The Housing Authority of the City of Pearsall, TX, Improperly Procured and Paid Its Interim Executive Director

Published by the Department of Housing and Urban Development, Office of Inspector General on 2015-10-02.

Below is a raw (and likely hideous) rendition of the original report. (PDF)

                                                                         U.S. DEPARTMENT OF
                                                           HOUSING AND URBAN DEVELOPMENT
                                                                  OFFICE OF INSPECTOR GENERAL



                                               
                                                                        October 2, 2015
                                                                                                                        MEMORANDUM NO:
                                                                                                                             2016-FW-1801


Memorandum
TO:                          David G. Pohler
                             Director, San Antonio Office of Public Housing, 6JPH

                             //signed//
FROM:                        Gerald R. Kirkland
                             Regional Inspector General for Audit, 6AGA

SUBJECT:                     The Housing Authority of the City of Pearsall, TX, Improperly Procured and Paid
                             Its Interim Executive Director 


                                                                     INTRODUCTION

In accordance with the Office of Inspector General’s (OIG) goal to ensure the integrity and
soundness of the U.S. Department of Housing and Urban Development’s (HUD) Public and
Indian Housing programs and to follow up on weaknesses identified in another review,1 we
reviewed the Housing Authority of the City of Pearsall, TX, to determine whether it followed
Federal procurement and the State of Texas’ requirements when contracting for its interim
executive director for calendar years 2014 and 2015.

HUD Handbook 2000.06, REV-4, sets specific timeframes for management decisions on
recommended corrective actions. For each recommendation without a management decision,
please respond and provide status reports in accordance with the HUD Handbook. Please furnish
us copies of any correspondence or directives issued because of the review.

                                                               METHODOLOGY AND SCOPE

We conducted our work at the Authority’s offices located in Pearsall, TX, HUD’s Office of
Public Housing in San Antonio, TX, and OIG’s offices in San Antonio and Fort Worth, TX,
between July 24 and August 24, 2015. The limited review generally covered the Authority’s
procurement of, contract with, and payments for its interim executive director position for
calendar years 2014 and 2015. We expanded the scope as necessary to accomplish our objective.
                                                            
1
       Audit Memorandum 2015-FW-1806 issued June 11, 2015.



                                                                         Office of Audit (Region 6)
                                                          819 Taylor Street, Suite 13A09, Fort Worth, TX 76102
                                                                Phone (817) 978-9309, Fax (817) 978-9316
                                                    Visit the Office of Inspector General Web site at www.hudoig.gov.
To accomplish our objective, we reviewed the Authority’s

       Relevant board of commissioners’ meeting minutes.
       Advertisements for the executive director position placed in the local newspaper from
        February 13 to February 15, 2014, and with the Texas Housing Association from January
        23 through February 15, 2014.
       Board-approved procurement policy, dated May 23, 1996.
       Contract with its interim executive director, which the contractor and a notary signed on
        February 12, 2014.
       Audited financial statements for fiscal years ending June 30, 2013 and 2014.
       Financial information from HUD’s Public and Indian Housing Information Center system
        for fiscal years 2014 and 2015. We did not test the reliability of the electronic data as we
        used the data for only background purposes.
       Bank statements from December 1, 2013, through July 31, 2015.

We also reviewed

       Financial information provided by the Authority’s fee accountant, listing all payments
        (100 percent) to the contractor and the Authority’s allocation of contract costs among its
        programs. We traced each of the recorded payments to check payments in the
        Authority’s low-rent bank account statements.
       Relevant laws and regulations.
       The contractor’s executive director contract with another public housing agency, signed
        by the contractor and a notary on May 24, 2012.
       The contractor’s resignation letter to the Authority, dated June 10, 2015, which stated he
        resigned effective June 30, 2015.

In addition, we interviewed

       HUD’s Office of Public Housing staff,
       Current and former Authority staff and board members,
       The contractor,
       The mayor of Pearsall, TX, and
       The former counsel to the Authority.

