             Report to Congressional Requesters




             INFORMATION
June 2019




             TECHNOLOGY

             Agencies Need to
             Develop
             Modernization Plans
             for Critical Legacy
             Systems




GAO-19-471
                                               June 2019

                                               INFORMATION TECHNOLOGY
                                               Agencies Need to Develop Modernization Plans for
                                               Critical Legacy Systems
Highlights of GAO-19-471, a report to
congressional requesters




Why GAO Did This Study                         What GAO Found
The federal government plans to spend          Among the 10 most critical legacy systems that GAO identified as in need of
over $90 billion in fiscal year 2019 on        modernization (see table 1), several use outdated languages, have unsupported
IT. About 80 percent of this amount is         hardware and software, and are operating with known security vulnerabilities. For
used to operate and maintain existing          example, the selected legacy system at the Department of Education runs on
IT investments, including aging (also          Common Business Oriented Language (COBOL)—a programming language that
called legacy) systems. As they age,           has a dwindling number of people available with the skills needed to support it. In
legacy systems can be more costly to           addition, the Department of the Interior’s system contains obsolete hardware that
maintain, more exposed to                      is not supported by the manufacturers. Regarding cybersecurity, the Department
cybersecurity risks, and less effective
                                               of Homeland Security’s system had a large number of reported vulnerabilities, of
in meeting their intended purpose.
                                               which 168 were considered high or critical risk to the network as of September
GAO was asked to review federal                2018.
agencies’ legacy systems. This report
(1) identifies the most critical federal       Table 1: The 10 Most Critical Federal Legacy Systems in Need of Modernization
legacy systems in need of                                                                       Age of Age of       System                   Security
                                                                                                system, oldest      criticality              risk
modernization and evaluates agency                                                              in       hardware, (according                (according
plans for modernizing them, and (2)             Agency
                                                                                             a
                                                                                System name years        in years   to agency)               to agency)
identifies examples of legacy system            Department of Defense           System 1        14       3          Moderately               Moderate
modernization initiatives that agencies                                                                             high
considered successful.                          Department of Education         System 2        46       3          High                     High
                                                                                                                                b
                                                   Department of Health and               System 3       50           Unknown       High     High
To do so, GAO analyzed a total of 65               Human Services
legacy systems in need of                          Department of Homeland                 System 4       8 – 11
                                                                                                                  c
                                                                                                                      11            High     High
modernization that 24 agencies had                 Security
identified. Of these 65, GAO identified            Department of the Interior             System 5       18           18            High     Moderately
                                                                                                                                             high
the 10 most in need of modernization
                                                   Department of the Treasury             System 6       51           4             High     Moderately
based on attributes such as age,                                                                                                             low
criticality, and risk. GAO then analyzed           Department of Transportation           System 7       35           7             High     Moderately
agencies’ modernization plans for the                                                                                                        high
10 selected legacy systems against                 Office of Personnel                    System 8       34           14            High     Moderately
key IT modernization best practices.               Management                                                                                low
                                                   Small Business Administration          System 9       17           10            High     Moderately
The 24 agencies also provided 94                                                                                                             high
examples of successful IT                          Social Security Administration         System 10      45           5             High     Moderate
modernizations from the last 5 years.          Source: GAO analysis of agency data. | GAO-19-471
In addition, GAO identified other              a
                                                   Due to sensitivity concerns, GAO substituted a numeric identifier for the system names.
examples of modernization successes            b
                                                The agency stated that the system’s hardware had various refresh dates and was not able to identify
at these agencies. GAO then selected           the oldest hardware.
a total of five examples to highlight a        c
                                                The agency stated that the majority of the network’s hardware was purchased between 2008 and
mix of system modernization types and          2011.
a range of benefits realized.
                                               Of the 10 agencies responsible for these legacy systems, seven agencies (the
This is a public version of a sensitive        Departments of Defense, Homeland Security, the Interior, the Treasury; as well
report that is being issued                    as the Office of Personnel Management; Small Business Administration; and
concurrently. Information that agencies        Social Security Administration) had documented plans for modernizing the
deemed sensitive has been omitted.             systems (see table 2). The Departments of Education, Health and Human
                                               Services, and Transportation did not have documented modernization plans. Of
View GAO-19-471. For more information,         the seven agencies with plans, only the Departments of the Interior and
contact Carol C. Harris at (202) 512-4456 or   Defense’s modernization plans included the key elements identified in best
harriscc@gao.gov.                              practices (milestones, a description of the work necessary to complete the
                                               modernization, and a plan for the disposition of the legacy system). Until the
                                                                                                      United States Government Accountability Office
                                         Agencies Need to Develop Modernization Plans for Critical Legacy Systems




What GAO Recommends                      other eight agencies establish complete modernization plans, they will have an
                                         increased risk of cost overruns, schedule delays, and project failure.
In the sensitive report, GAO is making
a total of eight recommendations—one     Table 2: Extent to Which Agencies’ Legacy System Documented Modernization Plans Included
to each of eight agencies—to ensure      Key Elements
that they document modernization                                                                      Describes     Summarizes
plans for the selected legacy systems.                                                  Includes      work          planned
                                                                                        milestones to necessary to disposition
The eight agencies agreed with GAO’s                                         System     complete the  modernize     of legacy
                                                                                  a
findings and recommendations, and         Agency                             name       modernization system        system
                                          Department of Defense              System 1   Yes           Yes           Yes
seven of the agencies described plans
to address the recommendations.              Department of Education                     System 2    No modernization plan
                                             Department of Health and Human              System 3    No modernization plan
                                             Services
                                             Department of Homeland Security             System 4    No              Yes         No
                                             Department of the Interior                  System 5    Yes             Yes         Yes
                                             Department of the Treasury                  System 6    Partial         Yes         No
                                             Department of Transportation                System 7    No modernization plan
                                             Office of Personnel Management              System 8    Partial         Partial     No
                                             Small Business Administration               System 9    Yes             No          Yes
                                             Social Security Administration              System 10   Partial         Partial     No
                                         Source: GAO analysis of agency data. | GAO-19-471

                                         Agencies received a “partial” if the element was completed for a portion of the modernization.
                                         a
                                         Due to sensitivity concerns, GAO substituted a numeric identifier for the system names.
                                         The five examples that GAO selected of successful information technology (IT)
                                         modernization initiatives included transforming legacy code into a more modern
                                         programming language and moving legacy software to the cloud. Doing so
                                         allowed the agencies to reportedly leverage IT to successfully address their
                                         missions and achieve a wide range of benefits, including cost savings.




                                         Page ii                                                                                      Highlights
Contents


Letter                                                                                   1
                Background                                                               4
                GAO Identified 10 Critical Federal Legacy Systems; Agencies
                  Often Lack Complete Plans for Their Modernization                    13
                Agencies Reported a Variety of IT Modernization Successes              20
                Conclusions                                                            23
                Recommendations for Executive Action                                   23
                Agency Comments and Our Evaluation                                     23

Appendix I      Objectives, Scope, and Methodology                                     28



Appendix II     The 24 Chief Financial Officers Act Agencies’ Most Critical Legacy
                Systems in Need of Modernization                                       36



Appendix III    Profiles of the 10 Most Critical Legacy Systems in Need of
                Modernization                                                          39



Appendix IV     Comments from the Department of Education                              59



Appendix V      Comments from the Department of Health and Human Services              60



Appendix VI     Comments from the Department of Homeland Security                      62



Appendix VII    Comments from the Internal Revenue Service                             64



Appendix VIII   Comments from the Office of Personnel Management                       67




                Page i                                                 GAO-19-471 Legacy IT
Appendix IX     Comments from the Small Business Administration                       68



Appendix X      Comments from the Social Security Administration                      69



Appendix XI     Comments from the Department of Housing and Urban
                Development                                                           70



Appendix XII    Comments from the U.S. Agency for International Development           71



Appendix XIII   GAO Contact and Staff Acknowledgments                                 72


Tables
                Table 1: The 10 Most Critical Federal Legacy Systems in Need of
                        Modernization                                                 15
                Table 2: Extent to Which Agencies’ Legacy System Documented
                        Modernization Plans Included Key Elements                     18
                Table 3: Agency-Reported Examples of Successful Information
                        Technology (IT) Modernization Initiatives in the Last 5
                        Years and Associated Benefits                                 20
                Table 4: Attributes and Associated Point Values Used to Rank
                        Legacy Systems                                                31
                Table 5: Attributes and Associated Point Values Used to Rank
                        Legacy Systems in the Subsequent Round of Analysis            32
                Table 6: The 10 Selected Most Critical Legacy Systems in Need of
                        Modernization                                                 33
                Table 7: Combined List of Agencies’ Most Critical Legacy Systems
                        in Need of Modernization                                      36


Figures
                Figure 1: Airmen Maintaining an Air Force Aircraft                    40
                Figure 2: Photograph of a Dam                                         48




                Page ii                                               GAO-19-471 Legacy IT
Abbreviations

CIO                        Chief Information Officer
COBOL                      Common Business Oriented Language
DHS                        Department of Homeland Security
DOD                        Department of Defense
Education                  Department of Education
Energy                     Department of Energy
FAA                        Federal Aviation Administration
GSA                        General Services Administration
HHS                        Department of Health and Human Services
HUD                        Department of Housing and Urban Development
ICS                        Industrial Control System
IRS                        Internal Revenue Service
IT                         information technology
Interior                   Department of the Interior
Justice                    Department of Justice
LOUO                       limited official use only
MGT                        Modernizing Government Technology
NRC                        Nuclear Regulatory Commission
OIG                        Office of Inspector General
OMB                        Office of Management and Budget
OPM                        Office of Personnel Management
SCADA                      Supervisory Control and Data Acquisition
SBA                        Small Business Administration
SSA                        Social Security Administration
State                      Department of State
Transportation             Department of Transportation
Treasury                   Department of the Treasury
VA                         Department of Veterans Affairs


This is a work of the U.S. government and is not subject to copyright protection in the
United States. The published product may be reproduced and distributed in its entirety
without further permission from GAO. However, because this work may contain
copyrighted images or other material, permission from the copyright holder may be
necessary if you wish to reproduce this material separately.




Page iii                                                             GAO-19-471 Legacy IT
                       Letter




441 G St. N.W.
Washington, DC 20548




                       June 11, 2019

                       Congressional Requesters

                       According to the President’s Budget, the federal government plans to
                       spend over $90 billion in fiscal year 2019 on information technology (IT). 1
                       Of this amount, the government plans to spend about 80 percent on the
                       operations and maintenance of existing IT investments, including aging
                       (also called legacy) systems. 2

                       However, federal legacy systems are becoming increasingly obsolete. In
                       May 2016, we reported that many of the government’s IT investments
                       used outdated software languages and hardware parts that were
                       unsupported. 3 We also reported instances where agencies were using
                       systems that had components that were at least 50 years old or the
                       vendors were no longer providing support for hardware or software. As
                       they age, legacy systems can become more expensive to maintain, more
                       exposed to cybersecurity risks, and less effective in accomplishing their
                       intended purpose.

                       Accordingly, you asked us to review federal agencies’ legacy systems.
                       Our specific objectives were to (1) identify the most critical federal legacy
                       systems in need of modernization and evaluate plans for modernizing
                       them, and (2) identify examples of legacy system modernization initiatives
                       in the last 5 years that agencies considered successful.

                       This report presents a public version of a “limited official use only”
                       (LOUO) report that we are also issuing today. 4 The Department of
                       Homeland Security (DHS) and the Department of the Interior (Interior)
                       1
                        Office of Management and Budget, Analytical Perspectives, Budget of the United States
                       Government, Fiscal Year 2019 (Washington, D.C.: 2018) and Department of Defense,
                       Information Technology and Cyberspace Activities Budget Overview, Fiscal Year 2019
                       President’s Budget Request, (March 2018).
                       2
                        The Modernizing Government Technology (MGT) Act defines a legacy IT system as a
                       system that is outdated or obsolete. National Defense Authorization Act for Fiscal Year
                       2018, Pub. L. No. 115-91, Div. A, Title X, Subtitle G (2017).
                       3
                        GAO, Information Technology: Federal Agencies Need to Address Aging Legacy
                       Systems, GAO-16-468 (Washington, D.C.: May 25, 2016).
                       4
                        GAO, Information Technology: Agencies Need to Develop Modernization Plans for
                       Critical Legacy Systems, GAO-19-351SU (Washington, D.C.: June 11, 2019).




                       Page 1                                                              GAO-19-471 Legacy IT
determined that certain information in our original report should be
protected from public disclosure. Therefore, we will not release the LOUO
report to the general public because of the sensitive information it
contains.

The LOUO report includes eight recommendations that we made to eight
agencies to identify and document modernization plans for particular
legacy systems, including milestones, a description of the work
necessary, and details on the disposition of the legacy system. 5 In this
public version of the report, we have omitted sensitive information
regarding particular legacy systems, including the systems’ names and
other information that would identify the systems.

Although the information provided in this report is more limited, this report
addresses the same objectives as the LOUO report and is based on the
same audit methodology. We provided a draft of this report to agency
officials to obtain their review and comments on the sensitivity of the
information contained herein. We confirmed with the agency officials that
this report can be made available to the public without jeopardizing the
security of federal agencies’ legacy systems.

To identify the most critical legacy systems in need of modernization, we
followed up with each of the 24 federal agencies’ covered by the Chief
Financial Officers Act of 1990 regarding their legacy systems that they
had identified in 2017 as most in need of modernization. 6 All 24 agencies
either confirmed or updated their lists of these systems most in need of
modernization. This resulted in a collective list of 65 systems.




5
 We made recommendations to the Departments of Education, Health and Human
Services, Homeland Security, Transportation, the Treasury; the Office of Personnel
Management; Small Business Administration; and Social Security Administration.
6
 The 24 major federal agencies covered by the Chief Financial Officers Act of 1990 are
the Departments of Agriculture, Commerce, Defense, Education, Energy, Health and
Human Services, Homeland Security, Housing and Urban Development, the Interior,
Justice, Labor, State, Transportation, the Treasury, and Veterans Affairs; Environmental
Protection Agency; General Services Administration; National Aeronautics and Space
Administration; National Science Foundation; Nuclear Regulatory Commission; Office of
Personnel Management; Small Business Administration; Social Security Administration;
and U.S. Agency for International Development. 31 U.S.C. §90l(b).




Page 2                                                              GAO-19-471 Legacy IT
We then reviewed available technical literature 7 and consulted with
system development experts within GAO to develop a set of attributes for
determining system obsolescence and their need for modernization.
These attributes included a system’s age, hardware age, operating and
labor costs, vendor warranty and support status, and security risk. 8 We
assigned point values to each system based on the systems’ agency-
reported attributes. We totaled each system’s assigned point values and
used the results to rank the 65 legacy systems. We then designated the
10 systems with the highest scores as those legacy systems most in need
of modernization. 9 However, due to sensitivity concerns, in this report we
substituted a numeric identifier for the system names and are not
providing detailed descriptions.

To evaluate agencies’ plans for modernizing the 10 federal legacy
systems most in need of modernization, we requested that the relevant
agencies provide us with their documented plans for modernizing the
selected systems. We reviewed government and industry best practices
related to the modernization of legacy systems. 10 Based on our reviews of
these documents, we determined that agencies’ documented plans for
system modernization should include, at a minimum, (1) milestones to
7
 Our review of literature included General Services Administration, Unified Shared
Services Management, Modernization and Migration Management (M3) Playbook (Aug. 3,
2016); M3 Playbook Guidance (Aug. 3, 2016); American Technology Council, Report to
the President on Federal IT Modernization (Dec. 13, 2017); Office of Management and
Budget, Management of Federal High Value Assets, M-17-09 (Washington, D.C.: Dec. 9,
2016); American Council for Technology-Industry Advisory Council, Legacy System
Modernization: Addressing Challenges on the Path to Success (Fairfax, VA: Oct. 7, 2016);
and Dr. Gregory S. Dawson, Arizona State University, IBM Center for The Business of
Government, A Roadmap for IT Modernization in Government (Washington, D.C.: 2018).
8
 A legacy system may run on updated hardware, and thus, the system’s age and
hardware age may not be the same.
9
 The 10 agencies with the most critical legacy systems in need of modernization are the
Departments of Defense, Education, Health and Human Services, Homeland Security, the
Interior, the Treasury, and Transportation; the Office of Personnel Management; the Small
Business Administration; and the Social Security Administration.
10
  General Services Administration, Unified Shared Services Management, Modernization
and Migration Management (M3) Playbook (Aug. 3, 2016); M3 Playbook Guidance (Aug.
3, 2016); American Technology Council, Report to the President on Federal IT
Modernization (Dec. 13, 2017); Office of Management and Budget, Management of
Federal High Value Assets, M-17-09 (Washington, D.C.: Dec. 9, 2016); American Council
for Technology-Industry Advisory Council, Legacy System Modernization: Addressing
Challenges on the Path to Success (Fairfax, VA: Oct. 7, 2016); and Dr. Gregory S.
Dawson, Arizona State University, IBM Center for The Business of Government, A
Roadmap for IT Modernization in Government (Washington, D.C.: 2018).




