                          United States General Accounting Office

GAO                       Testimony
                          Before the Subcommittee on Government Management,
                          Information and Technology, Committee on Government
                          Reform, and the Subcommittee on Technology, Committee
                          on Science, House of Representatives

For Release on Delivery
Expected at
10 a.m.
                          YEAR 2000 COMPUTING
Friday,
October 29, 1999          CHALLENGE

                          Federal Business
                          Continuity and
                          Contingency Plans and Day
                          One Strategies
                          Statement of Joel C. Willemssen
                          Director, Civil Agencies Information Systems
                          Accounting and Information Management Division




GAO/T-AIMD-00-40
             Mr. Chairman, Ms. Chairwoman, and Members of the Subcommittees:

             Thank you for inviting us to participate in today’s hearing on the status of
             agencies’ business continuity and contingency plans and Day One
             strategies. The public faces the risk that critical services provided by the
             government and the private sector could be disrupted by the Year 2000
             computing problem. Financial transactions could be delayed, flights
             grounded, power lost, and national defense affected. Moreover, America’s
             infrastructures are a complex array of public and private enterprises with
             many interdependencies at all levels. These many interdependencies
             among governments and within key economic sectors could cause a single
             failure to have adverse repercussions in other sectors.

             The risk to government operations due to these many potential points of
             failure can be mitigated by the development of effective business
             continuity and contingency plans. In addition, Day One strategies—
             developed either as part of business continuity and contingency plans or
             separately—can help agencies manage the risks of the rollover period
             during late December 1999 and early January 2000.

             As requested, after a brief background discussion, today I will (1) discuss
             the state of the government’s business continuity and contingency planning
             and (2) describe the status of Day One strategies.



Background   Because of its urgent nature and the potentially devastating impact it could
             have on critical government operations, in February 1997 we designated
             the Year 2000 problem a high-risk area for the federal government.1 We
             have also issued guidance to help organizations successfully address the
             issue.2 Two of our publications—on business continuity and contingency



             1
              High-Risk Series: Information Management and Technology (GAO/HR-97-9, February
             1997).
             2
              Year 2000 Computing Crisis: An Assessment Guide (GAO/AIMD-10.1.14, issued as an
             exposure draft in February 1997 and in final form in September 1997); Year 2000
             Computing Crisis: Business Continuity and Contingency Planning (GAO/AIMD-10.1.19,
             issued as an exposure draft in March 1998 and in final form in August 1998); Year 2000
             Computing Crisis: A Testing Guide (GAO/AIMD-10.1.21, issued as an exposure draft in
             June 1998 and in final form in November 1998); and Year 2000 Computing Challenge: Day
             One Planning and Operations Guide (GAO/AIMD-10.1.22, issued as a discussion draft in
             September 1999 and in final form in October 1999).




             Page 1                                                               GAO/T-AIMD-00-40
planing and on Day One planning and operations—provide guidance on the
subject of this hearing.

Our business continuity and contingency guide describes the tasks needed
to ensure the continuity of agency operations in the event of Year 2000-
induced disruptions. The Day One guide provides a conceptual framework
for developing a Day One strategy and reducing the risk of adverse Year
2000 impact on agency operations during late December 1999 and early
January 2000.

Business continuity and contingency plans are essential. Without such
plans, when failures occur, agencies will not have well-defined responses
and may not have enough time to develop and test alternatives. Federal
agencies depend on data provided by their business partners as well as on
services provided by the public infrastructure (e.g., power, water,
transportation, and voice and data telecommunications). One weak link
anywhere in the chain of critical dependencies can cause major disruptions
to business operations. Given these interdependencies, it is imperative that
contingency plans be developed for all critical core business processes and
supporting systems, regardless of whether these systems are owned by the
agency. Accordingly, in April 1998 we recommended that the President’s
Council on Year 2000 Conversion require agencies to develop contingency
plans for all critical core business processes.3

Since 1998, the federal government has improved its approach to business
continuity and contingency planning. The Office of Management and
Budget (OMB) has clarified its contingency plan instructions and, along
with the Chief Information Officers Council, has adopted our business
continuity and contingency planning guide for federal use. In addition, on
January 26, 1999, OMB called on federal agencies to identify and report on
the high-level core business functions that are to be addressed in their
business continuity and contingency plans, as well as to provide key
milestones for development and testing of such plans in their February
1999 quarterly reports. In addition, on May 13, OMB required agencies to
submit high-level versions of these plans by June 15.




