Office of Audit, Region 6         Audit Report Number: 2017-FW-1001
Fort Worth, TX                                     December 12, 2016
To:            Regenia Hawkins, Director, Office of Public Housing, 6APH

               //signed//
From:          Martin D. Herrera, Acting Regional Inspector General for Audit, 6AGA
Subject:       The Lubbock Housing Authority, Lubbock, TX, Had Weaknesses in Managing Its
               Capital Fund Program Operations


Attached is the U.S. Department of Housing and Urban Development (HUD), Office of Inspector
General’s (OIG) final results of our review of the Lubbock Housing Authority’s Public Housing
Capital Fund program.
HUD Handbook 2000.06, REV-4, sets specific timeframes for management decisions on
recommended corrective actions. For each recommendation without a management decision,
please respond and provide status reports in accordance with the HUD Handbook. Please furnish
us copies of any correspondence or directives issued because of the audit.
The Inspector General Act, Title 5 United States Code, section 8M, requires that OIG post its
publicly available reports on the OIG Web site. Accordingly, this report will be posted at
http://www.hudoig.gov.
If you have any questions or comments about this report, please do not hesitate to call me at
(817) 978-9309.
                    Audit Report Number: 2017-FW-1001
                    Date: December 12, 2016

                    The Lubbock Housing Authority, Lubbock, TX, Had Weaknesses in
                    Managing Its Capital Fund Program Operations



Highlights

What We Audited and Why
We audited the Lubbock Housing Authority’s Public Housing Capital Fund program as part of
our regional audit plan. Our objective was to determine whether the Authority properly
implemented its U.S. Department of Housing and Urban Development (HUD) Capital Fund
program.

What We Found
The Authority generally implemented its Capital Fund program in compliance with HUD
requirements and undertook work consistent with its annual and 5-year plans. However, it could
improve the management of its Capital Fund operations. While the Authority’s records provided
general support for its procurements, its files contained deficiencies. In addition, the Authority
did not have adequate competition for many of its procurements, and its contractors did not
always pay the required minimum Davis-Bacon Act wages. Further, the Authority improperly
used capital funds instead of insurance proceeds to replace two roofs, and it did not appropriately
hold tenants accountable for their damage. These conditions existed because the Authority had
significant turnover of procurement managers during the scope under review, causing
inconsistency in its operations, and it did not fully understand or apply procurement
requirements. As a result, it could not always fully support that it entered into fair and
reasonable contracts, and it could not assure HUD that it operated its program effectively and
efficiently.

What We Recommend
We recommend that the Director of HUD’s Fort Worth Office of Public Housing require the
Authority to implement stronger controls to ensure consistency in its Capital Fund program and
increase competition for its procurements, resolve $38,232 in questioned costs, and hold its
tenants accountable for damages they cause to units.
Table of Contents
Background and Objective......................................................................................3

Results of Audit ........................................................................................................4
         Finding: The Authority Had Weaknesses in Managing Its Capital Fund Program
         Operations ......................................................................................................................... 4

Scope and Methodology .........................................................................................10

Internal Controls ....................................................................................................12

Appendixes ..............................................................................................................13
         A. Schedule of Questioned Costs and Funds To Be Put to Better Use ...................... 13