Page 3                                                             GAO-19-471 Legacy IT
             complete the modernization, (2) a description of the work necessary to
             modernize the system, and (3) details regarding the disposition of the
             legacy system. We then analyzed agencies’ documented modernization
             plans for the selected legacy systems to determine whether the plans
             included these elements. We supplemented our work with interviews of
             officials in the agencies’ offices of the Chief Information Officer (CIO) and
             program offices for the selected legacy systems.

             To identify legacy system modernization initiatives that agencies indicated
             were successful, we asked each of the 24 agencies to provide us with
             examples of those modernization initiatives that they completed between
             2014 and 2018 and deemed to be successful. In addition, we identified
             other examples of modernization successes at these agencies. We also
             coordinated with the selected agencies’ Offices of Inspector General
             (OIG) to determine whether those offices had any past or current audit
             work that would contradict the agencies’ determination that the initiatives
             were successful. We then selected initiatives that reflected a mix of
             different agencies, types of system modernizations undertaken, and types
             of benefits realized from the initiatives. A full description of our objectives,
             scope, and methodology can be found in appendix I.

             We conducted this performance audit from January 2018 to June 2019 in
             accordance with generally accepted government auditing standards.
             Those standards require that we plan and perform the audit to obtain
             sufficient, appropriate evidence to provide a reasonable basis for our
             findings and conclusions based on our audit objectives. We believe that
             the evidence obtained provides a reasonable basis for our findings and
             conclusions based on our audit objectives.


             Historically, the federal government has had difficulties acquiring,
Background   developing, and managing IT investments. 11 Further, federal agencies
             have struggled with appropriately planning and budgeting for modernizing
             legacy systems; upgrading underlying infrastructure; and investing in high
             quality, lower cost service delivery technology. The consequences of not
             updating legacy systems has contributed to, among other things, security
             risks, unmet mission needs, staffing issues, and increased costs.

             11
               As a result of the many issues the federal government has experienced, we identified
             “Improving the Management of IT Acquisitions and Operations” as a high-risk area in
             February 2015. GAO, High-Risk Series: An Update, GAO-15-290 (Washington, D.C.: Feb.
             11, 2015).




             Page 4                                                           GAO-19-471 Legacy IT
•    Security risks. Legacy systems may operate with known security
     vulnerabilities that are either technically difficult or prohibitively
     expensive to address. In some cases, vendors no longer provide
     support for hardware or software, creating security vulnerabilities and
     additional costs. For example, in November 2017, the Department of
     Education’s (Education) Inspector General identified security
     weaknesses that included the department’s use of unsupported
     operating systems, databases, and applications. 12 By using
     unsupported software, the department put its sensitive information at
     risk, including the personal records and financial information of
     millions of federal student aid applicants. 13
•    Unmet mission needs. Legacy systems may not be able to reliably
     meet mission needs because they are outdated or obsolete. For
     instance, in 2016, the Department of State’s (State) Inspector General
     reported on the unreliability of the Bureau of Consular Affairs’ legacy
     systems. 14 Specifically, during the summers of 2014 and 2015,
     outages in the legacy systems slowed and, at times, stopped the
     processing of routine consular services such as visa processing. For
     example, in June 2015, system outages caused by a hardware failure
     halted visa processing for 13 days, creating a backlog of 650,000
     visas.
•    Staffing issues. In order to operate and maintain legacy systems,
     staff may need experience with older technology and programming
     languages, such as the Common Business Oriented Language
     (COBOL). 15 Agencies have had difficulty finding employees with such
     knowledge and may have to pay a premium to hire specialized staff or
     contractors. For example, we reported in May 2016 that the Social
     Security Administration (SSA) had to rehire retired employees to

12
  Department of Education, Office of Inspector General, FY 2018 Management
Challenges, (Washington, D.C.: November 2017).
13
  According to Education’s Office of General Counsel, Education has developed
corrective action plans to address the Inspector General’s recommendation.
14
  U.S. Department of State, Office of Inspector General, Inspection of the Bureau of
Consular Affairs, Office of Consular Systems and Technology, ISP-I-17-04, (Arlington, VA:
December 2016).
15
  COBOL, which was introduced in 1959, became the first widely used, high-level
programming language for business applications. The Gartner Group, a leading IT
research and advisory company, has reported that organizations using COBOL should
consider replacing the language, as procurement and operating costs are expected to
steadily rise, and because there is a decrease in people available with the proper skill sets
to support the language.




Page 5                                                                GAO-19-471 Legacy IT
      maintain its COBOL systems. 16 Further, having a shortage of expert
      personnel available to maintain a critical system creates significant
      risk to an agency’s mission. For instance, we reported in June 2018
      that the Internal Revenue Service (IRS) was experiencing shortages
      of staff with the skills to support key tax processing systems that used
      legacy programming languages. 17 These staff shortages not only
      posed risks to the operation of the key tax processing systems, but
      they also hindered the agency’s efforts to modernize its core tax
      processing system.
•     Increased costs. The cost of operating and maintaining legacy
      systems increases over time. The issue of cost is linked to the three
      previously described consequences—either because the other issues
      directly raise costs or, as in the case of not meeting mission needs,
      the agency is not receiving a favorable return on investment. Further,
      in an era of constrained budgets, the high costs of maintaining legacy
      systems could limit agencies’ ability to modernize and develop new or
      replacement systems.
During the course of our review, agencies reported that they consider
several factors prior to deciding whether to modernize a legacy system. In
particular, agencies evaluate factors, such as the inherent risks, the
criticality of the system, the associated costs, and the system’s
operational performance.

•     Risks. Agencies consider the risks associated with maintaining the
      legacy system as well as modernizing the legacy system. For
      instance, agencies may prioritize the modernization of legacy systems
      that have security vulnerabilities or software that is unsupported by
      the vendor. 18 However, limited system accessibility may also reduce
      the need to modernize a legacy system. For example, air-gapped
      systems, which are systems that are isolated from the internet, may




16
    GAO-16-468.
17
  GAO, Information Technology: IRS Needs to Take Additional Actions to Address
Significant Risks to Tax Processing, GAO-18-298 (Washington, D.C.: June 28, 2018).
18
  When computer systems or software are no longer supported, the vendor of the product
ceases to provide patches, security fixes, or updates, leaving system vulnerabilities open
to exploitation.




Page 6                                                              GAO-19-471 Legacy IT
     mitigate a legacy system’s cybersecurity risk by preventing remote
     hackers from having system access. 19
     Conversely, we have also reported that air-gapped systems are not
     necessarily secure: they could potentially be accessed by other
     means than the internet, such as through Universal Serial Bus
     devices. 20 Even so, removing the threat of remote access is a
     mitigation technique used by agencies such as the Nuclear
     Regulatory Commission (NRC). According to NRC, the agency
     reduced the riskiness of using computers with unsupported operating
     systems by putting these computers on isolated networks or by
     disconnecting them from networks entirely.

•    Criticality. Agencies consider how critical the system is to the
     agency’s mission. Several agencies stated that they would consider
     how essential a legacy system is to their agencies’ missions before
     deciding to modernize it. For example, the Department of Health and
     Human Services (HHS) stated that, when deciding to modernize a
     legacy system, it considers the degree to which core mission
     functions of the agency or other agencies are dependent on the
     system. Similarly, Department of Energy (Energy) officials noted that
     the department is required to maintain several legacy systems
     associated with the storage of its nuclear waste.
•    Costs. Agencies consider the costs of maintaining a legacy system
     and modernizing the system. For example, according to the
     Department of Veterans Affairs (VA), there are systems for which a
     life-cycle cost analysis of the legacy system may show that the cost to
     modernize exceeds the projected costs to maintain the system.
     Similarly, the Department of Defense (DOD) noted that, before
     deciding on a modernization solution, it is important to assess the
     costs of the transition to a new or replacement solution.
     An agency also may decide to modernize a system when there is
     potential for cost savings to be realized with a modernization effort.
     For example, HHS stated that it may pursue the modernization of a
     legacy system if the department anticipates reductions in operations

19
  Michael DePhillips and Susan Pepper, “Computer Security – Indirect Vulnerabilities and
Threat Vectors (Air-Gap In-depth)” (paper presented at the International Conference on
Physical Protection of Nuclear Material and Nuclear Facilities, Vienna, Austria: November
2017).
20
 GAO, Weapon Systems Cybersecurity: DOD Just Beginning to Grapple with Scale of
Vulnerabilities, GAO-19-128 (Washington, D.C.: Oct. 9, 2018).




Page 7                                                              GAO-19-471 Legacy IT
                                and maintenance costs due to efficiencies gained through the
                                modernization.

                          •     Performance. Before making the decision to modernize, agencies
                                consider the legacy system’s operational performance. Specifically, if
                                the legacy system is performing poorly, the agency may decide to
                                modernize it. For example, the Department of Transportation
                                (Transportation) stated that, if a legacy system is no longer
                                functioning properly, it should be modernized. In addition, HHS noted
                                that the ability to improve the functionality of the legacy system could
                                be a reason to modernize it.

GAO Has Reported on the   As previously mentioned, in May 2016, we reported that federal legacy IT
Need to Improve           investments were becoming increasingly obsolete. 21 In this regard,
Oversight of Legacy IT    agencies had reported operating systems that used outdated languages
                          and old parts, which were difficult to replace. Further, we noted that each
                          of the 12 selected agencies had reported using unsupported operating
                          systems and components, which could create security vulnerabilities and
                          additional costs. 22 At the time, five of the selected agencies reported
                          using 1980s and 1990s Microsoft operating systems that stopped being
                          supported by the vendor more than a decade ago. We concluded that
                          agencies were, in part, maintaining obsolete investments because they
                          were not required to identify, evaluate, and prioritize investments to
                          determine whether the investments should be kept as-is, modernized,
                          replaced, or retired. We pointed out that the Office of Management and
                          Budget (OMB) had created draft guidance that would require agencies to
                          do so, but OMB had not committed to a firm time frame for when the
                          guidance would be issued.

                          As such, we made 16 recommendations to OMB and the selected federal
                          agencies to better manage legacy systems and investments. Most
                          agencies agreed with the recommendations or had no comment.
                          However, as of May 2019, 13 recommendations had not been
                          implemented. In particular, OMB has not finalized and issued its draft
                          guidance on legacy systems. Until this guidance is finalized and issued,
                          21
                              GAO-16-468.
                          22
                            The agencies in our 2016 review were the 12 that reported the highest planned IT
                          spending for fiscal year 2015. These agencies were the Departments of Agriculture,
                          Commerce, Defense, Energy, Health and Human Services, Homeland Security, Justice,
                          State, Transportation, the Treasury, and Veterans Affairs; and the Social Security
                          Administration.




                          Page 8                                                          GAO-19-471 Legacy IT
                            the federal government will continue to run the risk of maintaining
                            investments that have outlived their effectiveness and are increasingly
                            difficult to protect from cybersecurity vulnerabilities.


Congress and the            Congress and the executive branch have initiated several efforts to
Executive Branch Have       modernize federal IT, including:
Made Efforts to Modernize   •   Identification of High Value Assets. In a December 2016
Federal IT                      memorandum, OMB observed that continued increases in computing
                                power combined with declining computing and storage costs and
                                increased network connectivity had expanded the government’s
                                capacity to store and process data. 23 However, OMB noted that this
                                rise in technology and interconnectivity also meant that the federal
                                government’s critical networks, systems, and data were more
                                exposed to cyber risks. As a result, OMB issued guidance to assist
                                federal agencies covered by the Chief Financial Officers Act in
                                managing the risks to these assets, which it designated as High Value
                                Assets. 24
                                Subsequently, in December 2018, OMB issued a memorandum that
                                provided further guidance regarding the establishment and
                                enhancement of the High Value Asset program. 25 It stated that the
                                program is to be operated by DHS in coordination with OMB. Further,
                                the new guidance expanded the program to apply to all agencies (i.e.,
                                agencies covered by the Chief Financial Officers Act, as well as those
                                not covered by the act) and expanded the definition of High Value




                            23
                              OMB, Management of Federal High Value Assets, M-17-09 (Washington, D.C.: Dec. 9,
                            2016).
                            24
                              OMB’s December 2016 memorandum defined High Value Assets as those assets,
                            federal information systems, information, and data for which an unauthorized access, use,
                            disclosure, disruption, modification, or destruction could cause significant impact to the
                            United States’ national security interests, foreign relations, economy, or to the public
                            confidence, civil liberties, or public health and safety of the American people. This
                            definition replaced a previous definition from OMB Memorandum M-16-04.
                            25
                              OMB, Strengthening the Cybersecurity of Federal Agencies by Enhancing the High
                            Value Asset Program, M-19-03 (Washington, D.C.: Dec. 10, 2018). This memorandum
                            rescinded the previous guidance on High Value Assets, M-16-04 and M-17-09.




                            Page 9                                                              GAO-19-471 Legacy IT
      Assets. 26 The guidance required agencies to identify and report these
      assets (which may include legacy systems), assess them for security
      risks, and remediate any weaknesses identified, including those
      associated with obsolete or unsupported technology.

•     Assessment of federal IT modernization. On May 11, 2017, the
      President signed Executive Order 13800, Strengthening the
      Cybersecurity of Federal Networks and Critical Infrastructure. 27 This
      executive order outlined actions to enhance cybersecurity across
      federal agencies and critical infrastructure to improve the nation’s
      cyber posture and capabilities against cybersecurity threats. Among
      other things, the order tasked the Director of the American
      Technology Council to coordinate a report to the President from the
      Secretary of DHS, the Director of OMB, and the Administrator of the
      General Services Administration (GSA), in consultation with the
      Secretary of Commerce, regarding modernizing federal IT. 28
      As a result, the Report to the President on Federal IT Modernization
      was issued on December 13, 2017, and outlined the current and
      envisioned state of federal IT. 29 The report focused on modernization
      efforts to improve the security posture of federal IT and recognized
      that agencies have attempted to modernize systems but have been
      stymied by a variety of factors, including resource prioritization, ability
      to procure services quickly, and technical issues. The report provided
      multiple recommendations intended to address these issues through
      the modernization and consolidation of networks and the use of
      shared services. In particular, the report recommended that the

26
  According to OMB’s December 2018 guidance, an agency may designate federal
information or an information system as a High Value Asset when one or more of these
categories apply to it: (1) the information or information system that processes, stores, or
transmits the information is of high value to the federal government or its adversaries; (2)
the agency that owns the information or information system cannot accomplish its primary
mission essential functions within expected timelines without the information or
information system; and (3) the information or information system serves a critical function
in maintaining the security and resilience of the federal civilian enterprise.
27
    Exec. Order No. 13800, 82 Fed Reg. 22391 (2017).
28
  The American Technology Council was established in May 2017, and has the goal of
helping to transform and modernize federal agency IT and how the federal government
uses and delivers digital services. The President is the chairman of this council, and the
Federal CIO and the United States Digital Service Administrator are among the members.
29
  American Technology Council, Report to the President on Federal IT Modernization,
(Washington, D.C.: Dec. 13, 2017).




Page 10                                                               GAO-19-471 Legacy IT
    federal government prioritize the modernization of legacy IT by
    focusing on enhancing security and privacy controls for those assets
    that are essential for agencies to serve the American people and
    whose security posture is most vulnerable (i.e., High Value Assets).