3
Year 2000 Computing Crisis: Potential for Widespread Disruption Calls for Strong
Leadership and Partnerships (GAO/AIMD-98-85, April 30, 1998).




Page 2                                                              GAO/T-AIMD-00-40
                       As noted in our business continuity and contingency planning guide, a key
                       element of such a plan is the development of a zero day or Day One risk
                       reduction strategy. In testimony on January 20, 1999, we noted that the
                       Social Security Administration had developed a Day One strategy and
                       suggested that OMB consider requiring other agencies to develop such a
                       plan.4 In its September 1999 quarterly report, OMB subsequently required
                       agencies to submit Day One strategies to OMB by October 15, 1999, as well
                       as updated high-level business continuity and contingency plans.



While Work Remains,    Although more work remains, agency business continuity and contingency
                       planning has evolved and improved since 1998. In March 1998, we testified
Agency Business        that several agencies reported that they planned to develop contingency
Continuity and         plans only if they fell behind schedule in completing their Year 2000 fixes.5
                       In June 1998, we testified that only four agencies had reported that they
Contingency Planning   had drafted contingency plans for their core business functions.6 By
Has Improved           contrast, in January 1999, we testified that many agencies had reported that
                       they had completed or were drafting business continuity and contingency
                       plans while others were in the early stages of such planning.7 Finally, as we
                       testified in August, according to an OMB official, all of the major
                       departments and agencies had submitted high-level business continuity and
                       contingency plans in response to OMB’s May 13, 1999, memorandum.8

                       With respect to OMB’s latest request for high-level plans, the 24 major
                       departments and agencies and the U.S. Postal Service9 have submitted
                       updated business continuity and contingency plans. However, while the
                       Department of the Treasury and the General Services Administration


                       4
                       Year 2000 Computing Crisis: Readiness Improving, But Much Work Remains to Avoid
                       Major Disruptions (GAO/T-AIMD-99-50, January 20, 1999).
                       5
                       Year 2000 Computing Crisis: Strong Leadership and Effective Public/Private
                       Cooperation Needed to Avoid Major Disruptions (GAO/T-AIMD-98-101, March 18, 1998).
                       6
                       Year 2000 Computing Crisis: Actions Must Be Taken Now to Address Slow Pace of
                       Federal Progress (GAO/T-AIMD-98-205, June 10, 1998).
                       7
                       GAO/T-AIMD-99-50, January 20, 1999.
                       8
                       Year 2000 Computing Challenge: Important Progress Made, Yet Much Work Remains to
                       Ensure Delivery of Critical Services (GAO/T-AIMD-99-266, August 13, 1999).
                       9
                        With respect to our analysis of high-level plans and the Day One Strategies, the term
                       agencies will hereafter include the Postal Service.




                       Page 3                                                                    GAO/T-AIMD-00-40
reported that they had provided their plans to OMB, we did not receive
these plans in time to include them in our analysis and, therefore, we
analyzed 23 submissions.

While OMB’s May 1999 memorandum directed agencies to describe their
overall strategies and processes for ensuring the readiness of key programs
and functions across the agency, it did not detail the format or reporting
elements that the agencies were to follow. Accordingly, the plans vary
considerably in terms of format and level of detail. Some agencies, such as
the Departments of Justice and Labor described their general approach or
strategy while others, such as the Departments of Education and
Transportation, provided program or component agency specific plans that
contained more detailed information. As an example of the first type of
plan, the Social Security Administration’s high-level plan identified broad
areas of risk and general mitigation strategies and contingencies. However,
as we testified in July,10 the Social Security Administration has also
completed local contingency plans to support its core business operations,
and has obtained contingency plans for all state disability determination
services as well as developed, in conjunction with the Department of the
Treasury and the Federal Reserve, a Benefits Payment Delivery Y2K
Contingency Plan. In contrast, the Department of Education provided OMB
with its detailed contingency plans for its core business processes and their
supporting systems.