         B. Auditee Comments and OIG’s Evaluation ............................................................. 14




                                                                     2
Background and Objective
The Lubbock Housing Authority, established in 1941, is a public housing agency (PHA) that
provides subsidized housing to low- and moderate-income individuals and families. The Authority
has the responsibility and authority to maintain the public housing and Section 8 Housing Choice
Voucher programs for the City of Lubbock, TX. A five-member board of commissioners, including
one resident commissioner, governs the Authority. The mayor of Lubbock appoints the
commissioners to staggered 2-year terms. The Authority owns and manages 367 public housing
units scattered throughout Lubbock, including 48 units designated for elderly housing. It also
manages 957 Section 8 housing choice vouchers. During our audit, the Authority also had two
management agreements in place to manage and operate housing programs at the Floydada and
Lockney Housing Authorities. At its April 2016 meeting, the Authority’s board voted to exercise its
60-day notice to terminate those management agreements.
The U.S. Department of Housing and Urban Development (HUD), Office of Public and Indian
Housing, Office of Capital Improvements, administers the Public Housing Capital Fund program.
Annually, HUD provides Capital Fund grants to PHAs for the development, financing, and
modernization of its public housing developments and management improvements. Each year, the
Authority must make a Capital Fund submission to HUD to receive Capital Fund grants. The key
element of the Capital Fund submission is the 5-year action plan, which describes the Authority’s 5-
year plans for its Capital Fund activities. It also includes a budget for each year in the 5-year action
plan, which details specific work planned in each year. HUD also awarded Replacement Housing
Factor (RHF) Capital Fund grants 1 to PHAs that have removed units from their inventory for the
sole purpose of developing new public housing units. For fiscal years 2014 and 2015, HUD
provided the Authority more than $1.17 million in Capital Fund grants.
The Authority used its Capital Fund grants for various activities, including roofing, interior
renovations, garage conversions, and parking lot replacements at three of its four developments.2
Between February 2014 and January 2016, the Authority entered into 40 procurement contracts
totaling $564,647 using its Capital Fund grants. In 2014, the Authority entered into a $1.43 million
construction contract using its accumulated RHF Capital Fund grants to build 12 new one-bedroom
elderly units at its Mary Myers development.
Our objective was to determine whether the Authority properly implemented its Capital Fund
program.




1
    PHAs may accumulate RHF funds for up to 5 years before starting development activities.
2
    The three developments included asset management projects 21 – Cherry Point-36 South, 22 – Behner Place-
    Mary Myers, and 23 – 96 West. The Authority’s fourth development, AMP 25 – Park Meadows II, is a low-
    income housing tax credit property. Since it did not receive capital funds, we did not include AMP 25 in this
    audit.



                                                          3
Results of Audit

Finding: The Authority Had Weaknesses in Managing Its Capital
Fund Program Operations
The Authority generally implemented its Capital Fund program in compliance with HUD
requirements and undertook work consistent with its annual and 5-year plans. However, it could
improve the management of its Capital Fund operations. While the Authority’s files provided
general support for its procurements, many contracts had only two bidders, and its contractors
did not always pay the required minimum Davis-Bacon Act wages. Further, the Authority
improperly used capital funds instead of insurance proceeds to replace roofs, and it did not
appropriately hold tenants accountable for damage they caused. These issues existed because the
Authority had three different individuals in charge of procurements during the review period, did
not fully understand requirements, and did not ensure consistency within its operations. As a
result, it could not always fully support that it entered into fair and reasonable contracts, and it
could not assure HUD that it operated its program effectively and efficiently.

The Authority Did Not Always Ensure That Its Procurements Met Requirements
The Authority did not always ensure that it met requirements when procuring contracts. HUD
required the Authority to maintain documentation detailing the significant history of its
procurements. 3 However, 40 of 41 procurement files reviewed 4 did not document every
requirement. Examples included lack of advertisements, independent cost estimates, evidence of
adequate competition, and required contract clauses. 5 In addition, the Authority’s procurement
files did not always document evaluations of submitted bids or detail how it negotiated price as
required. 6 These 40 contracts totaled $564,647 and were for general repairs. 7
In the most serious instance, the Authority executed a contract with a construction contractor for
$16,065. However, the Authority paid this contractor $44,065 for this work, 8 $28,000 more than
the contract. When questioned about the discrepancy, the Authority provided an undated and
unexecuted contract for $42,955. Further, the file contained a change order dated 3 months
before the contract, indicating that no contract was in place when the work began. The Authority
was unable to support the $28,000 in additional payments, and its records did not contain enough
information to detail the significant history of this procurement.


3
    HUD Handbook 7460.8 REV-2, section 7.2
4
    The Authority’s files showed that it procured and contracted in accordance with requirements for building 12
    new one-bedroom units at its Mary Myers development. This $1.4 million contract was the largest and most
    complex of the Authority’s 41 procurements reviewed.
5
    None of the 40 contracts contained the required Anti-Kickback Act or Contract Work Hours and Safety
    Standards Act clauses.
6
    HUD Handbook 7460.8, REV-2 section 7.2
7
    The 40 contracts ranged from $2,295 to $97,392, with an average amount of $14,116.
8
    This amount included payment of three invoices totaling the $42,955 bid amount and a $1,110 change order.