•   Enactment of the Modernizing Government Technology (MGT)
    Act. To help further agencies’ efforts to modernize IT, in December
    2017, Congress and the President enacted a law to authorize the
    availability of funding mechanisms to improve, retire, or replace
    existing IT systems to enhance cybersecurity and to improve
    efficiency and effectiveness. The law, known as the MGT Act,
    authorizes agencies to establish working capital funds for use in
    transitioning from legacy systems, as well as for addressing evolving
    threats to information security. 30 The law also created the Technology
    Modernization Fund, within the Department of the Treasury
    (Treasury), from which agencies can “borrow” money to retire and
    replace legacy systems, as well as acquire or develop systems.
    Subsequently, in February 2018, OMB issued guidance for agencies
    to implement the MGT Act. 31 The guidance was intended to provide
    agencies additional information regarding the Technology
    Modernization Fund, and the administration and funding of the related
    IT working capital funds. 32 Specifically, the guidance allowed agencies
    to begin submitting initial project proposals for modernization on
    February 27, 2018.

    In addition, in accordance with the MGT Act, the guidance provides
    details regarding a Technology Modernization Board, which is to
    consist of (1) the Federal CIO; (2) a senior official with IT technical
    expertise from GSA; (3) a member of DHS’s National Protection and




30
  National Defense Authorization Act for Fiscal Year 2018, Pub. L. No. 115-91, Div. A,
Title X, Subtitle G (2017).
31
  OMB, Implementation of the Modernizing Government Technology Act, M-18-12
(Washington, D.C.: Feb. 27, 2018).
32
  OMB staff stated that, while the MGT Act authorizes agencies to establish working
capital funds, the Act does not confer the transfer authority necessary to operate an IT
working capital fund.




Page 11                                                               GAO-19-471 Legacy IT
     Program Directorate; 33 and (4) four federal employees with technical
     expertise in IT development, financial management, cybersecurity and
     privacy, and acquisition, appointed by the Director of OMB. 34

     As of February 2019, the Technology Management Fund Board had
     approved funds for seven IT modernization projects across five
     agencies: the Department of Agriculture, Energy, the Department of
     Housing and Urban Development (HUD), the Department of Labor,
     and GSA. For example, the board approved $20 million for HUD to
     modernize a mainframe and five COBOL-based applications that are
     expensive to maintain. According to the board’s website, without
     these funds, HUD would not have been able to pursue this project for
     several years.
•    Issuance of the President’s Management Agenda. In March 2018,
     the Administration issued the President’s Management Agenda, which
     lays out a long-term vision for modernizing the federal government. 35
     The agenda identifies three related drivers of transformation—IT
     modernization; data, accountability, and transparency; and the
     workforce of the future—that are intended to push change across the
     federal government.
     The President’s Management Agenda identifies 14 related Cross-
     Agency Priority goals, many of which have elements that involve IT. 36
     In particular, the Cross-Agency Priority goal on IT modernization
     states that modern technology must function as the backbone of how
     government serves the public in the digital age. Further, the goal on IT
     modernization provides three priorities that are to guide the
     Administration’s efforts to modernize federal IT: (1) enhancing mission
     effectiveness by improving the quality and efficiency of critical
33
  The National Protection and Program Directorate was the DHS component responsible
for addressing physical and cyber infrastructure protection. The Cybersecurity and
Infrastructure Security Agency Act of 2018 renamed the National Protection and Program
Directorate to be the Cybersecurity and Infrastructure Security Agency and established a
director and responsibilities for the agency.
34
  As of February 2019, these four employees were the Acting Administrator of OMB’s U.S.
Digital Service, the Small Business Administration’s CIO, SSA’s CIO, and VA’s Chief
Technology Officer.
35
  President’s Management Council and Executive Office of the President, President’s
Management Agenda (Washington, D.C.: Mar. 20, 2018).
36
  Cross-Agency Priority goals were established in response to the GPRA Modernization
Act of 2010, Pub. L. No. 111-352, Sec. 5 (Jan. 4, 2011); 124 Stat. 3866, 3873; 31 U.S.C. §
1120(a)(1)(B).




Page 12                                                             GAO-19-471 Legacy IT
                           services, including the increased utilization of cloud-based solutions; 37
                           (2) reducing cybersecurity risks to the federal mission by leveraging
                           current commercial capabilities and implementing cutting edge
                           cybersecurity capabilities; and (3) building a modern IT workforce by
                           recruiting, reskilling, and retaining professionals able to help drive
                           modernization with up-to-date technology.


                      As determined by our review of 65 critical federal legacy systems (see
GAO Identified 10     appendix II), the 10 most critical legacy systems in need of modernization
Critical Federal      are maintained by 10 different federal agencies whose missions are
                      essential to government operations, such as emergency management,
Legacy Systems;       health care, and wartime readiness. 38 These legacy systems provide vital
Agencies Often Lack   support to the agencies’ missions.
Complete Plans for    According to the agencies, these legacy systems range from about 8 to
Their Modernization   51 years old and, collectively, cost approximately $337 million annually to
                      operate and maintain. 39 Several of the systems use older languages,
                      such as COBOL and assembly language code. 40 However, as we
                      reported in June 2018, reliance on assembly language code and COBOL
                      has risks, such as a rise in procurement and operating costs, and a
                      decrease in the availability of individuals with the proper skill sets. 41



                      37
                        Cloud computing is a means for delivering computing services via IT networks. When
                      executed effectively, cloud-based solutions can allow agencies to pay for only the IT
                      services used, thus paying less for more services.
                      38
                        To identify the 10 most critical legacy systems in need of modernization, we collected
                      information on 65 of the most critical federal legacy systems and assigned point values
                      based on system attributes, including a system’s age, hardware’s age, system criticality,
                      and security risk (see appendix II for the full list of 65 systems). We then selected the 10
                      systems with the highest scores as the most critical legacy systems in need of
                      modernization.
                      39
                        SSA was unable to isolate the costs for just System 10 and, as a result, this number
                      includes the cost of operating some of SSA’s other mainframe systems.
                      40
                        As we reported in May 2016, assembly language code is a low-level computer language
                      initially used in the 1950s. Programs written in assembly language are conservative of
                      machine resources and quite fast; however, they are much more difficult to write and
                      maintain than other languages. Programs written in assembly language may only run on
                      the type of computer for which they were originally developed.
                      41
                        GAO, Information Technology: IRS Needs to Take Additional Actions to Address
                      Significant Risks to Tax Processing, GAO-18-298 (Washington, D.C.: June 28, 2018).




                      Page 13                                                                GAO-19-471 Legacy IT
Further, several of these legacy systems are also operating with known
security vulnerabilities and unsupported hardware and software. For
example, DHS’s Federal Emergency Management Agency performed a
security assessment on its selected legacy system in September 2018.
This review found 249 reported vulnerabilities, of which 168 were
considered high or critical risk to the network.

With regard to unsupported hardware and software, Interior’s system
contains obsolete hardware that is not supported by the manufacturers.
Moreover, the system’s original hardware and software installation did not
include any long-term vendor support. Thus, any original components that
remain operational may have had long-term exposure to security and
performance weaknesses.

Table 1 provides a generalized list of each of the 10 most critical legacy
systems that we identified, as well as agency-reported system attributes,
including the system’s age, hardware’s age, system criticality, and
security risk. (Due to sensitivity concerns, we substituted a numeric
identifier for the system names and are not providing detailed
descriptions). Appendix III provides additional generalized agency-
reported details on each of these 10 legacy systems.




Page 14                                                  GAO-19-471 Legacy IT
Table 1: The 10 Most Critical Federal Legacy Systems in Need of Modernization

                                                                                                                 Age of      System              Security
                                                                                                  Age of         oldest      criticality         risk
                              System                                                            system,      hardware,       (according to       (according
                                   a                                a
Agency                        name             System description                               in years       in years      agency)             to agency)
Department of                 System 1         A maintenance system that supports                      14              3     Moderately          Moderate
Defense                                        wartime readiness, among other things                                         high
Department of                 System 2         A system that contains student                          46              3     High                High
Education                                      information
Department of                 System 3         An information system that supports                     50    Unknownb        High                High
Health and Human                               clinical and patient administrative
Services                                       activities
Department of     System 4                     A network that consists of routers,           Between 8                11     High                High
Homeland Security                              switches, and other network appliances          and 11c
Department of the             System 5         A system that supports the operation of                 18             18     High                Moderately
Interior                                       certain dams and power plants                                                                     high
Department of the             System 6         A system that contains taxpayer                         51              4     High                Moderately
Treasury                                       information                                                                                       low
Department of                 System 7         A system that contains information on                   35              7     High                Moderately
Transportation                                 aircraft                                                                                          high
Office of Personnel System 8                   Hardware, software, and service                         34             14     High                Moderately
Management                                     components that support information                                                               low
                                               technology applications and services
Small Business                System 9         A system that controls access to                        17             10     High                Moderately
Administration                                 applications                                                                                      high
Social Security               System 10 A group of systems that contain                                45              5     High                Moderate
Administration                          information on Social Security
                                        beneficiaries

Key:
Agencies reported the system criticality and security risk on a scale of 1 to 5 (with 5 being the most critical and the highest risk).
Low-1: According to the agency, system has low security risk or criticality.
Moderately low-2: According to the agency, system has moderately low security risk or criticality.
Moderate-3: According to the agency, system has moderate security risk or criticality.
Moderately high-4: According to the agency, system has moderately high security risk or criticality.
High-5: According to the agency, system has high security risk or criticality.
Source: GAO analysis of agency data. | GAO-19-471
                                                         a
                                                          Due to sensitivity concerns, we substituted a numeric identifier for the system names and only
                                                         provided general details.
                                                         b
                                                          The agency stated that the system’s hardware had various refresh dates and that it was not able to
                                                         identify the oldest hardware.
                                                         c
                                                          The agency stated that the majority of the network’s hardware was purchased between 2008 and
                                                         2011.




                                                         Page 15                                                                         GAO-19-471 Legacy IT
The Majority of Agencies   Given the age of the hardware and software in legacy systems, the
Lack Complete Plans for    systems’ criticality to agency missions, and the security risks posed by
                           operating aging systems, it is imperative that agencies carefully plan for
Modernizing the Most
                           their successful modernization. Documenting modernization plans in
Critical Legacy Systems    sufficient detail increases the likelihood that modernization initiatives will
                           succeed. According to our review of government and industry best
                           practices for the modernization of federal IT, 42 agencies should have
                           documented modernization plans for legacy systems that, at a minimum,
                           include three key elements: (1) milestones to complete the modernization,
                           (2) a description of the work necessary to modernize the legacy system,
                           and (3) details regarding the disposition of the legacy system.

                           Of the 10 identified agencies with critical systems most in need of
                           modernization, seven (DOD, DHS, Interior, Treasury, the Office of
                           Personnel Management (OPM), the Small Business Administration
                           (SBA), and SSA) had documented modernization plans for their
                           respective critical legacy systems and three did not have documented
                           plans. The three agencies that did not have documented modernization
                           plans for their critical legacy systems were: (1) Education, (2) HHS, and
                           (3) Transportation.

                           Of the seven agencies with documented plans, DOD and Interior had
                           modernization plans that addressed each of the three key elements. For
                           example, Interior submitted documentation of both completed and
                           forthcoming milestones leading to the deployment of the modernized
                           system. The department also provided a list of the mandatory
                           requirements for the updated system, as well as the work that needed to
                           be performed at each stage of the project, including the disposition of the
                           legacy system.

                           Likewise, DOD provided documentation of the milestones and the work
                           needed to complete the modernization of its legacy system. In addition,
                           the documentation discussed the department’s plans for the disposition of
                           the legacy system.

                           42
                             GSA, Unified Shared Services Management, Modernization and Migration Management
                           (M3) Playbook (Aug. 3, 2016); M3 Playbook Guidance (Aug. 3, 2016); American
                           Technology Council, Report to the President on Federal IT Modernization (Dec. 13, 2017);
                           OMB, Management of Federal High Value Assets, M-17-09 (Washington, D.C.: Dec. 9,
                           2016); American Council for Technology-Industry Advisory Council, Legacy System
                           Modernization: Addressing Challenges on the Path to Success (Fairfax, VA: Oct. 7, 2016);
                           and Dr. Gregory S. Dawson, Arizona State University, IBM Center for The Business of
                           Government, A Roadmap for IT Modernization in Government (Washington, D.C.: 2018).




                           Page 16                                                           GAO-19-471 Legacy IT
While the other five agencies—Treasury, DHS, OPM, SBA, and SSA—
had developed modernization plans for their respective legacy systems,
their plans did not fully address one or more of the three key elements.
For instance, DHS’s Federal Emergency Management Agency’s
modernization plan for its selected legacy system described the work that
the department needed to accomplish, but did not include the associated
milestones or the disposition of the legacy system. Similarly, SBA
included milestones and a plan for the disposition of the legacy system,
but did not include a description of the work necessary to accomplish the
modernization.

Treasury, OPM, and SSA partially included one or more of the key
elements in their modernization plans. For instance, OPM’s and SSA’s
plans included upcoming milestones for one part of the initiative, but not
the entire effort. Similarly, OPM’s modernization plans only described a
portion of the work necessary to complete each modernization initiative.
Further, none of these four agencies’ modernization plans included
considerations for the disposition of legacy system components following
the completion of the modernization initiatives. While agencies may be
using development practices that minimize initial planning, such as
agile, 43 agencies should have high-level information on cost, scope, and
timing. 44

Table 2 identifies the seven agencies with documented modernization
plans for their critical systems, as well as the extent to which the plans
were sufficiently detailed to include the three key elements. (Due to
sensitivity concerns, we substituted a numeric identifier for the system
names.)




43
  Agile development is a type of incremental development, which calls for the rapid
delivery of software in small, short increments. Many organizations, especially in the
federal government, are accustomed to using a waterfall software development model,
which consists of long, sequential phases.
44
 GAO, FEMA Grants Modernization: Improvements Needed to Strengthen Program
Management and Cybersecurity, GAO-19-164 (Washington, D.C.: Apr. 9, 2019).




Page 17                                                             GAO-19-471 Legacy IT
Table 2: Extent to Which Agencies’ Legacy System Documented Modernization Plans Included Key Elements

                                                                                   Includes milestones          Describes work               Summarizes
                                                                                   to complete the              necessary to                 planned disposition
 Agency                                                 System namea               modernization                modernize system             of legacy system
 Department of Defense                                  System 1                   Yes                          Yes                          Yes
 Department of Homeland Security                        System 4                   No                           Yes                          No
 Department of the Interior                             System 5                   Yes                          Yes                          Yes
 Department of the Treasury                             System 6                   Partial                      Yes                          No
 Office of Personnel Management                         System 8                   Partial                      Partial                      No
 Small Business Administration                          System 9                   Yes                          No                           Yes
 Social Security Administration                         System 10                  Partial                      Partial                      No

Legend:
Yes – Agency included element in modernization plan.
Partial – Agency partially included the element in the modernization plan (e.g., the element was completed for only a portion of the modernization, rather
than the entire modernization).
No – Agency did not include element in modernization plan.
Source: GAO analysis of agency modernization plans. | GAO-19-471
                                                               a
                                                                   Due to sensitivity concerns, we have substituted the systems’ names with a numeric identifier.


                                                               The agencies provided a variety of explanations for the missing
                                                               modernization plans. For example, according to the three agencies
                                                               without documented modernization plans:

                                                               •       Education’s modernization plans were pending the results of a
                                                                       comprehensive IT visualization and engineering project that would
                                                                       determine which IT systems and services could be feasibly
                                                                       modernized, consolidated, or eliminated;
                                                               •       HHS had entered into a contract to begin a modernization initiative but
                                                                       had not yet completed its plans; and
                                                               •       Transportation had solicited information from industry to determine
                                                                       whether the agency’s ideas for modernization were feasible.
                                                               Of the five agencies which had plans that lacked key elements, officials
                                                               within SSA’s office of the CIO stated that the agency has yet to complete
                                                               its modernization planning, even though modernization efforts are
                                                               currently underway. The officials said that they will update the planning
                                                               documentation and make further decisions as the modernization effort
                                                               progresses.