In their high-level plans, some agencies provided details of the types of
contingencies that could be implemented in the event of a Year 2000-
induced failure. For example:

• The Social Security Administration described the risk that its field
  offices would be unable to issue certain types of payments due to Year
  2000-related problems with automated support. In this event, the Social
  Security Administration stated that it would coordinate with the
  Department of the Treasury to address the problem. Further, in the
  event that it is known by December 1999 that enterprises such as local
  banks and/or the Postal Service were not ready to make delivery of
  payments in early January, the Social Security Administration stated
  that it would consider plans to issue payments early.



10
 Social Security Administration: Update on Year 2000 and Other Key Information
Technology Initiatives (GAO/T-AIMD-99-259, July 29, 1999).




Page 4                                                            GAO/T-AIMD-00-40
• The Department of Education described the risk of a registration system
  failure at a school that prevents it from determining the title IV (student
  financial aid)11 eligibility of its students. Education’s risk
  mitigation/contingency activity if this occurs is threefold. First,
  Education stated that it will encourage schools to take steps to obtain
  registration and preregistration information before January 2000 for
  students beginning or continuing classes after January 1. Second,
  Education stated that it will encourage schools to develop other
  processes, including manual processes, for determining the enrollment
  status and eligibility of students who begin classes after January 1, 2000.
  Third, for students enrolled or preregistered in fall 1999 classes,
  Education will allow schools to package aid and credit students’
  accounts using fall 1999 enrollment or preregistration information, but
  not to disburse funds directly to students or parents. After the system is
  repaired, funds will have to be returned for any student who was
  ineligible. To implement these contingencies, Education stated that it
  would not enforce certain requirements and provided directions that a
  school is to follow (e.g., if a school makes a short-term loan to a student
  in lieu of paying a credit balance, the school may not charge the student
  interest on that loan).
• The Department of Veterans Affairs’ Veterans Health Administration’s
  contingency planning guidebook provides sample templates to be used
  as guides or models by its health care facilities. For example, to prepare
  for the potential problem that a facility would be unable to provide
  water in its inpatient wards for patients’ needs and staff infection
  control, the facility could prepare locations for bottled water and stock
  waterless soaps. In the event that a failure actually occurred and action
  was needed, an assessment of the situation could be reported to a
  facility’s command center, and bottled water centers established with
  control mechanisms.

All of the high-level plans in our review identified core business processes,
as called for in our guide. For example, the Department of Labor identified
and described seven core business functions: (1) benefits programs,
(2) national employment and/or economic conditions tracking, (3) job
training programs and employment assistance, (4) workers’ benefits,
(5) worker safety and health policy and oversight, (6) labor and
employment policy and oversight, and (7) program support.



11
     Title IV of the Higher Education Act of 1965, as amended.




Page 5                                                           GAO/T-AIMD-00-40
A key aspect of business continuity and contingency planning is validation,
which evaluates whether individual contingency plans are capable of
providing the needed level of support to the agency’s core business
processes and whether the plan can be implemented within a specified
period of time. In instances in which a full-scale test may not be feasible,
the agency may consider end-to-end testing of key plan components.
Moreover, an independent review of the plan can validate the soundness of
the proposed contingency strategy. We were able to identify 20 agencies
that discussed their validation strategies in their high-level plan. These
strategies encompassed a range of activities, including reviews, desktop
exercises, simulations, and/or quality assurance audits.