                                                          4
The Authority did not have adequate control of its change order process, as its contracting
officers approved change orders after the contractor completed the work. For instance, the
contracting officer approved five change orders for a contract after the work was completed.
Further, the Authority’s files did not contain evidence that it evaluated the need for additional
work or determine whether the work was within the scope of the contract before approving
change orders. 9 For example, in one contract, the scope of work was for a bathroom remodel;
however, the first change order was to remove front and back storm doors and an old garage door
and trim. In another instance, the Authority paid an invoice that included a change order entry,
but the file did not contain change order documentation or approvals.
These problems occurred because of the turnover in the employee in charge of procurement
during the scope of the review. The three employees had varied knowledge of procurement
practices and other work-related responsibilities causing inconsistencies in compliance. This
varied knowledge also led to misinterpretation and misapplication of requirements.

The Authority Awarded Contracts Without Adequate Competition
The Authority executed contracts that lacked adequate competition, which should generally
include solicitations from at least three bidders. 10 Specifically, the Authority executed 36 of its
41 contracts (88 percent) with 1 of 2 contractors. One contractor had 19 contracts worth
$204,186, and the other contractor had 17 contracts worth $205,932. These same two
contractors bid on 40 of 41 (98 percent) of the Authority’s procurements. In 25 (61 percent) of
the 41 procurements, the two contractors were the only bidders. Additionally, in three instances,
the Authority entered into contracts with one of the two contractors without receiving bids from
other contractors. 11
The Authority stated that the limited number of bidders was due to local contractors not having
required workers’ compensation insurance. In addition, it explained that the Authority’s
reputation after bad audits and investigations contributed to contractors not wanting to bid. The
Authority discussed its outreach to contractors and the difficulty imposed by requirements.
However, the Authority risks being unable to support that it used its capital funds to enter into
fair and reasonable contracts that were in its best interest.
The Authority’s Contractors Did Not Pay Minimum Davis-Bacon Act Wages
The Authority did not always pay the correct minimum Davis-Bacon Act wages. 12 For instance,
the Authority entered into four contracts with its two contractors to convert detached garages into
storage units. When the Authority submitted a wage-rate compliance report to HUD for
approval, HUD questioned whether the Authority used the correct U.S. Department of Labor



9
     HUD Handbook 7460.8, REV-2, section 11.4(B)
10
     HUD Handbook 7460.8, REV-2, section 5.3, and 24 CFR (Code of Federal Regulations) 85.36(c)(1)
11
     The three contracts ranged from $4,651 to $19,750.
12
     For construction contracts over $2,000, the Davis-Bacon Act requires contractors and subcontractors to pay their
     laborers no less than the local prevailing wages and fringe benefits.




                                                           5
wage determination 13 when procuring the contracts. In response, the Authority asked the two
contractors to recalculate their workers’ hours based on the correct wage determination. After
the contractors informed the Authority of the new calculations, the Authority paid one contractor
$6,535 for three contracts and another contractor $249 for one contract. 14

To support that it had corrected the mistake for one contractor, the Authority provided copies of
four contractor checks 15 with a notation showing the date on which payments were received and
signatures by the four individuals. However, the contractor explained that none of his workers
cashed the checks. Instead, the contractor stated that he paid the workers in cash and used the
checks as receipts to prove that he gave the workers cash. The workers said they received
payments in cash. HUD’s Labor Relations Desk Guide describes both paying wages in cash and
employers cashing paychecks as possible willful violation payment schemes. The contractor’s
actions in paying his employees in cash were questionable.

