile Manifesto and
              Appendix II: The Agile Manifesto and
              Principles



Principles

              Agile development encompasses concepts that were previously used in
              software development. These concepts were documented as Agile
              themes and principles by 17 practitioners, who called themselves the
              Agile Alliance. In February 2001 the Alliance released “The Agile
              Manifesto,” 1 in which they declared: “We are uncovering better ways of
              developing software by doing it and helping others do it. Through this
              work we have come to value:

              •   individuals and interactions over processes and tools

              •   working software over comprehensive documentation

              •   customer collaboration over contract negotiation

              •   responding to change over following a plan.”

              The Alliance added that while they recognized the value in the second
              part of each statement (i.e., “processes and tools”), they saw more value
              in the first part (“individuals and interactions”). The Alliance further
              delineated their vision with twelve principles.

              The 12 Agile Principles behind the Manifesto
              •   Our highest priority is to satisfy the customer through early and
                  continuous delivery of valuable software.

              •   Welcome changing requirements, even late in development. Agile
                  processes harness change for the customer’s competitive advantage.

              •   Deliver working software frequently, from a couple of weeks to a
                  couple of months, with a preference to the shorter timescale.

              •   Business people and developers must work together daily throughout
                  the project.

              •   Build projects around motivated individuals. Give them the
                  environment and support they need, and trust them to get the job
                  done.




              1
               http://agilemanifesto.org.




              Page 26                         GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix II: The Agile Manifesto and
Principles




•   The most efficient and effective method of conveying information to
    and within a development team is face-to-face conversation.

•   Working software is the primary measure of progress.

•   Agile processes promote sustainable development. The sponsors,
    developers, and users should be able to maintain a constant pace
    indefinitely.

•   Continuous attention to technical excellence and good design
    enhances agility.

•   Simplicity—the art of maximizing the amount of work not done—is
    essential.

•   The best architectures, requirements, and designs emerge from self-
    organizing teams.

•   At regular intervals, the team reflects on how to become more
    effective, then tunes and adjusts its behavior accordingly.




Page 27                         GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix III: Experienced Users
              Appendix III: Experienced Users




              We interviewed the following experienced users to identify effective Agile
              practices. With one exception, they also contributed to the validation of
              our list of effective practices.

              •   Scott W. Ambler—Chief Methodologist for IT, IBM Rational

              •   Sanjiv Augustine—President, Lithespeed Consulting

              •   Gregor Bailar—Consultant

              •   Dr. Alan W. Brown—IBM Distinguished Engineer, Rational CTO for
                  Europe, IBM Software Group

              •   Neil Chaudhuri—President, Vidya, L.L.C; Senior Software Engineer,
                  Potomac Fusion

              •   Jerome Frese—Senior Enterprise Life Cycle Coach, Internal Revenue
                  Service

              •   Dr. Steven J. Hutchison—Senior Executive, Office of the Secretary of
                  Defense; Acquisition, Technology, and Logistics

              •   Mary Ann Lapham—Senior Member Technical Staff, Software
                  Engineering Institute, Carnegie Mellon University

              •   Greg Pfister—Vice President Software Engineering, Agilex
                  Technologies

              •   Bob Schatz—Senior Consultant and Advisor, Agile Infusion LLC




              Page 28                           GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix IV: Federal Project Profiles
                           Appendix IV: Federal Project Profiles




                           The five federal software development projects that reported challenges
                           in applying Agile practices are profiled as follows.


Global Combat Support      Table 2: Profile of Global Combat Support System-J Increment 7
System-Joint Increment 7
                                                               Department of Defense, Defense Information
                            Agency                             Systems Agency
                            System description                 Supports logistics operations such as mission supplies
                                                               for military personnel.
                            Agile approach                     Scrum
                            Estimated cost                     $192.3 million over a 5-year period
                            Officials interviewed included     Project and deputy project managers
                           Source: Agency data.




National Aeronautics and   Table 3: Profile of National Aeronautics and Space Administration Enterprise
Space Administration       Applications Competency Center Materials Management Initiative
Enterprise Applications     Agency                             National Aeronautics and Space Administration
Competency Center           System description                 Supports receipt, warehousing, inventory, and issuance
Materials Management                                           of operating materials and supplies.
Initiative                  Agile approach                     Scrum
                            Estimated cost                     $6.6 million
                            Officials interviewed included     Civilian project manager and manager in the National
                                                               Aeronautics and Space Administration Enterprise
                                                               Application Competency Center
                           Source: Agency data.