In addition to reviewing high-level plans, we have assessed and reported on
the business continuity and contingency planning of several agencies or
their component entities and have found uneven progress. Some had
instituted key processes while others had not completed key tasks. For
example:

• As we reported on October 22, the Department of Justice’s Federal
  Bureau of Investigation had made progress in its Year 2000 business
  continuity planning.12 However, because Justice had not explicitly
  required and emphasized the importance of business continuity plans,
  the bureau had started late in undertaking its planning effort and was
  faced with a compressed time frame for testing and finalizing its plans.
  In addition, as of August 1999, the bureau did not have many of the
  management controls and processes needed to effectively guide its
  planning activities. For example, the bureau had not (1) developed a
  master schedule and milestones, (2) defined all of its core business
  processes, (3) assessed the costs and benefits of alternative continuity
  strategies, or (4) planned for the testing phase of its business continuity
  planning effort. We recommended improvements to the Federal Bureau
  of Investigation’s planning activities, including that it establish and
  implement effective controls and structures for managing its business
  continuity planning. In commenting on our report, Justice indicated that
  it and the bureau had taken the first steps in implementing our
  recommendations.




12
 Year 2000 Computing Challenge: FBI Needs to Complete Business Continuity Plans
(GAO/AIMD-00-11, October 22, 1999).




Page 6                                                            GAO/T-AIMD-00-40
• In testimony last week we stated that, because of deficiencies in their
  contingency plans, the Department of State and the U.S. Agency for
  International Development lacked assurance that they could sustain
  their worldwide operations and facilities into the next century.13 For
  example, State’s business continuity and contingency plan did not
  identify and link its core business processes to its Year 2000 contingency
  plans and procedures, and the department had not yet tested its plans
  with Year 2000-specific scenarios. In the case of the U.S. Agency for
  International Development, we found that it had identified one core
  business process in its business continuity and contingency plan but did
  not identify or address other key agency functions. Moreover, the U.S.
  Agency for International Development provided little information on
  contingency planning activities for its missions, and it was unclear when
  the agency expected to complete its business continuity and
  contingency planning process.
• As we reported on October 14, the Department of Justice’s Drug
  Enforcement Administration had managed its business continuity
  planning efforts in accordance with the structures and processes
  recommended by our guide, and had made progress toward completing
  its plans.14 However, while progress had been made, the Drug
  Enforcement Administration still had many tasks to complete, with little
  time to address schedule slippages. For example, at the time of our
  review, it had not validated its business continuity strategy; defined,
  documented, or reviewed test plans; or prepared test schedules and test
  scenarios. The agency planned to complete testing of its plans by the
  end of November.
• The Internal Revenue Service’s business continuity and contingency
  plans that addressed issuing refunds and receiving paper submissions
  were inconsistent in two key areas—performance goals and mitigating
  actions—as we reported in September.15 This raised questions about
  whether these two plans provided sufficient assurance that the Internal
  Revenue Service had taken all necessary steps to reduce the impact of a
  potential Year 2000 failure. For example, neither of the plans specified


13
 Year 2000 Computing Challenge: State and USAID Need to Strengthen Business
Continuity Planning (GAO/T-AIMD-00-25, October 21, 1999).
14
 Year 2000 Computing Challenge: DEA Has Developed Plans and Established Controls for
Business Continuity Planning (GAO/AIMD-00-8, October 14, 1999).
15
 IRS’ Year 2000 Efforts: Actions Are Under Way to Help Ensure That Contingency Plans
Are Complete and Consistent (GAO/GGD-99-176, September 14, 1999).




Page 7                                                             GAO/T-AIMD-00-40
     completion dates for the mitigating actions nor did the plans specify
     which individuals would be responsible for completing those actions. In
     response to our concerns, Internal Revenue Service officials agreed to
     make changes to these two plans and to review other business
     continuity and contingency plans for consistency and accuracy.