                                                               Officials within DHS’s Federal Emergency Management Agency’s Office
                                                               of the CIO stated that its plans for modernizing the system we reviewed



                                                               Page 18                                                                         GAO-19-471 Legacy IT
(System 4) are contingent on receiving funding and being able to allocate
staffing resources to planning activities. According to the officials, the
agency is also integrating its plans for modernizing System 4 with the
management of the rest of the agency’s systems.

Similarly, Treasury officials stated that IRS’s efforts to complete planning
for the remaining modernization activities have been delayed due to
budget constraints. In addition, officials within OPM’s Office of the CIO
stated that its modernization plan did not extend to fiscal year 2019
because there were changes in leadership during the creation of the plan,
and because of uncertainty in funding amounts.

While we recognize that system modernizations are dependent on
funding, it is important for agencies to prioritize funding for the
modernization of these critical legacy systems. In addition, Congress
provided increased authority for agencies to fund such modernization
efforts through the MGT Act’s Technology Modernization Fund and the
related IT working capital funds.

Until the agencies establish complete legacy system modernization plans
that include milestones, describe the work necessary to modernize the
system, and detail the disposition of the legacy system, the agencies’
modernization initiatives will have an increased likelihood of cost
overruns, schedule delays, and overall project failure. Project failure
would be particularly detrimental in these 10 cases, not only because of
wasted resources, but also because it would prolong the lifespan of
increasingly vulnerable and obsolete systems, exposing the agency and
system clients to security threats and potentially significant performance
issues.

Further, agencies may not be effectively planning for the modernization of
legacy systems, in part, because they are not required to. As we reported
in May 2016, agencies are not required to identify, evaluate, and prioritize
existing IT investments to determine whether they should be kept as-is,
modernized, replaced, or retired. 45 We recommended that OMB direct
agencies to identify legacy systems needing to be replaced or
modernized. As of April 2019, OMB had not implemented this
recommendation. OMB staff stated that agencies were directed to
manage the risk to High Value Assets associated with legacy systems in

45
 GAO-16-468.




Page 19                                                  GAO-19-471 Legacy IT
                                         OMB’s December 2018 guidance. 46 While OMB’s guidance does direct
                                         agencies to identify, report, assess, and remediate issues associated with
                                         High Value Assets, it does not require agencies to do so for all legacy
                                         systems. Until OMB requires agencies to do so, the federal government
                                         will continue to run the risk of continuing to maintain investments that
                                         have outlived their effectiveness.


                                         The 24 Chief Financial Officers Act agencies in our review identified a
Agencies Reported a                      total of 94 examples of successful modernizations of legacy systems
Variety of IT                            undertaken in the last 5 years. The initiatives were of several types,
                                         including those aimed at transforming legacy code into a more modern
Modernization                            programming language, migrating legacy services (e.g., email) to the
Successes                                cloud, and re-designing a legacy mainframe to a cloud-based application.
                                         Among these examples, the five that we selected reflect a mix of different
                                         agencies, types of system modernization initiatives, and types of benefits
                                         realized from the initiatives.

                                         Table 3 provides details on the five examples of successful IT
                                         modernization initiatives, as reported by their respective agencies, as well
                                         as the reported benefits related to those initiatives.

Table 3: Agency-Reported Examples of Successful Information Technology (IT) Modernization Initiatives in the Last 5 Years
and Associated Benefits

Agency         Initiative description                                       Benefits reported by agencies
Department of Standard Base Supply System and Enterprise Solution-          •  Avoided spending $11 million on costs
Defense       Supply. In April 2015, the Air Force, a component of DOD,        associated with hosting the system due to
(DOD)         began an initiative to modernize its Standard Base Supply        decommissioning the legacy system earlier than
              System and Enterprise Solution-Supply (legacy systems            anticipated
              responsible for the management of supplies and equipment for •   Avoided spending $25 million annually on
              warfighting missions). To do so, among other things, the         hosting costs
              component transformed millions of lines of Common Business
                                                                            •  Minimized the use of legacy code, which can be
              Oriented Language (COBOL) code to Java code. In February
                                                                               costly and difficult to maintain
              2018, the Air Force completed the migration to the modernized
              version of the Integrated Logistics Systems-Supply system.




                                         46
                                          OMB, Strengthening the Cybersecurity of Federal Agencies by Enhancing the High
                                         Value Asset Program, M-19-03 (Washington, D.C.: Dec. 10, 2018).




                                         Page 20                                                          GAO-19-471 Legacy IT
 Agency                Initiative description                                               Benefits reported by agencies
 Department of Direct Loan Consolidation System. In 2012, Education                         •  Improved customer experience through website
 Education     began its initiative to modernize the Direct Loan Consolidation                 consolidation
 (Education)   System, its system that allows students to apply for, receive,               •  Consolidated customer call centers
               and consolidate federal education loans. Among other things,
                                                                                            •  Reduced applicant data entry errors by
               this modernization allowed loans to be assigned to multiple
                                                                                               prepopulating data from another system
               servicers, corrected information security findings, and provided
               better customer service. In June 2016, Education                             •  Reduced the amount of oversight required by
               decommissioned the legacy system. Functions that were                           lowering the number of contractors and systems
               performed by the legacy system are now performed by                          •  Closed multiple critical security vulnerabilities
               another existing system, which has an application process in                 •  Improved customer service
               place for borrowers and a real-time interface to help
               prepopulate the application.
 Department of         Employing Shared Services/ Cloud. In August 2012, DHS                •    Realized cumulative $1.6 billion in cost savings
 Homeland              initiated the modernization of multiple IT infrastructure            •    Streamlined the supply chain for IT services
 Security              systems. This included an agency-wide transition to a DHS
                                                                                            •    Reduced the amount of labor needed to maintain
 (DHS)                 private cloud email system and migrating legacy services to 13
                                                                                                 legacy systems and software
                       DHS private cloud offerings.a In particular, all eight of DHS’s
                       operational components migrated applicable legacy services           •    Enhanced security
                       to 13 DHS private cloud offerings by the end of fiscal year
                       2016. As a result, DHS components were able to retire legacy
                       systems and replace legacy software application procurement
                       requirements. For example, U.S. Citizenship and Immigration
                       Services migrated several legacy services to the cloud,
                       including email, which ultimately saved the agency $42,000.
 Department of Treasury Offset Program. Treasury began the modernization                    •    Enhanced revenue by $759 million by collecting
 the Treasury  initiative for this system in July 2011 using Agile development                   delinquent debts
 (Treasury)    principles.b In November 2014, Treasury migrated its legacy                  •    Increased efficiency of the system
               COBOL- and Java-based Treasury Offset Program system to
                                                                                            •    Reduced time spent on manual interventions to
               its new Java-based Treasury Offset Program Next Generation.
                                                                                                 keep the system from failing
               The new system easily supported adding new debt collections
               from federal and state agencies, along with new payment                      •    Automated testing and deployment pipeline,
               streams.                                                                          reducing risk and cost
 Social                Representative Payee System. SSA began the                           •    Improved users’ ability to find data related to
 Security              modernization initiative in December 2011. The agency                     criminal history and fraud
 Administration        needed to have the ability to continually add new                    •    Increased security by becoming compliant with
 (SSA)                 representative payee records and expand the number of                     current agency standards and federal guidelines
                       records stored in the database. In April 2016, SSA completed
                                                                                            •    Improved business processes, such as search
                       its redesign of the system, changing it from a mainframe-
                                                                                                 capability
                       based system that used Assembler Language Code and
                       COBOL to a web-based application, and decommissioned the             •    Improved ability to identify criminal and
                       legacy system.                                                            fraudulent data
                                                                                            •    Improved system performance and incorporated
                                                                                                 user requested features
Source: GAO analysis of agency data. | GAO-19-471
                                                    a
                                                    A private cloud is set up specifically for one organization, although there may be multiple customers
                                                    within that organization and the cloud may exist on or off the customer’s premises.
                                                    b
                                                     Agile development is an incremental approach that delivers software functionality in short increments
                                                    before the system is fully deployed.




                                                    Page 21                                                                      GAO-19-471 Legacy IT
The five agencies attributed the success of their modernization initiatives
to various factors, including:

•    using automated technologies to examine programming code and
     perform testing (DOD and Treasury);
•    testing the system thoroughly (SSA and Treasury);
•    actively engaging the end users and stakeholders throughout the
     modernization process (SSA and Treasury);
•    cultivating a partnership between industry and government (DOD);
•    following management practices on change and life cycle
     management (Education);
•    developing and implementing an enterprise-wide cost collection and
     data analysis process for commodity IT to track and measure
     progress against consolidation, optimization, and savings targets
     (DHS);
•    creating an interface that was consistent across systems (SSA);
•    having strong executive leadership and support (Treasury); and
•    using agile principles to facilitate the team’s ownership of the project
     (Treasury).
These factors are largely consistent with government and industry best
practices. For example, we reported in 2011 on critical success factors
associated with major acquisitions, including engaging stakeholders and
having the support of senior executives. 47 Similarly, OMB’s guidance on
High Value Assets calls for agencies’ plans to address change
management and life cycle management. 48 Likewise, the Software
Engineering Institute’s Capability Maturity Model® Integration for
Development recommends that organizations engage stakeholders,
practice effective change and life cycle management, and thoroughly test
systems, among other practices. 49 Further, our Information Technology
Investment Management framework recommends involving end users,

47
 GAO, Information Technology: Critical Factors Underlying Successful Major
Acquisitions, GAO-12-7 (Washington, D.C.: Oct. 21, 2011).
48
 OMB, Strengthening the Cybersecurity of Federal Agencies by Enhancing the High
Value Asset Program, M-19-03 (Washington, D.C.: Dec. 10, 2018).
49
  Carnegie Mellon University’s Software Engineering Institute, Capability Maturity Model®
Integration for Development, Version 1.3 (CMMI-Dev V1.3) (Pittsburgh, PA: Nov. 2010).




Page 22                                                             GAO-19-471 Legacy IT
                      implementing change and life cycle management processes, and
                      obtaining the support of executive leadership. 50

                      Agencies that follow such practices are better positioned to modernize
                      their legacy systems. Doing so will also allow the agencies to leverage IT
                      to successfully address their missions.


                      The 10 most critical federal legacy systems in need of modernization are
Conclusions           becoming increasingly obsolete. Several agencies are using outdated
                      computer languages, which can be difficult to maintain and increase
                      costs. Further, several of these legacy systems are also operating with
                      unsupported hardware and software and known security vulnerabilities.

                      Most agencies did not have complete plans to modernize these legacy
                      systems. Due to the criticality and possible cybersecurity risks posed by
                      operating aging systems, having a plan that includes how and when the
                      agency plans to modernize is vital. In the absence of such plans, the
                      agencies increase the likelihood of cost overruns, schedule delays, and
                      overall project failure. Such outcomes would be particularly detrimental
                      because of the importance of these systems to agency missions.

                      Successfully modernizing legacy systems is possible, as demonstrated by
                      the five highlighted examples. Agencies attributed the success of their
                      modernization initiatives to a variety of management and technical factors
                      that were consistent with best practices.


                      In the LOUO report that we are issuing concurrently with this report, we
Recommendations for   are making a total of eight recommendations to eight federal agencies to
Executive Action      identify and document modernization plans for their respective legacy
                      systems, including milestones, a description of the work necessary, and
                      details on the disposition of the legacy system.


                      We requested comments on a draft of this report from OMB and the 24
Agency Comments       agencies included in our review. The eight agencies to which we made
and Our Evaluation    recommendations in the LOUO report agreed with our findings and

                      50
                        GAO, Information Technology Investment Management: A Framework for Assessing
                      and Improving Process Maturity, GAO-04-394G (Washington, D.C.: March 2004).




                      Page 23                                                      GAO-19-471 Legacy IT
recommendations. In addition, OMB and the 16 agencies to which we did
not make recommendations either agreed with our findings, did not agree
or disagree with the findings, or stated that they had no comments.
Further, multiple agencies provided technical comments, which we have
incorporated, as appropriate.

The following eight agencies agreed with our recommendations:

•   In written comments from Education, the agency stated that it
    concurred with the recommendation and indicated its intent to address
    it. Education’s comments are reprinted in appendix IV.
•   In written comments from HHS on the LOUO version of this report, the
    agency stated that it concurred with the recommendation and intends
    to evaluate ways to provide its modernization plan, including
    milestones and a description of the work necessary to modernize the
    system. HHS also provided technical comments that we incorporated,
    as appropriate.
    HHS deemed some of the information in its original agency comment
    letter pertaining to particular legacy systems to be sensitive, which
    must be protected from public disclosure. Therefore, we have omitted
    the sensitive information from the version of the agency comment
    letter that is reprinted in appendix V of this report.
•   In written comments, DHS stated that it concurred with our
    recommendation. DHS’s comments are reprinted in appendix VI.
•   In comments received via email from Transportation’s Director of
    Audit Relations and Program Improvement on May 9, 2019, the
    agency stated that it agreed with our recommendation.
•   In comments from Treasury’s Supervisory IT Specialist/Performance
    and Governance Analyst, received via email on May 17, 2019, the
    department stated that it agreed with our recommendation. In
    addition, Treasury’s component agency, IRS, provided written
    comments which stated that it agreed with the recommendation. The
    agency said it intends to develop a multiyear retirement strategy for its
    system to address the recommendation.
    In its written comments, IRS also stated that our draft report did not
    accurately convey that the legacy system replacement project is
    intended to only replace core components of its selected legacy
    system. The agency said that, even when the entire replacement
    project is completed, it will only address a portion of the work required
    to retire the legacy system. In response, we modified our discussion




Page 24                                                   GAO-19-471 Legacy IT
    of this project in the report. IRS’s comments are reprinted in appendix
    VII.
•   In written comments from OPM on the LOUO version of this report,
    the agency stated that it concurred with the recommendation and
    indicated its plans to address the recommendation. OPM also
    provided technical comments that we incorporated, as appropriate.
    OPM deemed some of the information in its original agency comment
    letter pertaining to particular legacy systems to be sensitive, which
    must be protected from public disclosure. Therefore, we have omitted
    the sensitive information in the version of the agency comment letter
    that is reprinted in appendix VIII.
•   In written comments, SBA concurred with our recommendation and
    stated that it intends to include a description of the work necessary to
    modernize the legacy system in the initiative’s project plan. The
    agency estimated that it will address the recommendation by July 31,
    2019.
    SBA deemed some of the information in its original agency comment
    letter pertaining to particular legacy systems to be sensitive, which
    must be protected from public disclosure. Therefore, we have omitted
    the sensitive information from the version of the agency comment
    letter that is reprinted in appendix IX.
•   In written comments from SSA, the agency stated that it agreed with
    our recommendation. The agency added that it is modernizing its
    legacy system using agile software methods and a multiyear roadmap
    of development activities. The agency further stated that, as it
    completes its modernization work, it expects to retire most of the
    legacy software associated with System 10. SSA also provided
    technical comments that we incorporated, as appropriate. SSA’s
    comments are reprinted in appendix X.
In addition, we received responses via email from 14 agencies to which
we did not make recommendations. Of these agencies, three agreed with
our findings and 11 stated that they did not have comments on the report.
Two other agencies—HUD and the U.S. Agency for International
Development—provided written comments in which they expressed
appreciation for the opportunity to review the report, but did not state
whether they agreed or disagreed with our findings. These agencies’
comments are reprinted in appendixes XI and XII, respectively.

Further, in an email from OMB staff on May 22, 2019, the agency did not
state whether it agreed or disagreed with our findings, but provided
technical comments that we incorporated, as appropriate.


Page 25                                                   GAO-19-471 Legacy IT
We are sending copies of this report to the appropriate congressional
committees; the Secretaries of the Departments of Agriculture,
Commerce, Defense, Education, Energy, Health and Human Services,
Homeland Security, Housing and Urban Development, Labor, State, the
Interior, the Treasury, Transportation, and Veterans Affairs; the U.S.
Attorney General (Department of Justice); the Administrators of the
Environmental Protection Agency, General Services Administration,
National Aeronautics and Space Administration, Small Business
Administration, and the U.S. Agency for International Development; the
Commissioner of the Social Security Administration; the Directors of the
National Science Foundation and the Office of Personnel Management;
and the Chairman of the Nuclear Regulatory Commission; and other
interested parties. This report is also available at no charge on the GAO
website at http://www.gao.gov.