                                        BACKGROUND

The Authority is a nonprofit government organization organized under the laws of the State of
Texas to provide housing for qualified individuals. The mayor of Pearsall, TX, appoints the five-
member board of commissioners. The board is responsible for establishing operating policies
and overseeing the interim executive director, who manages the Authority’s day-to-day
operations. The Authority had six employees and an independent contractor serving as its
interim executive director.


                                                 2
 
The Authority operates 24 U.S. Department of Agriculture rural rental housing units and 80
HUD low-rent public housing units. It also administers 118 housing choice vouchers. HUD
provided operating subsidies and Public Housing Capital Fund program funds for the
development and modernization of the Authority’s public housing developments and for
management improvements. The table below details the funding that HUD provided to the
Authority.

            HUD’s reported funding for the Authority
                    HUD program         Fiscal year 2014 Fiscal year 2015                            Total
            Low-rent operating subsidy       $ 248,355         $ 107,092                          $ 355,447
            Housing choice vouchers            326,566           340,015                              666,581
            Capital Fund program grants         84,043            88,489                              172,532
            Total                            $ 658,964         $ 535,596                          $ 1,194,560


                                                               RESULTS OF REVIEW

The Authority improperly procured its interim executive director (contractor) as it failed to
follow Federal, State, and its own requirements. The Authority also lacked support for the
reasonableness of its payments to its contractor, and it made payments to the contractor before it
awarded the contract and after the contractor resigned. These conditions occurred because no
one took responsibility to ensure that the Authority properly procured and paid for its contractor.
Instead, the board, its attorneys, and its contractor made conflicting statements concerning the
procurement and the actions taken. As a result, the Authority used $138,880 in HUD public
housing funds to pay unreasonable and ineligible contract fees.

The Authority Failed To Follow Federal Procurement Requirements
The Authority failed to follow Federal procurement requirements2 when it hired a contractor as
its interim executive director. The Authority did not advertise for a contractor, although its
December 2, 2013, board meeting minute notes said the Authority wanted its attorney “to find a
Consultant to be hired as interim Director for the Pearsall Housing Authority.” Instead, it posted
an advertisement for the position of executive director. Thus, the Authority did not properly
solicit for a contractor as it

                     Did not conduct the procurement in a manner that allowed for full and open
                      competition,
                     Did not list the selection factors for the procurement,
                     Lacked a method for evaluating the proposals received,
                     Lacked the significant history of the procurement, and
                     Failed to perform a cost analysis.



                                                            
2
       24 CFR (Code of Federal Regulations) 85.36 (b)(1), (b)(9), (c)(1), (c)(3), (d)(3), and (f)(1)

                                                                       3
 
In addition, the Authority’s actions contained the following procurement irregularities:

                     The Authority advertised the position locally the day after the contractor signed the
                      contract;
                     The board met in a closed executive session on February 12, 2014, concerning
                      appropriate actions pertaining to the position of executive director, which was 3 days
                      before the closing date of the position in the Authority’s advertisements; and
                     The board chairman signed the contract and had it notarized on February 18, 2014,
                      although the Authority could not show that the board met on February 18, 2014, or
                      voted on the contractor’s selection.

These conditions occurred because no one took responsibility to ensure that the Authority
properly procured its contractor. Instead, the Authority’s board, attorneys, and contractor made
conflicting statements concerning the procurement and the actions taken. According to the board
meeting minutes and a board member’s statement, the Authority relied on its attorney to hire the
contractor. Yet, the attorney stated he was not involved in the selection. The contractor could
not recall who asked him to fill the position and did not know who on the board formally
approved his contract. Since it did not properly procure this contract, the Authority should not
have used HUD program funds totaling $138,880 to make payments to the contractor.

The Authority Did Not Follow the State’s Open Meeting Requirements
The Authority did not follow the State’s Open Meeting Act requirements as it went into a closed
executive session during three board meetings to discuss the position of executive director. The
State’s Open Meetings Handbook3 states that “closed deliberations about the selection of an
independent contractor are not authorized.” As the board deliberated this position in executive
session, it lacked records of what transpired, including its (1) knowledge, (2) selection process,
and (3) rationale for awarding the contract.