While the process for making restitution to one contractor and his workers for the $6,535 Davis-
Bacon Act underpayment was flawed, the calculation was correct. The $249 calculation for the
other contractor was incorrect. Specifically, the contractor did not show how many hours
individuals worked in specific classifications. Therefore, the contractor was required to pay the
workers at the highest rate of the classified positions. 16 As a result, the error totaled $840 instead
of $249, a $591 difference. 17
To correct the mistakes, the Authority should have either executed a contract amendment to
incorporate the correct wage determination or processed a change order. 18 In addition, the
Authority should have required the contractors to report the restitution on corrected certified
payroll reports. The Authority took neither of these steps, and the contractors did not provide
corrected payroll reports. HUD’s labor relations specialist also acknowledged that she probably
did not walk the Authority through the process for correcting the Davis-Bacon Act
underpayments.

In addition, the Authority did not properly review contractor payroll records 19 to ensure that they
met requirements. Contractors submitted payroll records that claimed more total hours worked
than the reported daily hours showed. In these instances, the records related to fixed-price
contracts and did not affect the Authority’s procurements. However, when one of the contractors


13
     In its request for bids, the Authority mistakenly used the “residential” wage determination, which includes the
     construction or repair of single-family houses or apartment buildings of no more than four stories in height. It
     should have used the “building” wage determination, which includes the construction of sheltered enclosures
     with walk-in access.
14
     The four procurement files included the Authority’s underpayment calculations and an email from the
     compliance coordinator to the finance director requesting to have checks cut to the contractors.
15
     The contractor provided the same check copies, but his copies included gross pay, withholding, and net pay
     calculations.
16
     HUD Handbook 1344.1, paragraph 4-2(C)(2)(f)
17
     Since this contractor did not cash the $249 check, the total amount of $840 was reported.
18
     29 CFR 1.6(f)
19
     Not all procurement files contained payroll records.




                                                            6
used a plumber, the amount paid did not meet the minimum Davis-Bacon Act pay standard. The
contractor underpaid the worker $275 for 550 hours of work under eight contracts. When the
contractor did not pay the minimum Davis-Bacon Act standard, it appeared to be because he did
not consider fringe benefits as part of the minimum standard. HUD required only spot checks of
payroll records, and the reported errors were not significant. However, the underpayments
violated Davis-Bacon Act requirements.

The Authority Used Capital Funds Instead of Insurance Proceeds
Although required to use insurance proceeds to repair damaged or destroyed property, 20 the
Authority used its capital funds to repair its units. Because of storm damage 21 at 3 of its
developments, the Authority received an insurance settlement covering combined losses
sustained at 63 units. The settlement included allotments for roof repairs at two units that also
had roofs replaced using the Authority’s capital funds. HUD considered costs for unit repairs
due to natural disaster damage that insurance reimbursed to be an ineligible cost. 22 The
Authority used Capital Funds to pay for the roof repairs and did not reimburse its Capital Fund
program with the insurance proceeds, resulting in $9,117 in ineligible costs (see table).

Table: Ineligible costs

                             Description                             Unit 1               Unit 2

          Allotted insurance proceeds for roof repair                 $7,764                   $1,922
          Capital funds used for roof replacement                      7,195                    4,450

          Ineligible costs                                             7,195                    1,922

The Authority Did Not Appear To Hold Tenants Accountable
The Authority did not hold tenants accountable for property damage but, instead, used its capital
funds to repair individual units and garages. Site visits showed abuse and damage that appeared
to have been tenant caused (see pictures). Although the Authority’s lease with tenants stated that
tenants were obligated to refrain from destroying, defacing, damaging, or removing any part of
the Authority’s property and to pay reasonable charges for repairs if they did so, the Authority
did not always enforce its lease provisions. In addition, the Authority had a standard procedure
to write off tenant accounts 90 days after the tenant moved out.