Business continuity and contingency plans are also key to ensuring that the
government’s highest priority programs are not adversely affected by the
Year 2000 problem. In the case of some of the government’s essential
programs, not only is it important that the federal government have
effective plans but their partners (such as states) must also have such plans
in order to ensure program continuity. Accordingly, in its March 26, 1999,
memorandum designating the government’s 42 high-impact programs, such
as food stamps (OMB later added a 43rd high-impact program), each
program’s lead agency was charged with identifying to OMB the partners
integral to program delivery; taking a leadership role in convening those
partners; assuring that each partner has an adequate Year 2000 plan and, if
not, helping each partner without one; and developing a plan to ensure that
the program will operate effectively. According to OMB, such a plan might
include testing data exchanges across partners, developing complementary
business continuity and contingency plans, sharing key information on
readiness with other partners and the public, and taking other steps
necessary to ensure that the program will work.

Our reviews have shown that some high-impact programs are farther along
than others with respect to business continuity and contingency planning.
For example:

• Yesterday we testified on the contingency planning progress of the
  Department of Veterans Affairs’ two high-impact programs, benefits and
  health care.16 The Veterans Benefits Administration’s regional offices
  and Veterans Health Administration’s medical facilities have completed
  their business continuity and contingency plans but testing is
  incomplete. Only 5 of 58 Veterans Benefits Administration regional
  offices had completed testing of their business continuity and
  contingency plans (all are now required to complete testing by
  November 15). In addition, while all of the Veterans Health
  Administration’s medical facilities completed emergency power drills,


16
 Year 2000 Computing Challenge: Update on the Readiness of the Department of Veterans
Affairs (GAO/T-AIMD-00-39, October, 28, 1999).




Page 8                                                             GAO/T-AIMD-00-40
  other portions of their plans, such as the possibility of water and gas
  shortages, have not been tested.
• On October 6, we testified on the readiness status of the 10 high-impact
  state-administered federal programs, including the business continuity
  and contingency plans being developed by the states for these
  programs.17 With respect to the three such programs overseen by the
  Department of Agriculture’s Food and Nutrition Service (e.g., food
  stamps), it was unclear whether all states had adequate plans to ensure
  the continuity of these programs. Indeed, as of September 15, Food and
  Nutrition Service officials told us that only two states had submitted
  suitable contingency plans.

In the case of the Department of Health and Human Services’ Health Care
Financing Administration’s (HCFA) Medicaid program, of the 33 states and
two territories that had been reviewed by a business continuity and
contingency plan contractor, 11 were high risk, 11 were medium risk, and
13 were low risk. Regarding the five high-impact programs of the
department’s Administration for Children and Families administered by the
states (e.g., Temporary Assistance for Needy Families), business continuity
and contingency planning was one of the most common areas of concern
cited in 19 state assessment reports available as of September 27, 1999.

With respect to the Department of Labor’s Unemployment Insurance
program, a contractor rated states’ business continuity and contingency
plans from low to high in terms of their compliance with Labor’s
requirements for coverage of core business functions of benefits and tax
systems. Based on the contractor’s completed reviews, the quality of state
plans varied widely. For example, according to Labor’s contractor,
(1) 23 benefits and 14 tax plans had a low/very low degree of compliance
with Labor’s requirements and (2) 9 benefits and 5 tax plans had a high
degree of compliance with Labor’s requirements.




17
 Year 2000 Computing Challenge: Readiness of Key State-Administered Federal
Programs (GAO/T-AIMD-00-9, October 6, 1999).




Page 9                                                            GAO/T-AIMD-00-40
• In September, we reported that the Department of Agriculture’s Food
  Safety Inspection Service had not established milestones for completing
  complementary business continuity and contingency planning with its
  partners for its food safety inspection high-impact program. The food
  safety high-impact program’s partners include 25 states with approval to
  operate their own inspection programs.18
• As we testified on September 27, the Health Care Financing
  Administration (HCFA) continued to make steady progress on its
  agencywide and 29 internal business continuity and contingency plans
  for its high-impact Medicare program, but the status of contractor plans
  was unknown and the results of HCFA’s reviews of managed care
  organizations’ plans were not promising.19 With respect to its internal
  plans, HCFA had completed an agencywide business continuity and
  contingency plan, but essential validation activities remained. Regarding
  the Medicare contractors plans, HCFA’s contractor and our review both
  found that not all Medicare contractors have specified detailed
  procedures that are required for executing and testing their business
  continuity and contingency plans. In the case of the managed care
  organizations, as of September 2, 1999, HCFA had received plans from
  310 of the 383 managed care organizations. Its review of these 310 plans
  concluded that 69 percent needed major improvement, 18 percent
  needed minor improvement, and 13 percent were reasonable.