The Authority Did Not Follow Its Procurement Requirements
The Authority did not follow its own procurement policy, which required it to follow Federal
requirements, document its procurement process, document its selection rationale, and check
references of proposed contractors. If it had checked references, it would have learned of the
contractor’s full-time position at another public housing agency. However, no one took
responsibility to follow the Authority’s requirements. As a result, the Authority could not show
that it properly obtained its contract or that it obtained a contract that provided the greatest value.

The Authority Lacked Support for the Reasonableness of Its Payments to Its Contractor
The Authority could not show that the $7,000 per month salary it paid its contractor was
reasonable or prudent in accordance with Federal cost principles.4 According to Authority staff,
the contractor usually came to the Authority office once a week for about 15 to 20 minutes, and
he attended board meetings. Further, the Authority lacked reports or records to show how much
time the contractor spent on the Authority’s business. The contract required the contractor to
                                                            
3
       October 2013 revision, Part IX Closed Sessions, paragraph B.6., Section 551.074 Personnel Matters
4
       2 CFR Part 225, Appendix A, General Principles for Determining Allowable Costs - C. Basic Guidelines,
       paragraphs 1.b., 2.a., 2.b., and 2.d.

                                                               4
 
“devote his best efforts, time, skill, labor, and attention to his duties as PHA [Pearsall Housing
Authority] Interim Executive Director...” and stated the salary amount would be “prorated in
accordance with the actual period of time [the contractor] actually provides services to the PHA
as Interim Executive Director.” The contractor also had a contract with another public housing
agency to be that agency’s executive director, and his contract with that agency required him to
spend 100 percent of his time working on that agency’s business. The board chair stated he did
not know that the contractor also worked at another agency. However, the Authority’s attorney
knew of the contractor’s other employment and stated the board knew that this individual held a
full-time position at the other agency. Further, the contractor stated he informed the board of his
other position. The Authority made $119,000 in unreasonable payments to the contractor.5

The Authority Made Payments to the Contractor Before the Contract Was Awarded and
After the Contractor Resigned
In violation of Federal requirements,6 the Authority made ineligible payments to its contractor
for consulting services for the 2 months before its executed contract and for the month of July
2015, although the contractor resigned effective June 30, 2015. Two prior board members
signed the checks for December 2013, January 2014, and July 2015 consulting services. Further,
all three checks referenced the contractor’s invoice. Since it paid for services when it did not
have a contract, the Authority made $19,880 in ineligible payments with HUD program funds.7

                                                                 CONCLUSION

The Authority did not follow Federal, State, and its own procurement requirements and lacked
support to show that it made only reasonable, prudent, and necessary payments to its contractor.
It also made ineligible payments before the contract was awarded and after the contractor’s
resignation. These issues occurred because no one took responsibility to ensure that the
Authority properly procured and paid its contractor. As a result, the Authority could not show
that it properly obtained its contract or that it obtained a contract that provided the greatest value
to the Authority. Therefore, it will have to repay $138,880 to its HUD program accounts, which
will negatively impact its financial operations.

                                                               RECOMMENDATIONS

We recommend that the Director, Office of Public Housing, San Antonio, TX, require the Authority
to

1A.           Receive training on Federal procurement requirements, the State’s Open Meeting Act
              requirements, and its board of commissioners’ responsibilities.


                                                            
5
       The amount included the 17 months from contract execution to the contractor’s resignation.
6
       2 CFR Part 225, Appendix A, General Principles for Determining Allowable Costs - C. Basic Guidelines,
       paragraphs 1.b., 2.a., 2.b., and 2.d., and Appendix B, Selected Items of Cost, paragraph 31; and Consolidated
       Annual Contributions Contract, section 11.a.
7
       The Authority used U.S. Department of Agriculture funds of $1,120 to pay for the December 2013 consulting
       services.

                                                                      5
 
1B.   Repay from non-Federal funds ineligible contractor costs of $19,880 to its HUD low-rent
      ($18,900) and Housing Choice Voucher ($980) program accounts.

1C.   Repay from non-Federal funds unreasonable contractor costs of $119,000 to its HUD
      low-rent program account.