Should you or your staffs have any questions on information discussed in
this report, please contact me at (202) 512-4456 or harriscc@gao.gov.
Contact points for our Offices of Congressional Relations and Public
Affairs may be found on the last page of this report. GAO staff who made
major contributions to this report are listed in appendix XIII.




Carol C. Harris
Director
Information Technology Management Issues




Page 26                                                  GAO-19-471 Legacy IT
List of Requesters

The Honorable Elijah E. Cummings
Chairman
The Honorable Jim Jordan
Ranking Member
Committee on Oversight and Reform
House of Representatives

The Honorable Gerald E. Connolly
Chairman
The Honorable Mark Meadows
Ranking Member
Subcommittee on Government Operations
Committee on Oversight and Reform
House of Representatives

The Honorable Will Hurd
House of Representatives

The Honorable Robin L. Kelly
House of Representatives




Page 27                                 GAO-19-471 Legacy IT
Appendix I: Objectives, Scope, and
              Appendix I: Objectives, Scope, and
              Methodology



Methodology

              Our objectives were to (1) identify the most critical federal legacy systems
              in need of modernization and evaluate plans for modernizing them, and
              (2) identify examples of information technology (IT) legacy system
              modernization initiatives in the last 5 years that agencies considered
              successful. The scope of our review included the 24 agencies covered by
              the Chief Financial Officers Act of 1990. 1

              This report presents a public version of a “limited official use only”
              (LOUO) report that we are also issuing today. 2 The Department of
              Homeland Security and the Department of the Interior determined that
              certain information in our original report should be protected from public
              disclosure. Therefore, we will not release the LOUO report to the general
              public because of the sensitive information it contains.

              The LOUO report includes eight recommendations that we made to eight
              agencies to document modernization plans for particular legacy systems,
              including milestones, a description of the work necessary, and details on
              the disposition of the legacy system. 3 In this public version of the report,
              we have omitted sensitive information regarding particular legacy
              systems. Specifically, we have deleted systems’ names and other
              information that would identify the particular system, such as specific
              descriptions of the systems’ purposes and vulnerabilities.

              Although the information provided in this report is more limited, the report
              addresses the same objectives as the LOUO report and is based on the
              same audit methodology. We provided a draft of this report to agency
              officials to obtain their review and comments on the sensitivity of the
              information contained herein. We confirmed with the agency officials that


              1
               The 24 major federal agencies covered by the Chief Financial Officers Act of 1990 are
              the Departments of Agriculture, Commerce, Defense, Education, Energy, Health and
              Human Services, Homeland Security, Housing and Urban Development, the Interior,
              Justice, Labor, State, Transportation, the Treasury, and Veterans Affairs; Environmental
              Protection Agency; General Services Administration; National Aeronautics and Space
              Administration; National Science Foundation; Nuclear Regulatory Commission; Office of
              Personnel Management; Small Business Administration; and U.S. Agency for International
              Development.
              2
               GAO, Information Technology: Agencies Need to Develop Modernization Plans for
              Critical Legacy Systems, GAO-19-351SU (Washington, D.C.: June 11, 2019).
              3
               We made recommendations to the Departments of Education, Health and Human
              Services, Homeland Security, Transportation, the Treasury; the Office of Personnel
              Management; Small Business Administration; and Social Security Administration.




              Page 28                                                            GAO-19-471 Legacy IT
Appendix I: Objectives, Scope, and
Methodology




this report can be made available to the public without jeopardizing the
security of federal agencies’ legacy systems.

To identify the most critical legacy systems in need of modernization, we
first reviewed the agencies’ 2017 responses to congressional committees’
requests for information that identified the agencies’ top three legacy
systems in need of modernization. We then asked the agencies to either
confirm that those systems were still considered their top systems in need
of modernization or update their lists to include the three systems most in
need of modernization. All 24 agencies either confirmed or updated their
lists of legacy systems most in need of modernization. This resulted in a
collective list of 65 systems. 4 However, due to sensitivity concerns, we
are not disclosing the names of the systems in this report. Appendix II
provides a generalized list of the systems.

To develop a set of attributes for determining systems’ obsolescence and
their need for modernization, we reviewed available technical literature,
such as:

•   General Services Administration’s Unified Shared Services
    Management’s 5 Modernization and Migration Management (M3)
    Playbook and M3 Playbook Guidance, 6
•   American Technology Council’s 7 Report to the President on Federal
    IT Modernization, 8

4
 Most agencies provided a list of three legacy systems in need of modernization.
However, the Department of Education reported four legacy systems, the Department of
Commerce reported two legacy systems, and the Departments of Agriculture and Energy
each reported one legacy system. The U.S. Agency for International Development stated
that it did not have any legacy systems.
5
 The Unified Shared Services Management office resides within the General Services
Administration and is to provide the strategy and leadership to make mission-enabling
services better, faster, and more affordable.
6
 General Services Administration, Unified Shared Services Management, Modernization
and Migration Management (M3) Playbook (Aug. 3, 2016); M3 Playbook Guidance (Aug.
3, 2016).
7
 The American Technology Council was established in May 2017, and has the goal of
helping to transform and modernize federal agency IT and how the federal government
uses and delivers digital services. The President is the chairman of this council, and the
Federal CIO and the United States Digital Service Administrator are among the members.
8
 American Technology Council, Report to the President on Federal IT Modernization
(Dec. 13, 2017).




Page 29                                                             GAO-19-471 Legacy IT
Appendix I: Objectives, Scope, and
Methodology




•    Office of Management and Budget’s Management of Federal High
     Value Assets Memorandum, 9
•    IBM Center for The Business of Government’s A Roadmap for IT
     Modernization in Government, 10 and
•    American Council for Technology-Industry Advisory Council’s Legacy
     System Modernization: Addressing Challenges on the Path to
     Success. 11
We also consulted with system development experts within GAO and
reviewed our prior report on federal legacy systems. 12 Using these
sources, we developed a set of 14 total attributes for determining
systems’ obsolescence and their need for modernization. We then asked
the agencies in our review to provide the associated details for the
selected systems. We considered these details to rank the systems
against the attributes that we compiled. We assigned point values to each
system based on the systems’ agency-reported attributes. Table 4 details
the nine attributes and associated point values and ranges we used to
initially rank the legacy systems.




9
  Office of Management and Budget, Management of Federal High Value Assets, M-17-09
(Washington, D.C.: Dec. 9, 2016). This was the memorandum that was in place at the
time of our analysis. It has since been rescinded and replaced by M-19-03.
10
 Dr. Gregory S. Dawson, Arizona State University, IBM Center for The Business of
Government, A Roadmap for IT Modernization in Government (Washington, D.C.: 2018).
11
 American Council for Technology-Industry Advisory Council, Legacy System
Modernization: Addressing Challenges on the Path to Success (Fairfax, VA: Oct. 7, 2016).
12
 GAO, Information Technology: Federal Agencies Need to Address Aging Legacy
Systems, GAO-16-468 (Washington, D.C.: May 25, 2016).




Page 30                                                           GAO-19-471 Legacy IT
                                               Appendix I: Objectives, Scope, and
                                               Methodology




Table 4: Attributes and Associated Point Values Used to Rank Legacy Systems

System attribute                       Point values
Initial year of implementation         0 points if the system had been implemented in the 2010s
                                       2 points if the system had been implemented in the 2000s
                                       4 points if the system had been implemented in the 1990s
                                       6 points if the system had been implemented in the 1980s
                                       8 points if the system had been implemented in the 1970s
                                       10 points if the system had been implemented before 1970
High Value Asseta status               10 points if system had been a High Value Asset; 0 points if not
Date of oldest hardware                0 points if the oldest hardware had been installed in the 2010s
                                       1 point if the oldest hardware had been installed in the 2000s
                                       2 points if the oldest hardware had been installed in the 1990s
                                       3 points if the oldest hardware had been installed in the 1980s
                                       4 points if the oldest hardware had been installed in the 1970s
                                       5 points if the oldest hardware had been installed before 1970
Hardware warranty status               5 points if the system’s hardware was no longer under warranty; 0 points if the hardware was
                                       under warranty
Operating system support status        5 points if the system’s operating system was no longer supported by the vendor; 0 points if the
                                       operating system was supported
Software support status                5 points if the system’s software was no longer supported by the vendor; 0 points if the software
                                       was supported
Use of legacy programming              5 points if the system used a programming language that the agency identified as a legacy
language                               language; 0 points if the system did not use legacy programming languages
System criticality (on a scale of 1    1 – 5 points, as assessed by the agency
to 5, 5 being most critical)
Security risk (on a scale of 1 to 5,   1 – 5 points, as assessed by the agency
5 having the most risk)
Source: GAO analysis. | GAO-19-471
                                               a
                                                At the time of our analysis, the Office of Management and Budget’s memorandum M-17-09 was in
                                               place and defined High Value Assets as those assets, federal information systems, information, and
                                               data for which an unauthorized access, use, disclosure, disruption, modification, or destruction could
                                               cause significant impact to the United States’ national security interests, foreign relations, economy,
                                               or to the public confidence, civil liberties, or public health and safety of the American people. This
                                               memorandum and definition has since been rescinded and replaced by M-19-03.


                                               We then totaled the assigned points for each legacy system and ranked
                                               the results from highest to lowest number of assigned points. While we
                                               had planned to select the top 20 systems with the most points for more
                                               detailed analysis, three systems were ranked in nineteenth place. As a
                                               result, we selected 21 systems for our review.




                                               Page 31                                                                        GAO-19-471 Legacy IT
                                          Appendix I: Objectives, Scope, and
                                          Methodology




                                          We collected additional information on the 21 selected systems and
                                          performed a second round of analysis, scoring, and ranking. Based on
                                          the second set of scores, we identified the 10 systems with the highest
                                          scores as being the most critical legacy systems in need of
                                          modernization. We also supplemented our review with interviews of
                                          officials in the agencies’ offices of the Chief Information Officer and
                                          program offices for the selected legacy systems. Table 5 details the five
                                          attributes and associated point values and ranges we used to rank the
                                          legacy systems in the subsequent round of analysis. Table 6 lists these
                                          10 selected systems according to their designated identifiers. However,
                                          due to sensitivity concerns, we substituted a numeric identifier for the
                                          name of each system.

Table 5: Attributes and Associated Point Values Used to Rank Legacy Systems in the Subsequent Round of Analysis

System attribute                   Point values
Status of modernization plans      5 points if the agency did not have plans to modernize the system; 0 points if the agency had
                                   plans to modernize the system
Number of users                    0 points if the system had under 100 users
                                   1 point if the system had 100 to 5,000 users
                                   2 points if the system had 5,000 to 25,000 users
                                   3 points if the system had 25,000 to 100,000 users
                                   4 points if the system had 100,000 to 500,000 users
                                   5 points if the system had more than 500,000 users
Potential annual cost savings of   0 points if the modernization of the system could potentially result in cost savings of less than
system modernization               $100,000
                                   1 point if the modernization of the system could potentially result in cost savings of $100,000 to
                                   $500,000
                                   2 points if the modernization of the system could potentially result in cost savings of $500,000 to
                                   $2 million
                                   3 points if the modernization of the system could potentially result in cost savings of $2 million to
                                   $10 million
                                   4 points if the modernization of the system could potentially result in cost savings of $10 million
                                   to $20 million
                                   5 points if the modernization of the system could potentially result in cost savings of more than
                                   $20 million
Annual operating costs             0 points if the system’s annual operating costs were under $100,000
                                   1 point if the system’s annual operating costs were between $100,000 and $500,000
                                   2 points if the system’s annual operating costs were between $500,000 and $2 million
                                   3 points if the system’s annual operating costs were between $2 million and $10 million
                                   4 points if the system’s annual operating costs were between $10 million and $20 million
                                   5 points if the system’s annual operating costs were more than $20 million




                                          Page 32                                                                 GAO-19-471 Legacy IT
                                            Appendix I: Objectives, Scope, and
                                            Methodology




System attribute                     Point values
Annual labor costs                   0 points if the system’s annual labor costs were under $100,000
                                     1 point if the system’s annual labor costs were between $100,000 and $500,000
                                     2 points if the system’s annual labor costs were between $500,000 and $2 million
                                     3 points if the system’s annual labor costs were between $2 million and $10 million
                                     4 points if the system’s annual labor costs were between $10 million and $20 million
                                     5 points if the system’s annual labor costs were more than $20 million
Source: GAO analysis. | GAO-19-471




                                            Table 6: The 10 Selected Most Critical Legacy Systems in Need of Modernization

                                             Agency                                                      System name
                                             Department of Defense                                       System 1
                                             Department of Education                                     System 2
                                             Department of Health and Human Services                     System 3
                                             Department of Homeland Security                             System 4
                                             Department of the Interior                                  System 5
                                             Department of the Treasury                                  System 6
                                             Department of Transportation                                System 7
                                             Office of Personnel Management                              System 8
                                             Small Business Administration                               System 9
                                             Social Security Administration                              System 10
                                            Source: GAO analysis of agency documentation. | GAO-19-471



                                            To evaluate agencies’ plans for modernizing the 10 federal legacy
                                            systems most in need of modernization, we requested that agencies
                                            provide us with the relevant plans. These modernization plans could have
                                            been contained within several types of documentation, since a system
                                            modernization could be a new system development, a system acquisition,
                                            or a renovation of the legacy system. For example, if an agency was
                                            acquiring a new system from a vendor, the plans for modernization could
                                            have been contained within an acquisition plan or a statement of work in
                                            a contract. Likewise, if an agency was developing a new system on its
                                            own, the modernization plans could have been within a project plan or
                                            design document.

                                            We reviewed government and industry best practice documentation on
                                            the identification and modernization of legacy systems, including:




                                            Page 33                                                                    GAO-19-471 Legacy IT
Appendix I: Objectives, Scope, and
Methodology




•    General Services Administration’s Unified Shared Services
     Management’s 13 Modernization and Migration Management (M3)
     Playbook and M3 Playbook Guidance, 14
•    American Technology Council’s 15 Report to the President on Federal
     IT Modernization, 16
•    Office of Management and Budget’s Management of Federal High
     Value Assets memorandum, 17
•    IBM Center for The Business of Government’s A Roadmap for IT
     Modernization in Government, 18 and
•    American Council for Technology-Industry Advisory Council’s Legacy
     System Modernization: Addressing Challenges on the Path to
     Success. 19
Based on our reviews of these sources, we determined that agencies’
documented plans for system modernization should include, at a
minimum, (1) milestones to complete the modernization, (2) a description
of the work necessary to modernize the system, and (3) details regarding
the disposition of the legacy system. We then analyzed agencies’
documented modernization plans for the selected systems to determine
whether the plans included these elements. If an agency’s plans included

13
  The Unified Shared Services Management office resides within the General Services
Administration and is to provide the strategy and leadership to make mission-enabling
services better, faster, and more affordable.
14
  General Services Administration, Unified Shared Services Management, Modernization
and Migration Management (M3) Playbook (Aug. 3, 2016); M3 Playbook Guidance (Aug.
3, 2016).
15
  The American Technology Council was established in May 2017, and has the goal of
helping to transform and modernize federal agency IT and how the federal government
uses and delivers digital services. The President is the chairman of this council, and the
Federal CIO and the United States Digital Service Administrator are among the members.
16
  American Technology Council, Report to the President on Federal IT Modernization
(Dec. 13, 2017).
17
  Office of Management and Budget, Management of Federal High Value Assets, M-17-09
(Washington, D.C.: Dec. 9, 2016). This was the memorandum that was in place at the
time of our analysis. It has since been rescinded and replaced by M-19-03.
18
 Dr. Gregory S. Dawson, Arizona State University, IBM Center for The Business of
Government, A Roadmap for IT Modernization in Government (Washington, D.C.: 2018).
19
 American Council for Technology-Industry Advisory Council, Legacy System
Modernization: Addressing Challenges on the Path to Success (Fairfax, VA: Oct. 7, 2016).