Mr. Chairman, on October 26, 1999, we briefed your Subcommittee staff on
the results of our review of 11 high-impact programs, performed at your
request. We found mixed progress on the business continuity and
contingency planning for these programs. For example, the Defense
Finance and Accounting Service reported completing the development and
testing of its business continuity plan for military retiree and annuity pay
while the Immigration and Naturalization Service had not completed or
tested the business continuity plan for its immigration program. In other
cases, such as the Postal Service’s mail delivery program, the business
continuity plans had been prepared but testing was not completed.




18
 Year 2000 Computing Challenge: Readiness of USDA High-Impact Programs Improving,
But More Action Is Needed (GAO/AIMD-99-284, September 30, 1999).
19
 Year 2000 Computing Challenge: HCFA Action Needed to Address Remaining Medicare
Issues (GAO/T-AIMD-99-299, September 27, 1999).




Page 10                                                         GAO/T-AIMD-00-40
                      One key aspect of business continuity and contingency planning that has
                      not been adequately addressed is the potential cost of implementing plans.
                      Our business continuity and contingency planning guide calls on agencies
                      to assess the costs and benefits of identified alternative contingency
                      strategies. Accordingly, we testified in June that OMB’s assessment of
                      agencies’ high-level plans should consider whether agencies provided
                      estimated business continuity and contingency plan costs and, if not, OMB
                      should require that this information be provided expeditiously so that it can
                      give the Congress information on potential future funding needs.20

                      OMB has not required agencies to provide estimates of their business
                      continuity and contingency plans. Nevertheless, in their August 1999
                      quarterly reports, we identified five agencies that specified estimated costs
                      for some aspects of their business continuity and contingency plan
                      development and/or implementation. For example, the Department of
                      Health and Human Services estimated that it would cost about $99 million
                      to implement its business continuity and contingency plans and Day One
                      strategies regardless of how the year 2000 affects its operations, but its
                      estimate does not include the cost of invoking the business continuity and
                      contingency plan. The Department of Education’s quarterly report stated
                      that, as of August 13, 1999, its business continuity and contingency plan
                      preparation costs were estimated at $3.2 million, and estimated that it
                      would cost $7.5 million in the event that all of the plans had to be
                      implemented (which it believed to be of very low probability).



Day One Planning Is   Day One strategies are necessary to reduce the risk to facilities, systems,
                      programs, and services during the weekend of the critical rollover period.
Ongoing               Accordingly, such strategies describe a wide range of complex, interrelated
                      activities and geographically distributed processes that must be executed
                      shortly before, during, and after the rollover. Earlier this month we issued a
                      Day One strategy guide.21 As shown in figure 1, the guide addresses four
                      phases supported by executive oversight: (1) initiation, (2) rollover risk
                      assessment, planning, and preparation, (3) rehearsal, and (4) execution,
                      monitoring, responding, and reporting.



                      20
                       Year 2000 Computing Challenge: Estimated Costs, Planned Uses of Emergency Funding,
                      and Future Implications (GAO/T-AIMD-99-214, June 22, 1999).
                      21
                           GAO/AIMD-10.1.22, October 1999.




                      Page 11                                                           GAO/T-AIMD-00-40
Figure 1: Year 2000 Day One Planning and Operations Structure




                                         In its September 1999 quarterly report, OMB required agencies to submit
                                         Day One strategies by October 15. OMB subsequently asked agencies to
                                         address seven elements in their plans: (1) a schedule of activities,
                                         (2) personnel on call or on duty, (3) contractor availability,
                                         (4) communications with the workforce, (5) facilities and services to
                                         support the workforce, (6) security, and (7) communications with the
                                         public. OMB also told the agencies to consider our Day One strategy
                                         guidance carefully. All agencies have submitted such draft or final
                                         strategies to OMB (either as part of their business continuity and
                                         contingency plan or as a separate document). However, while the
                                         U.S. Agency for International Development and the General Services



                                         Page 12                                                   GAO/T-AIMD-00-40
Administration reported that they had provided their plans to OMB, we did
not receive these plans in time to include them in our analysis. Therefore,
we analyzed 23 agencies’ submissions.