1D.   Ensure that it follows Federal, State, and its own requirements when it obtains the services
      of a new executive director.




                                               6
 
                                       APPENDIXES

Appendix A

                    SCHEDULE OF QUESTIONED COSTS

                     Recommendation            Ineligible 1/    Unnecessary2/
                         number
                        1B                           $19,880
                        1C                                           $119,000
                       Totals                        $19,880         $ 119,000


1/ Ineligible costs are costs charged to a HUD-financed or HUD-insured program or activity
   that the auditor believes are not allowable by law; contract; or Federal, State, or local policies
   or regulations.

2/ Unreasonable or unnecessary costs are those costs not generally recognized as ordinary,
   prudent, relevant, or necessary within established practices. Unreasonable costs exceed the
   costs that would be incurred by a prudent person in conducting a competitive business.




                                                 7
 
Appendix B

        AUDITEE COMMENTS AND OIG’S EVALUATION


Ref to OIG Evaluation                                                 Auditee Comments


                                                              HOUSING AUTHORITY
                                                              of the City of Pearsall


                September 29, 2015

                Gerald R. Kirkland
                Regional Inspector General for Audit
                U.S. Department of
                Housing and Urban Development

                Re:       Full Response to the Draft Audit Memorandum The Housing Authority of the City
                            of Pearsall, Texas, Improperly Procured and Paid its Interim Executive Director


                Dear Sirs;

                Enclosed please find the Board of Commissioners Approved Response to the Draft Audit
                Memorandum dated September 10, 2015 (hereafter referred to as The Audit). This Response
                is being submitted to XX. XXXXX XXXX in both Word Document and .pdf Document form.

                The current leadership of the Housing Authority of the City of Pearsall (hereafter referred to
                as The Authority) reviewed the findings of the Audit performed that the evidence presented
                to the audit team leads to the conclusion that the 2013 Board of Directors:
                       1. Did not follow Federal Procurement Requirements when seeking an individual to act
                          as an Interim Executive Director for The Authority as outlined on page 3 and 4 of
                          The Audit;
                       2. Did not follow the State's Open Meeting Requirements when adjourning to
                          executive session while discussing the selection of an Interim Director once it was
                          established that this person would be paid as an independent contractor (hereafter
                          referred to Contractor A and not an employee (referenced in The Audit on page 4);
                       3. Made payments to the Contracting Firm A for services rendered by Contractor A in
Comment 1                 the months of December 2013 and January 2014 before the contract was executed
                          in writing by both parties (The Authority and Contractor A) and in July 2015 after
                          the resignation of the Contractor A in June 2015 for services rendered by
                          Contractor B (referred to in Board Meeting notes as being appointed after the
                          resignation of Contractor A). (Referenced in The Audit on page 5).

                The current leadership of the Housing Authority of the City of Pearsall (hereafter referred to
                as The Authority) reviewed the findings of the Audit performed and is only in partial
                agreement with the statement that "the Authority Lacked Support for the Reasonableness of
                Its Payments to Its Contractor". (Reference The Audit pages 4 and 5).

               The Housing Authority does not discriminate against any person because of race, age, color, religion, sex, national origin, familial status or disability.
               Changes in our program’s nonessential policies and practices would give you an opportunity to participate in the Authority’s housing program. If you are
               an individual with disabilities abuse and require reasonable accommodations or need assistance completing this application please contact our office.

                     501 W. Medina St. * Pearsall, TX 78061                                *    (830) 334-9416               *   fax (830) 334-8335 


                                                                            8
 
Ref to OIG Evaluation                                                 Auditee Comments


                                                              HOUSING AUTHORITY
                                                              of the City of Pearsall


                The 2015-2016 Board of Commissioners agrees that the evidence presented to the audit team
Comment 2       by those persons interviewed could lead to the conclusion stated above; however, The
                Authority under the 2015-2016 Board of Directors questions both the complicity and breadth
                of knowledge of the individuals interviewed and postulates that Contractor A most likely spent
                additional time, effort and work benefitting The Authority outside of the hours Contractor A
                (and/or Contractor B) spent physically at The Authority.