20
     Consolidated Annual Contributions Contract, Part A, Terms and Conditions, section 13(B)
21
     The Authority sustained the damages around June 2013.
22
     HUD Handbook 7485.3G, paragraph 2-20(A)(5)



                                                         7
Pictures of tenant-caused damages at asset management project 22




 Behner Place unit, 4112 36th Street                  Behner Place unit, 4109 35th Street


The Authority maintained records for tenant-caused damages. A review of 13 tenant records
with the most costly damages showed that for 10 (77 percent), the Authority wrote off the
amounts owed by the tenants after they moved out. In addition, 3 of the 10 (30 percent) had
Capital Fund repair projects initiated within 60 days of the tenants’ move-out date.
Conclusion
While the Authority generally implemented its Capital Fund program in compliance with HUD
requirements, because it did not consistently follow its policies and procedures, the Authority did
not always ensure that its procurements met HUD and other requirements. In addition, 88
percent of the Authority’s contracts went to two bidders, and those two contractors did not
always comply with Davis-Bacon Act requirements. These weaknesses put the Authority at risk
of being unable to assure HUD that it operated its program as effectively or efficiently as it
should or support that it entered into fair and reasonable contracts.




                                                 8
Recommendations
We recommend that the Director, Office of Public Housing, Fort Worth, TX, require the
Authority to

1A.       Increase its compliance with Capital Fund program requirements, including ensuring that
          its procurement files are complete, its contracts include all required clauses, it increases
          the number of contractors bidding jobs, and it properly uses insurance proceeds.
1B.       Support or repay its Capital Fund program from non-Federal funds $28,000 for work
          completed without a valid contract.
1C.       Implement effective monitoring procedures to ensure that contractors calculate certified
          payroll accurately using the current Davis-Bacon Act wage rate requirements and that
          contractors pay the certified wages to the workers.
1D.       Pay the contractors $1,115 23 in Davis-Bacon Act underpayments and ensure that they pay
          their affected workers.
1E.       Reimburse its Capital Fund program with the $9,117 of insurance proceeds for the roof
          repairs.
1F.       Enforce its lease requirements related to tenant damage to the property and to establish
          procedures to collect tenant accounts receivable before writing off the account.




23
     Computed as $840 ($249 check not cashed plus additional $591 error) and $275 additional underpayment.



                                                        9
Scope and Methodology
We conducted our audit at our offices in Fort Worth, TX, and the Authority’s offices at 1708
Crickets Avenue, Lubbock, TX, between March and August 2016. Our audit scope generally
covered the Authority’s programs for the period January 2014 through February 2016. We
expanded the scope as necessary to accomplish our audit objective.
To accomplish our audit objective, we

        •   Obtained and reviewed the Authority’s policies and procedures.
        •   Obtained and analyzed the Authority’s financial statements and general ledger,
            including comparing the budget to the general ledger.
        •   Reviewed relevant Federal and State regulations and other relevant rules and
            guidelines.
        •   Reviewed prior OIG audit work regarding the Authority.
        •   Gained a basic understanding of the Authority’s internal control environment and staff
            responsibilities.
        •   Conducted a data reliability assessment using U.S. Government Accountability Office
            (GAO) guidelines in the publication GAO-03-273G, Assessing the Reliability of
            Computer-Processed Data. Using ACL software, we determined that the data from the
            Authority’s procurement files were sufficiently reliable for determining the
            disproportionate amount of Capital Fund expenditures offered to two of the local
            contractors.
        •   Interviewed HUD and Authority staff, tenants, contractors, and contract workers.
        •   Reviewed the Authority’s and its contractors’ records regarding Davis-Bacon Act wage
            rate determinations and calculations.
        •   Identified and reviewed the disposition of 13 non-statistically selected large tenant
            accounts receivable balances or those containing a large number of tenant-damage
            entries. The tenant accounts receivable balances ranged from $485 to $5,385 and the
            number of tenant-damage incidents ranged from 1 to 33. We did not project the results
            to the entire universe, as it was the policy of the Authority to write-off the amounts.
        •   Reviewed all of the Authority’s 41 Capital Fund procurements to determine whether
            the Authority met requirements.
        •   Performed walk-throughs of the Authority’s executive, compliance, and finance
            departments to obtain an understanding functions and processes.
        •   Performed walk-throughs of six representatively non-statistically selected units 24 from
            the Authority’s 40 Capital Fund contracts to determine whether the contracted work
            was performed.




24
     We did not intend to project any results, so we did not use statistical sampling.



                                                             10
We conducted the audit in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain sufficient, appropriate
evidence to provide a reasonable basis for our findings and conclusions based on our audit
objective. We believe that the evidence obtained provides a reasonable basis for our findings
and conclusions based on our audit objective.