Page 34                                                             GAO-19-471 Legacy IT
Appendix I: Objectives, Scope, and
Methodology




milestones for only a portion of the initiative or only described a portion of
the work necessary to complete the modernization, we assigned the
agency a partial rating. Appendix III provides details on each of the
selected systems and the agencies’ plans for modernizing them.

To identify examples of successful IT legacy system modernization
initiatives, we first asked each of the 24 agencies to provide us with
examples of their successful modernization initiatives completed between
2014 and 2018. The agencies reported 94 examples of successful
modernization initiatives. We also reviewed the agencies’ responses to
congressional committees’ requests for information to determine other
possible successful modernization initiatives at these agencies. Using the
examples discovered in this process and the agency-provided examples,
we then collected and reviewed documentation describing the
modernization initiatives, such as case studies and the agencies’ written
responses to our questions about the initiatives.

We used our professional judgment to select examples that reflected a
mix of different agencies, types of system modernization initiatives, and
types of benefits realized from the initiatives. We ultimately included in
our review those modernization initiatives that two or more members of
our audit team selected as examples that reflected a mix of different
agencies, types of system modernization initiatives, and types of benefits
realized from the initiatives. We also coordinated with the selected
agencies’ Offices of Inspector General to determine whether those offices
had any past or current audit work that would contradict the agencies’
determination that the selected initiatives were successful.

We conducted this performance audit from January 2018 to June 2019 in
accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.




Page 35                                                    GAO-19-471 Legacy IT
Appendix II: The 24 Chief Financial Officers
                                          Appendix II: The 24 Chief Financial Officers
                                          Act Agencies’ Most Critical Legacy Systems in
                                          Need of Modernization


Act Agencies’ Most Critical Legacy Systems
in Need of Modernization
                                          Each of the 24 Chief Financial Officers Act agencies identified their
                                          agency’s most critical legacy systems in need of modernization. The
                                          agencies identified a total of 65 such systems. 1 The agencies also
                                          identified various attributes of the legacy systems, including the systems’
                                          age, hardware age, 2 system criticality, and security risk. Table 7 provides
                                          a generalized list of the most critical legacy systems in need of
                                          modernization, as identified by the agencies, as well as selected factors
                                          related to each system’s age and criticality. (Due to sensitivity concerns,
                                          we substituted alphanumeric identifiers for the names of the agencies’
                                          systems. Specifically, we assigned a number to identify each of the 10
                                          most critical legacy systems in need of modernization that we discuss in
                                          this report and we assigned a letter or letters to identify the remaining 55
                                          systems.)

Table 7: Combined List of Agencies’ Most Critical Legacy Systems in Need of Modernization

                                                         Age of                 Age of System criticality   Security risk
                                                      system, in     oldest hardware (as determined         (as determined
Agency                         System namea                years   installed, in years by agency)           by agency)
Department of Agriculture      System A                        8            Unknownb High                   Moderately low
Department of Commerce         System B                       16                     5 High                 High
                               System C                       25                     7 High                 Low
Department of Defense          System 1                       14                     3 Moderately high      Moderate
                               System D                       55                     5 High                 Low
                               System E                       33                    12 High                 Moderately low
Department of Education        System 2                       46                     3 High                 High
                               System F                       13                    12 High                 Moderately high
                               System G                       25                     5 High                 High
                               System H                       24                    17 Moderate             High
Department of Energy           System I                       32                     2 High                 Low
Department of Health and       System 3                       50              Variousc High                 High
Human Services                                                                        b
                               System J                       21            Unknown       High              Moderate
                               System K                        7                     8 High                 Moderate

                                          1
                                           Most agencies provided a list of three legacy systems in need of modernization.
                                          However, the Department of Education reported four legacy systems, the Department of
                                          Commerce reported two legacy systems, and the Departments of Agriculture and Energy
                                          each reported one legacy system. The U.S. Agency for International Development stated
                                          that it did not have any legacy systems.
                                          2
                                           A legacy system may run on updated hardware, and, thus, the system’s age and
                                          hardware age may not be the same.




                                          Page 36                                                            GAO-19-471 Legacy IT
                                             Appendix II: The 24 Chief Financial Officers
                                             Act Agencies’ Most Critical Legacy Systems in
                                             Need of Modernization




                                                            Age of                 Age of System criticality   Security risk
                                                         system, in     oldest hardware (as determined         (as determined
Agency                           System namea                 years   installed, in years by agency)           by agency)
Department of Homeland           System 4                        11                    11 High                 High
Security
                                 System L                         9                     2 High                 Moderately low
                                 System M                         6                     1 High                 Low
Department of Housing and        System N                        42                     2 High                 Moderate
Urban Development
                                 System O                        44                     2 High                 Moderate
                                 System P                        44                     2 High                 Moderate
Department of Justice            System Q                        21                    10 High                 High
                                 System R                        38                     7 High                 Moderately low
                                 System S                        49                     6 Moderately high      Low
Department of Labor              System T                        14                     9 High                 Low
                                 System U                        21                    10 High                 Low
                                 System V                        15                     3 High                 Moderate
Department of State              System W                        24                     5 High                 Moderate
                                 System X                        21                     5 Moderately high      Moderate
                                 System Y                        20                     3 Moderately high      Moderate
Department of the Interior       System 5                        18                    18 High                 Moderately high
                                 System Z                        29                     9 High                 High
                                 System AA                       23                    23 Moderately high      Low
Department of the Treasury       System 6                        51                     4 High                 Moderately low
                                 System AB                       13                    10 Moderate             Moderate
                                 System AC                       10                     8 High                 Moderately low
Department of Transportation     System 7                        35                     7 High                 Moderately high
                                 System AD                       17                     4 High                 Moderately high
                                                                                         b
                                 System AE                       19                  n/a     High              High
Department of Veterans Affairs   System AF                       31                     3 High                 Low
                                 System AG                       49                     2 High                 Moderately low
                                 System AH                       31                     4 High                 Moderate
Environmental Protection         System AI                       24                     1 High                 Low
Agency
                                 System AJ                       17                     1 High                 Low
                                 System AK                       14                     1 High                 Low
General Services Administration System AL                        39                     2 High                 Low
                                 System AM                        5                    10 High                 Moderate
                                                                                         b
                                 System AN                        8            Unknown       High              Moderate
National Aeronautics and Space System AO                         10                    13 High                 High
Administration
                               System AP                   About 19                    31 Moderately high      Moderately low
                                 System AQ                        6                     6 High                 Low




                                             Page 37                                                            GAO-19-471 Legacy IT
                                                             Appendix II: The 24 Chief Financial Officers
                                                             Act Agencies’ Most Critical Legacy Systems in
                                                             Need of Modernization




                                                                                Age of                   Age of System criticality          Security risk
                                                                             system, in       oldest hardware (as determined                (as determined
Agency                                         System namea                       years     installed, in years by agency)                  by agency)
Nuclear Regulatory Commission System ARd                                               11                       7 Moderately high           Moderate
                                                             d
                                               System AS                               20                       2 Moderately high           Moderate
                                               System AT                               15                       9 Moderately high           Moderately low
National Science Foundation                    System AU                               18                       2 High                      Moderately low
                                               System AV                               18                       2 Moderate                  Moderately low
                                               System AW                               22                       2 Moderate                  Moderate
Office of Personnel                            System 8                                34                       6 High                      Moderately low
Management
                                               System AX                               29                       6 High                      Moderately high
                                               System AY                               21                       6 High                      Moderately low
Small Business Administration                  System 9                                17                      10 High                      Moderately high
                                               System AZ                               13                      10 Moderately high           Moderately high
                                               System BA                               15                       3 High                      Moderately high
Social Security Administration                 System 10                               45                       5 High                      Moderate
                                               System BB                               34                       5 High                      Moderate
                                               System BC                               38                       4 High                      Moderate
U.S. Agency for International                  n/a – Agency stated that it does not have any legacy systems.
Development

Key:
Agencies reported the system criticality and security risk on a scale of 1 to 5 (with 5 being the most critical or the highest risk). We assigned the following
based on those numbers.
Low-1: According to the agency, system has low security risk or criticality.
Moderately low-2: According to the agency, system has moderately low security risk or criticality.
Moderate-3: According to the agency, system has moderate security risk or criticality.
Moderately high-4: According to the agency, system has moderately high security risk or criticality.
High-5: According to the agency, system has high security risk or criticality.
Source: GAO analysis of agency documentation. | GAO-19-471
                                                             a
                                                                 Due to sensitivity concerns, we substituted an alphanumeric identifier for the system names.
                                                             b
                                                              The agency procures services from a vendor or another agency and was not able to get the
                                                             information from the vendor.
                                                             c
                                                              The agency stated that the system’s hardware had various refresh dates and was not able to identify
                                                             the oldest hardware.
                                                             d
                                                                 This system has been decommissioned since the agency reported it to us.




                                                             Page 38                                                                         GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
                Appendix III: Profiles of the 10 Most Critical
                Legacy Systems in Need of Modernization



Legacy Systems in Need of Modernization

                This appendix describes the 10 most critical legacy systems in need of
                modernization, as identified during our review. The profiles of each
                system describe (1) the system’s purpose, (2) the reason that the system
                needs to be modernized, (3) the agency’s plans for modernization, and
                (4) possible benefits to be realized once the system is modernized.




                Page 39                                                GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 1                                           The Department of Defense (DOD)—U.S. Air Force’s System 1 provides
                                                   configuration control and management to support wartime readiness and
Department of Defense—U.S. Air Force               operational support of aircraft, among other things. See figure 1 for a
Reported number of users: Approximately            photograph of airmen maintaining an aircraft.
242,672
Initial year of implementation: 2005
                                                   Figure 1: Airmen Maintaining an Air Force Aircraft
System hardware under warranty?
Agency did not know
Software vendor supported? No
Operating system(s) supported? Yes
Legacy programming language(s) used?
Yes
System criticality (as determined by
agency): Moderately high
System security risk (as determined by
agency): Moderate
Reported annual operating costs: $21.8
million
Reported annual labor costs: $3.6 million
Reported cost of modernization: $12
million
Potential cost savings: $34 million annually
Other benefits: Increased functionality,
increased aircraft touch time and availability
Status of modernization plans: Agency
has documented modernization plans that
include milestones to complete the
modernization, descriptions of the work
necessary to modernize the legacy system,          According to Air Force documentation, the cost to maintain and sustain
and plans for the disposition of the legacy        the system has been steadily increasing due to several factors, including
system
Source: GAO analysis of agency documentation and
                                                   (1) costs associated with maintaining and operating the system’s
interviews. | GAO-19-471                           infrastructure and the manpower to maintain the legacy code; and (2) the
                                                   difficulty and cost of experienced Common Business Oriented Language
                                                   (COBOL) 1 programmers, poor legacy documentation, and an aging
                                                   infrastructure and code. In addition, the system runs on a mainframe that
                                                   is hosted by another agency. As a result of these issues, Air Force
                                                   officials expect annual costs to rise from $21.8 million in 2018 to
                                                   approximately $35 million beginning in 2020.



                                                   1
                                                    COBOL, which was introduced in 1959, became the first widely used, high-level
                                                   programming language for business applications. The Gartner Group, a leading
                                                   information technology research and advisory company, has reported that organizations
                                                   using COBOL should consider replacing the language, as procurement and operating
                                                   costs are expected to steadily rise, and because there is a decrease in people available
                                                   with the proper skill sets to support the language.




                                                   Page 40                                                             GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




In September 2018, the Air Force awarded a contract to modernize and
migrate the system to a cloud environment by September 2019. DOD
contractors developed a project plan for the modernization that contains
goals and outlines how the contractor plans to move through the
modernization process, listing out sequential tasks leading to project
completion. In addition, it outlines milestones from the starting point
through implementation, and provides for the disposition of the legacy
system. After the migration, as funding allows, the Air Force plans to
incrementally transform the system’s COBOL code to a more modern
language.

Air Force program office officials stated that the modernized system will
save the agency over $34 million a year, resulting in $356 million saved
over a 10-year period. Officials also noted that, given the savings, the
modernization would pay for itself in only 5 months. The Air Force also
expects increased functionality with this modernization leading to
increased aircraft touch time 2 and aircraft availability by enabling adoption
of new technologies.




2
 Aircraft touch time is the time spent performing aircraft maintenance tasks.




Page 41                                                               GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 2                                           The Department of Education’s (Education) System 2 processes and
                                                   stores student information and supports the processing of federal student
Department of Education—Federal
                                                   aid applications.
Student Aid
Reported number of users: Over 20 million          Education first implemented System 2 in 1973. 3 Agency officials stated
student applications annually and thousands
of other users
                                                   that the system runs approximately 1 million lines of Common Business
Initial year of implementation: 1973
                                                   Oriented Language (COBOL) 4 on an IBM mainframe. COBOL is a legacy
System hardware under warranty? Yes                language that can be costly to maintain. The department noted that 18
Software vendor supported? Yes                     contractors are employed to maintain the COBOL programming language
Operating system(s) supported? Yes                 for this and another system. Education officials stated that the agency
Legacy programming language(s) used?               would like to modernize System 2 to eliminate reliance on COBOL,
Yes                                                simplify user interactions, improve integration with other applications,
System criticality (as determined by
agency): High
                                                   respond to changing business requirements more quickly, and decrease
System security risk (as determined by             development and operational costs.
agency): High
Reported annual operating costs: $43.9             Education officials stated that the agency intends to modernize System 2
million
                                                   as part of its Next Generation Financial Services Environment initiative.
Reported annual labor costs: $2.0 million
                                                   This initiative is to modernize Federal Student Aid’s technical and
Reported cost of modernization: Agency
has not determined costs                           operational architecture and improve the customer experience. The
Potential cost savings: Agency has not             agency expects to consolidate all customer-facing websites and
calculated                                         implement a new loan servicing platform to benefit federal student loans.
Other benefits: Integration across the
enterprise, improved cybersecurity and data
protection, reduced system complexity, and         Education has not developed a plan for the modernization of System 2.
increased efficiency                               According to agency officials, these plans are pending the results of a
Status of modernization plans: Agency              comprehensive information technology (IT) visualization and engineering
does not have a modernization plan
Source: GAO analysis of agency documentation and
                                                   project that will determine which IT systems and services could be
interviews. | GAO-19-471                           feasibly modernized, consolidated, or eliminated.

                                                   While Education has not calculated the specific cost savings associated
                                                   with modernizing System 2, the department anticipates potential cost
                                                   savings, including decreased hardware and software licensing costs and
                                                   decreased costs associated with changes to business rules. According to
                                                   the agency, other potential benefits of modernizing this system include


                                                   3
                                                    At the time, Education was part of the Department of Health, Education, and Welfare.
                                                   4
                                                    COBOL, which was introduced in 1959, became the first widely used, high-level
                                                   programming language for business applications. The Gartner Group, a leading
                                                   information technology research and advisory company, has reported that organizations
                                                   using COBOL should consider replacing the language, as procurement and operating
                                                   costs are expected to steadily rise, and because there is a decrease in people available
                                                   with the proper skill sets to support the language.




                                                   Page 42                                                             GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




integration across the enterprise, improved cybersecurity and data
protection, reduced system complexity, and improved system efficiency.