                A cursory look at letters to and from the San Antonio HUD office indicate that correspondence
Comment 2       was taking place with Contractor A and Contractor B during 2014 and 2015 and that
                Contractor A and Contractor B were processing Funding Draws, Budget Submissions and
                facilitating Environmental Reviews all of which most probably occurred during time worked
                from San Antonio not Pearsall.

                The Audit contains the following Recommendations:
                          1A. [The Authority] Receive training on Federal procurement requirements, the
                          State's Open Meeting Act requirements, and its board of commissioners'
                          responsibilities.

Comment 3                        The Authority agrees with this recommendation and has already taken
                                 steps to be in compliance.

                                 1B. [The Authority] Repay from non-Federal funds ineligible contractor costs of
                                 $19,880 to its HUD low-rent ($18,900) and Housing Choice Voucher ($980)
                                 program accounts.

Comment 3                        The Authority agrees with this recommendation based upon the
                                 information presented to date.

                                 1C. [The Authority] Repay from non-Federal funds unreasonable contractor costs
                                 of $119,000 to its HUD low-rent program account.

Comment 2                        The Authority challenges the conclusion that the total amount of
                                 $119,000 (the sum total of 17 months of payments to Contract Firm A
                                 from February 2014 through June 2015) be repaid to its low-rent
                                 account.




               The Housing Authority does not discriminate against any person because of race, age, color, religion, sex, national origin, familial status or disability.
               Changes in our program’s nonessential policies and practices would give you an opportunity to participate in the Authority’s housing program. If you are
               an individual with disabilities abuse and require reasonable accommodations or need assistance completing this application please contact our office.

                     501 W. Medina St. * Pearsall, TX 78061                                *    (830) 334-9416               *   fax (830) 334-8335 




                                                                            9
 
Ref to OIG Evaluation                                                 Auditee Comments


                                                              HOUSING AUTHORITY
                                                              of the City of Pearsall


                                 1D. Ensure that it follows Federal, State, and its own requirements when it
                                 obtains the services of a new executive director.

                                 The Authority agrees with this recommendation and has already taken
Comment 3                        steps to be in compliance

                In conclusion, the current leadership of the Housing Authority of the City of Pearsall submits
                this response for your consideration and continued cooperation in seeking a full agreement on
                effective corrective actions and resolving the area of disputed issue regarding the value of
                services rendered by Contractor A for The Authority during the time frame in question as it
                appears that Contractor A did indeed perform services to The Authority during 2014 and 2015
                and staff in the San Antonio HUD Field Office was aware of said services being performed.

                If you have any questions, please do not hesitate to contact me at (830) 334-9416.

                Yours sincerely,




                Rene Chadick
                Interim Executive Director




               The Housing Authority does not discriminate against any person because of race, age, color, religion, sex, national origin, familial status or disability.
               Changes in our program’s nonessential policies and practices would give you an opportunity to participate in the Authority’s housing program. If you are
               an individual with disabilities abuse and require reasonable accommodations or need assistance completing this application please contact our office.

                     501 W. Medina St. * Pearsall, TX 78061                                *    (830) 334-9416               *   fax (830) 334-8335 




                                                                           10
 
                         OIG Evaluation of Auditee Comments

Comment 1   The Authority indicated the July 2015 payment was made for services rendered
            by “Contractor B.” We disagree. The Authority issued the July 2015 check to the
            contractor. Further, the individual the Authority referred to as “Contractor B”
            stated at the entrance conference he was not receiving compensation and his
            services were voluntary.

Comment 2   The Authority said that the contractor most likely spent additional time, effort,
            and work benefitting the Authority outside of the hours the contractor physically
            spent at the Authority. It also indicated that correspondence such as funding
            draws, budget submissions, and environmental reviews most probably occurred
            during time the contractor worked from San Antonio. We disagree. The
            Authority did not properly procure the contract and lacked support for the
            reasonableness of the $119,000 paid to the contractor.