                                               11
Internal Controls
Internal control is a process adopted by those charged with governance and management,
designed to provide reasonable assurance about the achievement of the organization’s mission,
goals, and objective with regard to

•   Effectiveness and efficiency of operations,
•   Reliability of financial reporting, and
•   Compliance with applicable laws and regulations.
Internal controls comprise the plans, policies, methods, and procedures used to meet the
organization’s mission, goals, and objectives. Internal controls include the processes and
procedures for planning, organizing, directing, and controlling program operations as well as the
systems for measuring, reporting, and monitoring program performance.

Relevant Internal Controls
We determined that the following internal controls were relevant to our audit objective:

•   Program operations – Policies and procedures in place to reasonably ensure that the program
    met its objectives.
•   Compliance with laws and regulations – Policies and procedures in place to reasonably
    ensure that resource use was consistent with laws and regulations.
We assessed the relevant controls identified above.
A deficiency in internal control exists when the design or operation of a control does not allow
management or employees, in the normal course of performing their assigned functions, the
reasonable opportunity to prevent, detect, or correct (1) impairments to effectiveness or
efficiency of operations, (2) misstatements in financial or performance information, or (3)
violations of laws and regulations on a timely basis.
We evaluated internal controls related to the audit objective in accordance with generally
accepted government auditing standards. Our evaluation of internal controls was not designed to
provide assurance regarding the effectiveness of the internal control structure as a whole.
Accordingly, we do not express an opinion on the effectiveness of the Authority’s internal
control.




                                                  12
Appendixes

Appendix A


           Schedule of Questioned Costs and Funds To Be Put to Better Use
                Recommendation       Ineligible 1/  Unsupported 2/
                     number
                         1B                                  $28,000

                         1D                                   1,115

                         1E               $9,117

                       Totals             9,117              29,115



1/   Ineligible costs are costs charged to a HUD-financed or HUD-insured program or activity
     that the auditor believes are not allowable by law; contract; or Federal, State, or local
     policies or regulations.
2/   Unsupported costs are those costs charged to a HUD-financed or HUD-insured program
     or activity when we cannot determine eligibility at the time of the audit. Unsupported
     costs require a decision by HUD program officials. This decision, in addition to
     obtaining supporting documentation, might involve a legal interpretation or clarification
     of departmental policies and procedures.




                                              13
Appendix B
             Auditee Comments and OIG’s Evaluation



Ref to OIG
Evaluation    Auditee Comments




                               14
Ref to OIG
Evaluation




             15
Ref to OIG
Evaluation




Comment 1




Comment 2




Comment 3




             16
Ref to OIG
Evaluation




Comment 1




Comment 4




Comment 5




             17
Ref to OIG
Evaluation




Comment 6




Comment 4


Comment 5




             18
                         OIG Evaluation of Auditee Comments


Comment 1   We appreciate the Authority’s positive response to the report. We appreciate the
            Authority’s willingness to address the deficiencies cited in the report.
Comment 2   Although procedures have been developed for procurement and contract
            administration, the Authority will need to work with HUD to ensure proper
            implementation of the procedures.
Comment 3   We acknowledge that it was an error on the part of the Authority concerning the
            contract. We appreciate the Authority’s willingness to address the deficiencies
            cited in the report.
Comment 4   The Authority will need to provide HUD with documentation that it had
            reimbursed its Capital Fund program for the cost of the roofing work covered by
            insurance proceeds.
Comment 5   Although the Authority stated it took efforts to ensure tenant accountability, the
            Authority agreed that it wrote off uncollectible debts quarterly. We agree with
            cost-effective efforts to increase collections, such as the use of a debt collection
            agency, as mentioned in the Authority’s response. The Authority will need to
            work with HUD to develop and implement necessary procedures to enforce lease
            requirements and improve tenant accounts receivable collections.
Comment 6   The Authority will need to provide support to HUD that it has taken the actions
            necessary to implement the recommendations, including providing support for
            any reimbursements.




                                              19