Page 43                                               GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 3                                           The Department of Health and Human Services’ (HHS) System 3 is a
                                                   clinical and patient administrative information system. HHS’s component,
Department of Health and Human                     Indian Health Service’s (IHS) uses the system to gather, store, and
Services—Indian Health Service                     display clinical, administrative, and financial information on patients seen
Reported number of users: Approximately            in a clinic, hospital, or remotely through the use of telehealth and home
20,000
Initial year of implementation: 1969
                                                   visit practices.
System hardware under warranty? Yes
Software vendor supported? Yes                     HHS officials stated that the modernization of System 3 is imperative.
Operating system(s) supported? Yes                 Specifically, the agency noted that the system’s technical architecture and
Legacy programming language(s) used?               infrastructure were outdated. This has resulted in challenges in
Yes                                                developing new capabilities in response to business and regulatory
System criticality (as determined by               requirements. Further, System 3 is coded in C++ and MUMPS. MUMPS
agency): High
System security risk (as determined by
                                                   is a programming language that HHS considers to be a legacy language. 5
agency): High                                      The agency noted that it has become increasingly difficult to find
Reported annual operating costs: $79.1             programmers proficient in writing code for MUMPS. Lastly, the system’s
million
                                                   more than 50 modules were added over time to address new business
Reported annual labor costs: $26.7
million
                                                   requirements. The software is installed on hundreds of separate
Reported cost of modernization: Agency             computers, which has led to variations in the configurations at each site.
has not calculated                                 According to IHS, this type of add-on development becomes detrimental
Potential cost savings: Agency has not             over time and eventually requires a complete redesign to improve
calculated
                                                   database design efficiency, process efficiency, workflow integration, and
Other benefits: Improves interoperability
with other healthcare partners and                 graphical user interfaces.
enhances patient care
Status of modernization plans: Agency              While the agency does not yet have modernization plans, in September
does not have a modernization plan
                                                   2018, HHS awarded a contract to conduct research for modernizing IHS’s
Source: GAO analysis of agency documentation and
interviews. | GAO-19-471                           health information technology (IT) infrastructure, applications, and
                                                   capabilities. According to the department, the research will be conducted
                                                   in several stages over the next year, and a substantial part of the
                                                   research will be an evaluation of the current state of health IT across
                                                   IHS’s health facilities. Once the research is conducted, in consultation
                                                   with IHS and its stakeholders, the contractor will use the findings and
                                                   recommendations to propose a prioritized roadmap for modernization.
                                                   According to HHS, the agency will be completing the modernization
                                                   initiative over the next 5 years, but anticipated that it may be able to begin
                                                   to execute an implementation plan as early as 2020.



                                                   5
                                                    MUMPS was originally known as the Massachusetts General Hospital Utility Multi-
                                                   Programming System. It is a programming language developed originally for building
                                                   medical systems. In January 2018, we reported that there is a dwindling supply of
                                                   qualified software developers for MUMPS.




                                                   Page 44                                                           GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




With regards to potential cost savings, HHS noted that the modernization
will take significant capital investment to complete and it is unknown
whether the modernization will lead to cost savings. HHS officials stated
that this modernization could improve interoperability with its health care
partners, the Department of Veterans Affairs and the Department of
Defense, and significantly enhance direct patient care.




Page 45                                                  GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 4                                           The Department of Homeland Security—Federal Emergency
                                                   Management Agency’s (FEMA) System 4 consists of routers, switches,
Department of Homeland Security—                   firewalls, and other network appliances (all referred to as devices) to
Federal Emergency Management Agency                support the connectivity of FEMA sites.
Reported number of users: On average
30,000; more during a disaster
                                                   According to the agency, System 4 needs to be modernized because
Initial year of implementation: Between
2008 and 2011                                      there are significant cyber and network vulnerability risks associated with
System hardware under warranty? No                 its end of life (i.e., no longer supported or manufactured by the vendor)
Software vendor supported? No                      devices. In particular, the system’s devices typically require replacement
Operating system(s) supported? No                  every 3 to 5 years from the date of purchase. Despite this, the majority of
Legacy programming language(s) used?               the hardware was purchased between 8 and 11 years ago. As of
No
                                                   December 2018, about 545 of these devices were at the end of life.
System criticality (as determined by
agency): High
System security risk (as determined by             In a security assessment report performed in September 2018, System 4
agency): High                                      received 249 security findings, of which 168 were high or critical risk to
Reported annual operating costs: $1.9              the system. Further compounding this issue, the agency is not certain
million
                                                   exactly how many devices make up the system. In particular, FEMA
Reported annual labor costs: $0
Reported cost of modernization: Agency
                                                   officials stated that the vendor completed an inventory of devices in May
has not calculated                                 2018, but that inventory did not align with other inventory counts. As a
Potential cost savings: Agency has not             result, the agency plans to develop an inventory reconciliation strategy
calculated                                         and process to address this issue.
Other benefits: Ability to meet mission
requirements, reduction of network
downtime, and increased network availability       FEMA intends to replace System 4’s devices in two phases. The first
Status of modernization plans: Agency              phase will target the agency’s smaller facilities, while the second phase is
has documented modernization plans that            to address the larger facilities, which may require more complex
describe the work necessary to modernize
the system; however, they do not contain           installations. FEMA’s Office of the Chief Information Officer is conducting
milestones to complete the modernization or        site surveys to better define requirements and cost estimates. While the
plans for the disposition of legacy system
components following system modernization
                                                   agency has yet to develop finalized modernization plans for this initiative
Source: GAO analysis of agency documentation and   with milestones, DHS officials and contract information technology staff
interviews. | GAO-19-471
                                                   developed a list of future recommended activities that would help
                                                   modernize the system as part of their November 2018 quarterly business
                                                   review. Despite the lack of finalized plans, FEMA intends to replace 240
                                                   of the 545 devices that are at the end of support, if funds are available.
                                                   The agency also intends to upgrade the remaining 305 devices in the
                                                   future, if funds are available.

                                                   The agency has not calculated the exact amount of cost savings. Once
                                                   the system is completely updated and a lifecycle replacement operations
                                                   and maintenance support plan is in place and funded, FEMA and DHS
                                                   expect to realize cost savings based on new technology and increased




                                                   Page 46                                                   GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




throughput. 6 Further, the agency stated that with new equipment, it would
be able to meet mission requirements and take advantage of new
technologies. In addition, replacing these unsupported devices would
significantly reduce downtime and increase network availability.




6
 Throughput refers to the performance of tasks by a computing service or device over a
specific period. It measures the amount of completed work against time consumed and
may be used to measure the performance of a process, memory, and/or network
communications.




Page 47                                                            GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 5                                           The Department of the Interior’s (Interior) System 5 is an Industrial
                                                   Control System (ICS) Supervisory Control and Data Acquisition (SCADA)
Department of the Interior—Bureau of               System that supports the general operation of dams and power plants on
Reclamation                                        a particular river and its tributaries. The system serves its customers by,
Reported number of users: 49                       among other things, starting and stopping the generators, adjusting the
Initial year of implementation: 2001
                                                   output of electricity to assure electric grid stability, and monitoring the
System hardware under warranty? No
                                                   operating conditions of dam and power plant equipment. Figure 2 shows
Software vendor supported? No
                                                   an example of an Interior dam.
Operating system(s) supported? No
Legacy programming language(s) used?
Yes                                                Figure 2: Photograph of a Dam
System criticality (as determined by
agency): High
System security risk (as determined by
agency): Moderately high
Reported annual operating costs:
$427,000
Reported annual labor costs: $448,000
Reported cost of modernization: $4.5
million
Potential cost savings: $152,000 per year
Other benefits: Increased capacity for new
system requirements, elimination of
obsolete hardware, increased system
reliability
Status of modernization plans: Agency
has documented modernization plans that
include milestones to complete the
modernization, descriptions of the work
necessary to modernize the legacy system,
and plans for the disposition of legacy
system components following system
modernization
Source: GAO analysis of agency documentation and
interviews. | GAO-19-471



                                                   The system is approximately 18 years old and contains obsolete
                                                   hardware that is not supported by the manufacturers. Further, according
                                                   to a program official, the system’s original hardware and software
                                                   installation did not include any long-term vendor support. Thus, any
                                                   original components that remain operational may have had long-term
                                                   exposure to security and performance weaknesses. In January 2014, the
                                                   Director of National Intelligence testified that ICS and SCADA systems
                                                   used in electrical power distribution provided an enticing target to
                                                   malicious actors and that, although newer architectures provide flexibility,
                                                   functionality, and resilience, large segments of the systems remain
                                                   vulnerable to attack, potentially causing significant economic or human
                                                   impact. Further, according to Interior’s system modernization plans, the
                                                   agency needs to modernize the system in order to increase data


                                                   Page 48                                                   GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




collection capabilities and security. Specifically, the system is expected to
interface with more plant equipment and collect and report on more data
than it has in the past.

According to Interior’s plans, the modernized system is expected to
accommodate future growth requirements. The plans also support the
complete replacement of the system’s obsolete hardware and software.
The modernization plans also outline goals, milestones, and the work to
be accomplished. The agency plans to complete the modernization by
January 2020.

By replacing the legacy system, Interior plans to realize a number of
potential benefits, including annual cost savings of $152,000. In addition,
the system will no longer run on obsolete, unsupported hardware.
Furthermore, newer software and hardware are expected to allow for the
automation of compliance tasks, increase system security, and expand
system availability. According to the system’s fiscal year 2017 operational
analysis, these benefits should create a more reliable system for both the
agency and the customers of the networked hydroelectric dams.




Page 49                                                   GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 6                                           The Department of the Treasury’s Internal Revenue Service’s (IRS)
                                                   System 6 contains taxpayer data. Many IRS processes depend on output,
                                                   directly or indirectly, from this data source.
Department of the Treasury—Internal
Revenue Service
Reported number of users: 0
                                     a             System 6 was written in a now outdated assembly language code 7 and
Initial year of implementation: 1968               Common Business Oriented Language (COBOL). 8 The department and
System hardware under warranty? No                 we have raised a number of concerns related to this system’s reliance on
Software vendor supported? Yes                     assembly language code and COBOL, the maintainability of the system,
Operating system(s) supported? Yes                 and staff attrition. For example, in May 2016, we reported that legacy
Legacy programming language(s) used?               systems using outdated languages may become increasingly more
Yes
                                                   expensive and agencies may pay a premium to hire staff or contractors
System criticality (as determined by
agency): High                                      with the knowledge to maintain these systems. 9
System security risk (as determined by
agency): Moderately low                            IRS plans to address these concerns by modernizing core components of
Reported annual operating costs: $5.5              System 6. The new system is intended to provide improved functionality.
million
Reported annual labor costs: $10.4
                                                   However, IRS is having trouble fully staffing the modernization effort,
million                                            resulting in significant delays. While the agency has developed
Reported cost of modernization: $1.6               modernization plans, they are incomplete. For example, the plans’
billion                                            milestones do not go past the current project and their descriptions of the
Potential cost savings: None
                                                   work necessary to complete the project are at a higher level when
Other benefits: Quick resolution of
customer issues, reduced IT costs and
                                                   outlining the goals of future stages. In May 2019, the agency stated that
complexity, and enhanced analytics and             even when the current modernization effort is fully implemented, only a
reporting                                          portion of the work required to retire the legacy system will have been
Status of modernization plans: Agency              completed. The agency has not provided a target date for
has documented modernization plans that
describe the work necessary to modernize           decommissioning the legacy system.
the legacy system; however, they only
partially include milestones to complete the
modernization and do not include details on        While IRS does not anticipate cost savings associated with the
the disposition of the legacy system               modernization of this system, it anticipates many internal and external
                                                   benefits for both the taxpayer and the agency. In particular, according to
       a
Note: According to the agency, the system
does not have users in the traditional sense
and instead passes along data for
                                                   7
applications to use. In 2018, the system            As we reported in May 2016, assembly language code is a low-level computer language
assisted the agency in processing over 154         initially used in the 1950s. Programs written in assembly language are conservative of
million tax returns.                               machine resources and quite fast; however, they are much more difficult to write and
Source: GAO analysis of agency documentation and   maintain than other languages. Programs written in assembly language may only run on
interviews. | GAO-19-471
                                                   the type of computer for which they were originally developed.
                                                   8
                                                    COBOL, which was introduced in 1959, became the first widely used, high-level
                                                   programming language for business applications. The Gartner Group, a leading IT
                                                   research and advisory company, has reported that organizations using COBOL should
                                                   consider replacing the language, as procurement and operating costs are expected to
                                                   steadily rise, and because there is a decrease in people available with the proper skill sets
                                                   to support the language.
                                                   9
                                                    GAO, Information Technology: Federal Agencies Need to Address Aging Legacy
                                                   Systems, GAO-16-468 (Washington, D.C.: May 25, 2016).




                                                   Page 50                                                               GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




the IRS’s Fiscal Year 2019 Capital Investment Plan, the benefits of
modernizing this system include: (1) increased agility of agency response
to changing taxpayer priorities and legislation; (2) reduced IT costs and
complexity; (3) enhanced analytics and reporting to greatly improve
compliance and issue resolution; and (4) reduced burden of manually
intensive processes on IRS employees, by enabling automated
calculations that currently are not possible.




Page 51                                                GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 7                                           The Department of Transportation’s (Transportation) Federal Aviation
                                                   Administration’s (FAA) System 7 contains information on aircraft and
                                                   pilots. The system also provides information to other government
Department of Transportation—Federal
Aviation Administration                            agencies, including those responsible for homeland security and
Reported number of users: 160                      investigations of aviation accidents.
Initial year of implementation: 1984
System hardware under warranty?                    According to Transportation, the system is DOS-based and needs to be
Unknown                                            updated to continue to efficiently meet its mission. 10 Specifically, some of
Software vendor supported? No                      the core system components are mainframe applications that have been
Operating system(s) supported? No
                                                   in operation since 1984. In addition, the system is running unsupported
Legacy programming language(s) used?
No                                                 software, including one operating system that was last supported by the
System criticality (as determined by               vendor in 2010.
agency): High
System security risk (as determined by             FAA is planning to implement a new system to streamline processes,
agency): Moderately high
                                                   allow for the submission of electronic applications and forms, automate
Reported annual operating costs: $3.8
million                                            registration processes, improve data availability, and implement additional
Reported annual labor costs: $10.7                 security controls. However, the agency does not currently have a
million                                            documented modernization plan. Officials stated that the agency is
Reported cost of modernization: Agency             seeking alternatives to modernize the system and meet legislative
has not calculated
                                                   requirements. FAA has asked interested vendors to respond to a request
Potential cost savings: Agency has not
calculated                                         for information. According to the agency, the responses to this request
Other benefits: Enhanced security,                 are intended to inform strategic decisions about the modernization, and
compliance with law                                are planned to ultimately lead to proposed solutions from industry.
Status of modernization plans: Agency
does not have a modernization plan
Source: GAO analysis of agency documentation and
                                                   While FAA has not calculated the specific cost savings associated with
interviews. | GAO-19-471                           modernizing the system, the agency stated that it anticipates potential
                                                   cost savings. Agency officials stated that they plan to have information on
                                                   the anticipated cost savings in November 2019. The agency also expects
                                                   that the modernized system will provide enhanced security.




                                                   10
                                                     DOS, originally known as a disk operating system, is the operating system of a
                                                   computer that can be stored on and run off of a computer disk drive.




                                                   Page 52                                                             GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 8                                           The Office of Personnel Management’s (OPM) System 8 consists of the
                                                   hardware, software, and service components that support OPM’s
Office of Personnel Management                     information technology (IT) applications and services. This system
Reported number of users: Millions of              supports the agency’s business functions and supports the agency in
external users and 9,500 internal users            providing investigative products and services for more than 100 federal
Initial year of implementation: 1985
                                                   agencies.
System hardware under warranty? Yes
Software vendor supported? No
                                                   Modernizing this system is especially important due to past security
Operating system(s) supported? Yes
Legacy programming language(s) used?
                                                   incidents and persistent security concerns. Specifically, according to
Yes                                                OPM, segments of the agency’s infrastructure were allowed to age
System criticality (as determined by               beyond end of life and now pose a significant risk in performance and
agency): High                                      security to IT operations. 11 Further, in October 2017, OPM’s Office of the
System security risk (as determined by
agency): Moderately low
                                                   Inspector General (OIG) reported that the agency’s IT environment
Reported annual operating costs: $45.0             contained many instances of unsupported software and hardware, where
million                                            the vendor no longer provided patches, security fixes, or updates for the
Reported annual labor costs: $6.0 million          software. As a result, the OIG noted that there was increased risk that
Reported cost of modernization:                    OPM’s IT environment contained known vulnerabilities that would never
Approximately $10 million
                                                   be patched, and could have been exploited to allow unauthorized access
Potential cost savings: Approximately
$16.0 million in cost avoidance in fiscal year     to data. In June 2015, OPM reported that an intrusion into its systems had
2018                                               affected the personnel records of about 4.2 million current and former
Other benefits: Reduction in cybersecurity         federal employees. Then, in July 2015, the agency reported that a
and operational risks, ability to address
security vulnerabilities, avoidance of             separate but related incident had compromised its systems and the files
operational downtime                               related to background investigations for 21.5 million individuals. At a June
Status of modernization plans: Agency              2015 Congressional hearing, OPM’s Director stated that the
has documented modernization plans that
partially include milestones to complete the
                                                   modernization of the IT infrastructure was critical to protecting the
modernization and partially describe the           agency’s data from adversaries. The Director also stated that it was not
work necessary to modernize the legacy             feasible to implement encryption on networks that were too old, but noted
system; however, they do not include plans
for the disposition of legacy system               that OPM was taking other steps to secure the networks. 12
components following system modernization
Source: GAO analysis of agency documentation and
interviews. | GAO-19-471                           OPM plans to modernize System 8 by upgrading hardware at the end of
                                                   life, migrating off of legacy operating systems and support software, and
                                                   augmenting the agency’s established policies and procedures. In fiscal
                                                   year 2018, OPM completed software and hardware upgrades, including
                                                   replacement of core switches, network end points, and laptops. In fiscal
                                                   year 2019, the agency plans to continue its focus on refreshing aged IT
                                                   infrastructure, so that its hardware components will have the proper
                                                   11
                                                     OPM, Congressional Budget Justification and Annual Performance Plan, Fiscal Year
                                                   2019, (Washington, D.C.: February 2018).
                                                   12
                                                     OPM: Data Breach, Hearing Before the House Committee on Oversight and
                                                   Government Reform, 114th Cong. (statement of Director of the Office of Personnel
                                                   Management Katherine Archuleta).