Comment 3   The Authority agreed with recommendations 1A, 1B and 1D. We acknowledge
            the Authority’s actions, and it will need to provide proof of its compliance to
            HUD’s San Antonio Office of Public Housing.




                                            11
 
Appendix C

                                        CRITERIA

2 CFR Part 225
Cost Principles for State, Local, and Indian Tribal Governments (OMB [Office of
Management and Budget] Circular A–87)

Appendix A to Part 225—General Principles for Determining Allowable Costs
A. Purpose and Scope…
   2. Policy guides.
      a. The application of these principles is based on the fundamental premises that:
          (1) Governmental units are responsible for the efficient and effective administration
               of Federal awards through the application of sound management practices…

C. Basic Guidelines
   1. Factors affecting allowability of costs. To be allowable under Federal awards, costs must
      meet the following general criteria: 
      a. Be necessary and reasonable for proper and efficient performance and administration
         of Federal awards.
      b. Be allocable to Federal awards under the provisions of 2 CFR part 225…
      j. Be adequately documented.
   2. Reasonable costs. A cost is reasonable if, in its nature and amount, it does not exceed that
      which would be incurred by a prudent person under the circumstances prevailing at the
      time the decision was made to incur the cost. The question of reasonableness is
      particularly important when governmental units or components are predominately
      federally-funded. In determining reasonableness of a given cost, consideration shall be
      given to:
      a. Whether the cost is of a type generally recognized as ordinary and necessary for the
          operation of the governmental unit or the performance of the Federal award.
      b. The restraints or requirements imposed by such factors as: Sound business practices;
          arm’s-length bargaining; Federal, State and other laws and regulations; and, terms
          and conditions of the Federal award…
      d. Whether the individuals concerned acted with prudence in the circumstances
          considering their responsibilities to the governmental unit, its employees, the public
          at large, and the Federal Government.

Appendix B -Selected Items of Cost
31.   Pre-award costs. Pre-award costs are those incurred prior to the effective date of the
      award directly pursuant to the negotiation and in anticipation of the award where such
      costs are necessary to comply with the proposed delivery schedule or period of
      performance. Such costs are allowable only to the extent that they would have been
      allowable if incurred after the date of the award and only with the written approval of the
      awarding agency.

                                               12
 
24 CFR Part 85
Administrative Requirements for Grants and Cooperative Agreements to State, Local and
Federally Recognized Indian Tribal Governments
Subpart C - Post-Award Requirements
Financial Administration
Subsection 85.20 Standards for financial management systems
(b) The financial management systems of other grantees and subgrantees must meet the
    following standards:
…
    (3) Internal control. Effective control and accountability must be maintained for all grant
         and subgrant cash, real and personal property, and other assets. Grantees and
         subgrantees must adequately safeguard all such property and must assure that it is used
         solely for authorized purposes…
    (5) Allowable cost. Applicable OMB cost principles, agency program regulations, and the
         terms of grant and subgrant agreements will be followed in determining the
         reasonableness, allowability, and allocability of costs.
    (6) Source documentation. Accounting records must be supported by such source
         documentation as cancelled checks, paid bills, payrolls, time and attendance records,
         contract and subgrant award documents, etc.

Changes, Property and Subawards
Subsection 85.36 Procurement
(b) Procurement standards
    (1) Grantees and subgrantees will use their own procurement procedures which reflect
        applicable State and local laws and regulations, provided that the procurements conform
        to applicable Federal law and the standards identified in this section…
    (9) Grantees and subgrantees will maintain records sufficient to detail the significant history
        of a procurement. These records will include, but are not necessarily limited to the
        following: rationale for the method of procurement, selection of contract type,
        contractor selection or rejection, and the basis for the contract price…
(c) Competition
    (1) All procurement transactions will be conducted in a manner providing full and open
        competition consistent with the standards of §85.36. Some of the situations considered
        to be restrictive of competition include but are not limited to:
           (i) Placing unreasonable requirements on firms in order for them to qualify to do
                 business,
           (ii) Requiring unnecessary experience and excessive bonding,
           (iii) Noncompetitive pricing practices between firms or between affiliated
                 companies,
           (iv) Noncompetitive awards to consultants that are on retainer contracts,
           (v) Organizational conflicts of interest,
           (vi) Specifying only a brand name product instead of allowing an equal product to
                 be offered and describing the performance of other relevant requirements of the
                 procurement, and
           (vii) Any arbitrary action in the procurement process…
    (3) Grantees will have written selection procedures for procurement transactions.