Patents End-to-End         Table 4: Profile of Patents End-to-End

                                                               Department of Commerce, Patent and Trademark
                            Agency                             Office
                            System description                 Supports end‐to‐end electronic patent processing.
                            Agile approach                     Scrum
                            Estimated cost                     $150 million over 5 years
                            Officials interviewed included     Chief information officer, deputy chief information
                                                               officer, patents portfolio manager, and other project
                                                               managers
                           Source: Agency data.




                           Page 29                           GAO-12-681 Agile Effective Practices and Federal Challenges
                        Appendix IV: Federal Project Profiles




Occupational Health     Table 5: Profile of Occupational Health Record-keeping System
Record-keeping System
                                                            Department of Veterans Affairs, Veterans Health
                         Agency                             Administration
                         System description                 Supports private employee health records.
                         Agile approach                     Scrum
                         Estimated cost                     $20 million for development and operation
                         Officials interviewed included     Current and previous IT project managers
                        Source: Agency data.




Affordable Care Act     Table 6: Profile of Affordable Care Act Branded Prescription Drugs
Branded Prescription
                         Agency                             Internal Revenue Service
Drugs
                         System description                 Supports pharmaceutical fee and payment tracking.
                         Agile approach                     Iterative with some Agile practices
                         Estimated cost                     $40 to $44M over 10 years
                         Officials interviewed included     Associate chief information officer and program
                                                            manager
                        Source: Agency data.




                        Page 30                           GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix V: Comments from the Department
             Appendix V: Comments from the Department
             of Veterans Affairs



of Veterans Affairs




             Page 31                      GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix V: Comments from the Department
of Veterans Affairs




Page 32                      GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix VI: Comments from the
             Appendix VI: Comments from the Department
             of Commerce



Department of Commerce




             Page 33                      GAO-12-681 Agile Effective Practices and Federal Challenges
Appendix VII: GAO Contacts and Staff
                  Appendix VII: GAO Contacts and Staff
                  Acknowledgments



Acknowledgments

                  David A. Powner, (202) 512-9286 or pownerd@gao.gov
GAO Contacts      Dr. Nabajyoti Barkakati, (202) 512-4499 or barkakatin@gao.gov


                  In addition to the contact names above, individuals making contributions
Staff             to this report included James R. Sweetman, Jr. (assistant director), Jenny
Acknowledgments   Chanley, Neil Doherty, Rebecca Eyler, Claudia Fletcher, Nancy Glover,
                  and Karl Seifert.




(311262)
                  Page 34                        GAO-12-681 Agile Effective Practices and Federal Challenges
GAO’s Mission         The Government Accountability Office, the audit, evaluation, and
                      investigative arm of Congress, exists to support Congress in meeting its
                      constitutional responsibilities and to help improve the performance and
                      accountability of the federal government for the American people. GAO
                      examines the use of public funds; evaluates federal programs and
                      policies; and provides analyses, recommendations, and other assistance
                      to help Congress make informed oversight, policy, and funding decisions.
                      GAO’s commitment to good government is reflected in its core values of
                      accountability, integrity, and reliability.

                      The fastest and easiest way to obtain copies of GAO documents at no
Obtaining Copies of   cost is through GAO’s website (www.gao.gov). Each weekday afternoon,
GAO Reports and       GAO posts on its website newly released reports, testimony, and
                      correspondence. To have GAO e-mail you a list of newly posted products,
Testimony             go to www.gao.gov and select “E-mail Updates.”

Order by Phone        The price of each GAO publication reflects GAO’s actual cost of
                      production and distribution and depends on the number of pages in the
                      publication and whether the publication is printed in color or black and
                      white. Pricing and ordering information is posted on GAO’s website,
                      http://www.gao.gov/ordering.htm.
                      Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
                      TDD (202) 512-2537.
                      Orders may be paid for using American Express, Discover Card,
                      MasterCard, Visa, check, or money order. Call for additional information.
                      Connect with GAO on Facebook, Flickr, Twitter, and YouTube.
Connect with GAO      Subscribe to our RSS Feeds or E-mail Updates. Listen to our Podcasts.
                      Visit GAO on the web at www.gao.gov.
                      Contact:
To Report Fraud,
Waste, and Abuse in   Website: www.gao.gov/fraudnet/fraudnet.htm
                      E-mail: fraudnet@gao.gov
Federal Programs      Automated answering system: (800) 424-5454 or (202) 512-7470

                      Katherine Siggerud, Managing Director, siggerudk@gao.gov, (202) 512-
Congressional         4400, U.S. Government Accountability Office, 441 G Street NW, Room
Relations             7125, Washington, DC 20548

                      Chuck Young, Managing Director, youngc1@gao.gov, (202) 512-4800
Public Affairs        U.S. Government Accountability Office, 441 G Street NW, Room 7149
                      Washington, DC 20548