                                                   Page 53                                                           GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




vendor support. OPM developed multiple documents related to the
planning of this modernization effort, including a modernization schedule,
and its fiscal year 2019 budget justification.

However, the modernization plans contained in these documents did not
include details for the entire modernization effort. The milestones in these
documents, for instance, were either no longer current or only contained
milestones regarding one part of the project. While the budget justification
did outline what it planned to accomplish in fiscal years 2018 and 2019, it
did not mention the rest of the work needed to complete the infrastructure
modernization.

Similarly, the OIG has reported concerns regarding the agency’s plans to
modernize its infrastructure. 13 Most recently, in June 2018, the OIG
reported that OPM was generally continuing in the right direction toward
modernizing its IT environment, but the OIG had concerns with the
agency’s plan for modernization and its overall approach to IT
modernization. For example, the OIG was concerned that OPM’s
planning documents did not identify the full scope of the modernization
effort or contain cost estimates for the individual initiatives or the effort as
a whole. The OIG planned to monitor and continue to report on the
agency’s progress in modernizing its infrastructure.

OPM anticipates realizing both financial and nonfinancial benefits with the
modernization of its infrastructure. For example, as a part of its overall
infrastructure modernization, the agency avoided approximately $16
million in costs as part of its data center consolidation efforts for fiscal
year 2018. The agency also expects that cybersecurity and operational
risks associated with end of life hardware will be reduced. To that end,
the agency stated that remediating end of life hardware also should allow
OPM the ability to address identified security vulnerabilities and avoid
operational downtime, as support is more readily available.




13
  See, for example: OPM Office of the Inspector General, Office of Audits, Management
Advisory: U.S. Office of Personnel Management’s Fiscal Year 2017 IT Modernization
Expenditure Plan, Report Number 4A-CI-00-18-022 (Feb. 15, 2018) and Final
Management Advisory: U.S. Office of Personnel Management’s Fiscal Year 2018 IT
Modernization Expenditure Plan, Report Number 4A-CI-00-18-044 (June 20, 2018).




Page 54                                                           GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 9                                           The Small Business Administration’s (SBA) System 9 is a system that,
                                                   according to the agency, provides identification, authentication, and
Small Business Administration
                                                   authorization services 14 for several of the agency’s applications.
Reported number of users: Approximately
274,000                                            According to the agency, the system was developed by SBA and
Initial year of implementation: 2002               originally implemented in 2002. Agency officials stated that System 9’s
System hardware under warranty? No                 hardware and software are no longer supported by the associated
Software vendor supported? No                      vendors. Consequently, according to the agency, it is paying for extended
Operating system(s) supported? No                  support contracts that have increased operating costs for the system.
Legacy programming language(s) used?
Yes
                                                   Further, agency officials stated that the system resides on a platform that
System criticality (as determined by
                                                   is scheduled to be decommissioned within the next year. In addition, the
agency): High                                      system is coded using a programing language that the agency considers
System security risk (as determined by             to be a legacy programming language (among others).
agency): Moderately high
Reported annual operating costs:
$62,000
                                                   The agency’s documented modernization plan includes milestones to
Reported annual labor costs: $214,600              complete the modernization and plans for the disposition of the legacy
Reported cost of modernization:                    system following system modernization; however, the plan does not
$750,000                                           include a description of the work necessary to complete the
Potential cost savings: None                       modernization. However, agency officials stated that it intends to replace
Other benefits: Increased security and             the system’s functionality with login.gov. Login.gov was developed and is
stability of the system
                                                   maintained by the General Services Administration as a single sign-on
Status of modernization plans: Agency
has a documented modernization plan that           trusted identity platform. 15 Login.gov provides identification and
includes milestones to complete the                authentication for applications and is intended to offer the public secure
modernization and plans for the disposition
of the legacy system following system              and private online access to participating government programs.
modernization; however, it does not include        However, according to the agency, since login.gov does not provide
a description of the work necessary to
complete the modernization
                                                   authorization controls, SBA intends to develop additional software to
Source: GAO analysis of agency documentation and   provide authorization controls beginning in March 2019.
interviews. | GAO-19-471




                                                   14
                                                     Agencies design and implement access controls to provide assurance that access to
                                                   computer resources (data, equipment, and facilities) is reasonable and restricted to
                                                   authorized individuals. These controls protect computer resources from unauthorized use,
                                                   modification, disclosure, and loss by limiting, preventing or detecting inappropriate access
                                                   to them. Two of these control areas are identification and authentication, and
                                                   authorization. Identification and authentication controls allow a computer system to identify
                                                   and authenticate different users so that activities on the system can be linked to specific
                                                   individuals. Authorization is the process of granting or denying access rights and
                                                   permissions to a protected resource, such as a network, a system, an application, a
                                                   function, or a file.
                                                   15
                                                     Single sign-on reduces the burden of multiple passwords. It is intended to increase
                                                   security of the data and systems and compliance with federal information technology
                                                   policies and best practices.




                                                   Page 55                                                               GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




According to the agency, it does not anticipate any cost benefits from
modernizing System 9. However, the agency expects that the security
and stability of the system will increase.




Page 56                                                 GAO-19-471 Legacy IT
                                                   Appendix III: Profiles of the 10 Most Critical
                                                   Legacy Systems in Need of Modernization




System 10                                          The Social Security Administration’s (SSA) System 10 supports the
                                                   provision of particular Social Security benefits to eligible people.
Social Security Administration                     Currently, SSA collects detailed information from the recipients in person,
Reported number of users: Over 30,000              by telephone, and via the internet on multiple platforms (e.g., desktops
Initial year of implementation: 1974               and hand-held devices), and from internal and external interface
System hardware under warranty? Yes                methods. System 10 is comprised of many applications that collect
Software vendor supported? Yes                     information, make payments, and communicate with SSA’s clients.
Operating system(s) supported? Yes
Legacy programming language(s) used?               According to SSA’s October 2017 information technology modernization
Yes
                                                   plan, the agency needed to modernize its core systems, including System
System criticality (as determined by
agency): High                                      10, because of complications related to their age and original system
System security risk (as determined by             design. 16 SSA’s modernization plan indicates that, since implementation,
agency): Moderate                                  these systems had been subjected to constant modifications to
Reported annual operating costs: $139.2
        a
                                                   incorporate changes in legislation, regulations, and policy. Through the
million
                                                   years, new technologies and capabilities had been integrated into the
Reported annual labor costs: $6.7 million
Reported cost of modernization: $24.6
                                                   core systems and delivering new capabilities was becoming exorbitantly
million (from fiscal year 2017 to 2022)            expensive.
Potential cost savings: Approximately $4
million per year from fiscal year 2019             Further, most of the agency’s systems, including System 10, are
through fiscal year 2027a
Other benefits: Better access to beneficiary
                                                   generally unconnected to each other, creating functional silos servicing
data, faster and more efficient claim              independent lines of business. According to the agency, navigating these
processing, reduced need for manual data           systems is challenging, and copying beneficiary data from system to
entry, and lower number of improper
payments, among others                             system can result in data becoming out of sync.
Status of modernization plans: Agency
has documented plans that contain                  According to the agency’s modernization plan, SSA intends to replace its
milestones that partially cover the
modernization effort and partially describe        core systems, including System 10, with new components and platforms,
the work necessary to modernize the                engineered for usability, interoperability, and future adaptability. Work
system; however, they do not contain plans         accomplished over several years of incremental modernization has
for the disposition of legacy system
components following system modernization          already resulted in moving a substantial portion of System 10 away from
       a
Note: The agency was unable to isolate the         old technologies. For instance, according to SSA officials in the Office of
operating costs or potential cost savings for      the Deputy Commissioner, Systems, SSA moved System 10 to a modern,
this system. The figures presented are the
costs and potential savings for all of the         relational database platform and modernized aspects of the user
systems operating in the mainframe                 interface. 17 According to an SSA 5-year modernization roadmap, the
environment.
Source: GAO analysis of agency documentation and
                                                   agency is currently working to modernize and create web services as a
interviews. | GAO-19-471                           part of the effort to consolidate SSA’s initial claims processes; however,
                                                   the roadmap does not offer specific information about these efforts.

                                                   16
                                                    Social Security Administration, IT Modernization: A Business and IT Journey (Baltimore,
                                                   MD: Oct. 2017).
                                                   17
                                                     A relational database is a system that allows users to store data in and retrieve data
                                                   from linked databases that are perceived as a collection of relations or tables.




                                                   Page 57                                                               GAO-19-471 Legacy IT
Appendix III: Profiles of the 10 Most Critical
Legacy Systems in Need of Modernization




As for its modernization planning efforts, SSA’s plans include overall
modernization goals, a high-level overview of the planned system
architecture, milestones for fiscal year 2018, and a description of the work
that it had planned to accomplish in fiscal year 2018. However, the plans
do not include either System 10-specific milestones or a description of the
work necessary to modernize the legacy system beyond fiscal year 2018.
Further, the document does not include plans for the disposition of the
legacy system after modernization. According to officials in the Office of
the Deputy Commissioner, Systems, the agency will update the planning
documentation and make further decisions as the modernization effort
progresses.

SSA expects that modernizing System 10 will result in cost savings in
addition to many other benefits. For instance, the agency expects that it
will be able to save approximately $38 million from modernizing System
10 and other systems running in the agency’s mainframe environment. In
addition, increased staff access to benefit recipients’ data will enable staff
to review medical evidence faster and process claims more accurately,
among other things. According to the agency’s modernization plan, the
improvements to the system should improve productivity and service to
the public, as well as reduce the number of improper payments due to
technician error.




Page 58                                                    GAO-19-471 Legacy IT
Appendix IV: Comments from the
                        Appendix IV: Comments from the Department
                        of Education



Department of Education
         Error! No text of specified style in document.




                        Page 59                                     GAO-19-471 Legacy IT
Appendix V: Comments from the Department
             Appendix V: Comments from the Department
             of Health and Human Services



of Health and Human Services




             Page 60                                    GAO-19-471 Legacy IT
Appendix V: Comments from the Department
of Health and Human Services




Page 61                                    GAO-19-471 Legacy IT
Appendix VI: Comments from the
             Appendix VI: Comments from the Department
             of Homeland Security



Department of Homeland Security




             Page 62                                     GAO-19-471 Legacy IT
Appendix VI: Comments from the Department
of Homeland Security




Page 63                                     GAO-19-471 Legacy IT
Appendix VII: Comments from the Internal
              Appendix VII: Comments from the Internal
              Revenue Service



Revenue Service




              Page 64                                    GAO-19-471 Legacy IT
Appendix VII: Comments from the Internal
Revenue Service




Page 65                                    GAO-19-471 Legacy IT
Appendix VII: Comments from the Internal
Revenue Service




Page 66                                    GAO-19-471 Legacy IT
Appendix VIII: Comments from the Office of
          Appendix VIII: Comments from the Office of Personnel
          Management



Personnel Management
          Error! No text of specified style in document.




                         Page 67                                 GAO-19-471 Legacy IT
Appendix IX: Comments from the Small
         Appendix IX: Comments from the Small Business
         Administration



Business Administration
         Error! No text of specified style in document.




                        Page 68                           GAO-19-471 Legacy IT
Appendix X: Comments from the Social
                        Appendix X: Comments from the Social
                        Security Administration



Security Administration
         Error! No text of specified style in document.




                        Page 69                                GAO-19-471 Legacy IT
Appendix XI: Comments from the
                        Appendix XI: Comments from the Department
                        of Housing and Urban Development



Department of Housing and Urban
Development
         Error! No text of specified style in document.




                        Page 70                                     GAO-19-471 Legacy IT
Appendix XII: Comments from the U.S.
                        Appendix XII: Comments from the U.S. Agency
                        for International Development



Agency for International Development
         Error! No text of specified style in document.




                        Page 71                                       GAO-19-471 Legacy IT
Appendix XIII: GAO Contact and Staff
                  Appendix XIII: GAO Contact and Staff
                  Acknowledgments



Acknowledgments   Error! No text of specified style in document.




                  Carol C. Harris, (202) 512-4456 or harriscc@gao.gov
GAO Contact
                  In addition to the contact name above, the following staff made key
Staff             contributions to this report: Dave Powner (Director), Kevin Walsh
Acknowledgments   (Assistant Director), Jessica Waselkow (Assistant Director), Chris
                  Businsky, Rebecca Eyler, Angel Ip, and Meredith Raymond.




(103413)
                  Page 72                                                 GAO-19-471 Legacy IT
                         The Government Accountability Office, the audit, evaluation, and investigative
GAO’s Mission            arm of Congress, exists to support Congress in meeting its constitutional
                         responsibilities and to help improve the performance and accountability of the
                         federal government for the American people. GAO examines the use of public
                         funds; evaluates federal programs and policies; and provides analyses,
                         recommendations, and other assistance to help Congress make informed
                         oversight, policy, and funding decisions. GAO’s commitment to good government
                         is reflected in its core values of accountability, integrity, and reliability.

                         The fastest and easiest way to obtain copies of GAO documents at no cost is
Obtaining Copies of      through GAO’s website (https://www.gao.gov). Each weekday afternoon, GAO
GAO Reports and          posts on its website newly released reports, testimony, and correspondence. To
                         have GAO e-mail you a list of newly posted products, go to https://www.gao.gov
Testimony                and select “E-mail Updates.”

Order by Phone           The price of each GAO publication reflects GAO’s actual cost of production and
                         distribution and depends on the number of pages in the publication and whether
                         the publication is printed in color or black and white. Pricing and ordering
                         information is posted on GAO’s website, https://www.gao.gov/ordering.htm.
                         Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
                         TDD (202) 512-2537.
                         Orders may be paid for using American Express, Discover Card, MasterCard,
                         Visa, check, or money order. Call for additional information.

                         Connect with GAO on Facebook, Flickr, Twitter, and YouTube.
Connect with GAO         Subscribe to our RSS Feeds or E-mail Updates. Listen to our Podcasts.
                         Visit GAO on the web at https://www.gao.gov.

                         Contact FraudNet:
To Report Fraud,
                         Website: https://www.gao.gov/fraudnet/fraudnet.htm
Waste, and Abuse in
                         Automated answering system: (800) 424-5454 or (202) 512-7700
Federal Programs
                         Orice Williams Brown, Managing Director, WilliamsO@gao.gov, (202) 512-4400,
Congressional            U.S. Government Accountability Office, 441 G Street NW, Room 7125,
Relations                Washington, DC 20548

                         Chuck Young, Managing Director, youngc1@gao.gov, (202) 512-4800
Public Affairs           U.S. Government Accountability Office, 441 G Street NW, Room 7149
                         Washington, DC 20548

                         James-Christian Blockwood, Managing Director, spel@gao.gov, (202) 512-4707
Strategic Planning and   U.S. Government Accountability Office, 441 G Street NW, Room 7814,
External Liaison         Washington, DC 20548




                            Please Print on Recycled Paper.