                                                13
 
           (i)    Incorporate a clear and accurate description of the technical requirements for the
                  material, product, or service to be procured…
           (ii) Identify all requirements which the offerors must fulfill and all other factors to
                  be used in evaluating bids or proposals…
(d) Methods of procurement to be followed…
    (3) Procurement by competitive proposals. The technique of competitive proposals is
        normally conducted with more than one source submitting an offer, and either a fixed-
        price or cost-reimbursement type contract is awarded. It is generally used when
        conditions are not appropriate for the use of sealed bids. If this method is used, the
        following requirements apply:
           (i) Requests for proposals will be publicized and identify all evaluation factors and
                  their relative importance. Any response to publicized requests for proposals
                  shall be honored to the maximum extent practical;
           (ii) Proposals will be solicited from an adequate number of qualified sources;
           (iii) Grantees and subgrantees will have a method for conducting technical
                  evaluations of the proposals received and for selecting awardees;
           (iv) Awards will be made to the responsible firm whose proposal is most
                  advantageous to the program, with price and other factors considered…
(f) Contract cost and price
    (1) Grantees and subgrantees must perform a cost or price analysis in connection with every
        procurement action including contract modifications. The method and degree of
        analysis is dependent on the facts surrounding the particular procurement situation, but
        as a starting point, grantees must make independent estimates before receiving bids or
        proposals. A cost analysis must be performed when the offeror is required to submit the
        elements of his estimated cost, e.g., under professional, consulting, and architectural
        engineering services contracts. A cost analysis will be necessary when adequate price
        competition is lacking, and for sole source procurements, including contract
        modifications or change orders, unless price reasonableness can be established on the
        basis of a catalog or market price of a commercial product sold in substantial quantities
        to the general public or based on prices set by law or regulation. A price analysis will be
        used in all other instances to determine the reasonableness of the proposed contract
        price.

Consolidated Annual Contributions Contract
11. Use of Program Receipts
    a. The HA [housing agency] must use program receipts to provide decent, safe, and sanitary
       housing for eligible families in compliance with the U.S. Housing Act of 1937 and all
       HUD requirements. Program receipts may only be used to pay program expenditures.

Texas Open Meetings Handbook
Part VII. Notice Requirements
E. Emergency Meetings: Providing and Supplementing Notice
   Special rules allow for posting notice of emergency meetings and for supplementing a posted
   notice with emergency items. These rules affect the timing and content of the notice but not
   its physical location. Section 551.045 provides:


                                                14
 
      (a) In an emergency or when there is an urgent public necessity, the notice of a meeting or
          the supplemental notice of a subject added as an item to the agenda for a meeting for
          which notice has been posted in accordance with this subchapter is sufficient if it is
          posted for at least two hours before the meeting is convened.
      (b) An emergency or an urgent public necessity exists only if immediate action is required
          of a governmental body because of:
          (1) an imminent threat to public health and safety; or
          (2) a reasonably unforeseeable situation.
      (c) The governmental body shall clearly identify the emergency or urgent public necessity
          in the notice or supplemental notice under this section.
      (d) A person who is designated or authorized to post notice of a meeting by a
          governmental body under this subchapter shall post the notice taking at face value the
          governmental body’s stated reason for the emergency or urgent public necessity…
The public notice of an emergency meeting must be posted at least two hours before the meeting
is scheduled to begin…

Part IX. Closed Sessions
B. Provisions Authorizing Deliberations in Closed Session
       6. Section 551.074. Personnel Matters
       (b) Closed Meetings authorized by Section 551.074 may deal only with officers and
           employees of the governmental body; closed deliberations about the selection of an
           independent contractor are not authorized.




                                               15