Our review of the agency strategies found that about 40 percent (9 of 23)
addressed all seven elements. For example, in our testimony yesterday we
noted that the Department of Veterans Affairs addressed all of OMB’s
elements.22 This department and its agencies had developed a Day One
strategy that should help the department manage risks associated with the
rollover period and better position itself to address any disruptions that
may occur. For example, the strategy included a timeline of events between
December 31 and January 1 and a personnel strategy and leave policy that
identifies key managerial and technical personnel available to support day
one operations.

With respect to specific elements, we were able to identify 15 agencies that
included a schedule of activities and 17 that addressed staffing issues. Also,
in a few cases, agencies addressed either OMB’s internal communications
element or external communication element but not both. Further, some
elements were addressed in a general manner and/or indicated that more
work needed to be completed. For example, one agency reported that it is
developing procedures to ensure its ability to identify, report, and respond
effectively to Year-2000 related events.

An important part of Day One planning is ensuring that the Day One
strategy is executable. Accordingly, the Day One plans and their key
processes and timetables should be reviewed and, if feasible, rehearsed.
Our Day One strategy review found that 19 agencies discussed rehearsing
their strategies, although some did not provide specific dates of planned or
completed rehearsals.


In summary, business continuity and contingency plans and Day One
strategies are key to managing and reducing the risks associated with the
change to the year 2000. In the area of business continuity and contingency
planning, noteworthy progress has been made since early 1998, although
more work remains. With respect to Day One strategies, while about
40 percent of agencies addressed all of OMB’s elements in their
submissions, it is clear that much more work remains.

22
     GAO/T-AIMD-00-39, October 28, 1999.




Page 13                                                       GAO/T-AIMD-00-40
                   Mr. Chairman, Ms. Chairwoman, this concludes my statement. I would be
                   happy to respond to any questions that you or other members of the
                   Subcommittees may have at this time.



Contact and        For information about this testimony, please contact Joel Willemssen at
                   (202) 512-6253 or by e-mail at willemssenj.aimd@gao.gov. Individuals
Acknowledgments    making key contributions to this testimony included Margaret Davis,
                   Mirko Dolak, Jim Houtz, and Linda Lambert.




(511781)   Leter   Page 14                                                    GAO/T-AIMD-00-40
Ordering Information

The first copy of each GAO report and testimony is free.
Additional copies are $2 each. Orders should be sent to the
following address, accompanied by a check or money order made
out to the Superintendent of Documents, when necessary, VISA and
MasterCard credit cards are accepted, also.

Orders for 100 or more copies to be mailed to a single address are
discounted 25 percent.

Orders by mail:

U.S. General Accounting Office
P.O. Box 37050
Washington, DC 20013

or visit:

Room 1100
700 4th St. NW (corner of 4th and G Sts. NW)
U.S. General Accounting Office
Washington, DC

Orders may also be placed by calling (202) 512-6000
or by using fax number (202) 512-6061, or TDD (202) 512-2537.

Each day, GAO issues a list of newly available reports and
testimony. To receive facsimile copies of the daily list or any list
from the past 30 days, please call (202) 512-6000 using a touchtone
phone. A recorded menu will provide information on how to obtain
these lists.

For information on how to access GAO reports on the INTERNET,
send an e-mail message with “info” in the body to:

info@www.gao.gov

or visit GAO’s World Wide Web Home Page at:

http://www.gao.gov
United States                       Bulk Mail
General Accounting Office      Postage & Fees Paid
Washington, D.C. 20548-0001           GAO
                                 Permit No. GI00
Official Business
Penalty for Private Use $300

Address Correction Requested